Go to home page
Go to home page
French carp fishermen found Onondaga Lake rewarding (May 2008)
French carp fishermen found Onondaga Lake rewarding (May 2008)

Monthly report—May 2008

New Clinton conveyance contract begins
 

Highlights of the month

  • Construction continued on the Clinton Conveyances Phase I project. During the month:
    • The contractor (Delaney):
      • Continued installation of sheeting, sewers, and
      • manholes.
      • Installed the carrier pipe within the 88-inch
      • steel casing for the conveyance sewer that crosses under Onondaga Creek
      • Completed final pavement restoration on West
      • Onondaga Street and Gifford Street on the west side of Onondaga creek.

    • Sidewalk restoration continues throughout the job site. Restoration has begun on the Rescue Mission grounds.
    • The microtunneling contractor finished grouting the caisson joints for five of the caisson shafts and began microtunneling operation.

    This $15 million project involves installation of conveyance pipelines in areas near the Clinton Street RTF—not including pipelines in the Armory Square area or on the Trolley Lot.

  • Mobilization began for the Clinton Conveyances Phase 2A. Construction will primarily be focused on the area behind the MOST with installation of a pipe under the elevated railroad to the Trolley Lot:
    • Meetings were held with the Armory Square Association to bring them up to date on construction plans for this phase of the project.
    • Work to date has been on installing soil borings designed to help determine dewatering plan.
    • In the coming month, the contractor will begin installation of geotechnical monitoring instruments and install construction fencing and traffic detour signage.

  • Work activities on the Midland Phase II project during May included:
    • Addressing punch list items
    • Testing of various systems in the facility is ongoing
    • Final grading and landscaping.

  • There were no construction activities this month on the sewer separation project for CSO 050 (Parkway-Rockland). The only work remaining includes lining a section of a former combined sewer under a portion of Bissell and Temple and final milling and paving of all the affected streets. This work is now slated for summer 2008.
  • Parties to the ACJ continued meeting regularly, as agreed, to consider alternative CSO control measures regarding the remaining CSO projects of Clinton and Harbor Brook.
  • The Skimmer Boat began its 2008 season on Thursday, May 1 removing floatable debris from the Inner Harbor area. Under contract with the County, Alpha Boats Unlimited provides the boat and crew that collects trash one day a week during May; it goes to two days a week through the main recreational season of June-August.

    They complete daily logs on their collections that are submitted to the County, tracked, and compiled. Locations covered by the skimmer include the Inner Harbor, the stream channel to Onondaga Lake, and Onondaga Creek outlet at the Lake.

Progress of projects under construction

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—9/1/05 (revised) & Phase III Conveyance—5/01/07. Further milestone revisions to be determined)

Phase II construction completed

Installation of concrete in the Midland RTF disinfection tank (May 2005)
Installation of concrete in the Midland RTF disinfection tank (May 2005)

All construction work is now complete on the Midland RTF, and a pre-start up testing period is underway.

Upcoming work

Work anticipated for June 2008 includes:

  • Completion of landscaping and testing.
  • Punch list items will continue to be worked on.

Midland Phase III activities

The potential for revisions to the Phase III plans is being evaluated at this time.
 

 

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of time that construction will take place along each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 feet in diameter near West Castle Street to 4 feet in diameter near Newell Street.

Sewer separation: Rockland-Parkway area

First excavation to separate sewers—Rockland Street (Jul 2007)
First excavation to separate sewers—Rockland Street (Jul 2007)

Sewer separation for CSO basin 050—the Rockland Avenue-Parkway Drive area of Syracuse—involved installation of 4200 feet of new sewer pipeline. Construction began on July 9, 2007 at the intersection of Rockland and Hunt. The project is scheduled to be completed, including restoration of the streets, in the spring of 2008 at an estimated cost of $3.2 million.

Work underway (May 2008)

Construction to be concluded:

  • Relining a portion of the combined line under a portion of Bissell and Temple will be done this summer.
  • The streets will be fully restored.

The CSO has been converted to stormwater only and no longer discharges combined sewage and stormwater into Onondaga Creek.

Clinton Phase I conveyances

Construction continues to progress

A worker prepares grouting material for the caissons on West Street (Apr 2008)
A worker prepares grouting material for the caissons on West Street (Apr 2008)

  • Construction began at the end of July 2007 and is continuing.
  • Installation of manholes, sheeting, and sewer lines continues.
  • Completed grouting on five caissons. Micro-tunneling has begun.
  • Installed the carrier pipe within the 88-inch steel casing that was installed under Onondaga Creek. This task brought the pipe from the west side of the creek to the east side of the creek to connect west-side overflows to the future facility.
  • Completed restoration of Gifford Street and West Onondaga Street.

Upcoming work

Work anticipated for June includes:

  • Continue installation of manholes, sheeting, and sewer conveyance pipelines
  • Continuation of microtunneling operation on west side of Onondaga Creek
  • Continued surface restoration of Rescue Mission grounds.

Projects in design stage

Clinton Phase II conveyances and RTF (CSO)

(ACJ date: further amended completion date of January 1, 2013)
Clinton CSO area, noting CSO 030
Clinton CSO area, noting CSO 030

Mobilization began on Contract 2A. Contract 2A covers pipe installation under the railroad near RTF to the rear of the MOST and will take in one CSO (030). Exploratory borings were begun to help develop a dewatering plan.

Upcoming work:

  • Finish exploratory borings
  • Develop dewatering plan
  • Begin installation of geotechnical monitoring instruments
  • Install construction fencing and place signage for road detours.

RTF bids rejected

The County notified bidders on April 25, 2008 that all bids on the Clinton RTF project were rejected. Working with the ACJ parties and others, the County will pursue implementation of alternatives technologies to address the Clinton CSOs. These technologies will include green infrastructure projects.

The goal of the Clinton project is to abate eleven CSOs between Fayette and Oneida streets near downtown Syracuse.

Harbor Brook CSO abatement project (CSO)

(ACJ further amended completion date January 1, 2013)

Conveyance and RTF project activities: No activities to report this month.

The current planned project for the Harbor Brook CSOs includes two regional storage and treatment facilities, four underground floatables control facilities, upgrading one pump station, and installation of conveyance pipelines to transport CSO flow to the facilities. The two sites identified for purchase for the storage and treatment facilities are on vacant privately owned land. The County along with the other ACJ parties will be evaluating the potential use of green infrastructure in this CSO area as well as the Clinton area.

Other activities

Nothing to report at this time.

Completed projects

Hiawatha regional treatment facility (July 2001)
Hiawatha regional treatment facility (July 2001)

Projects completed since July 2002—not included in Interim Projects—are the following:

Major milestones met for CSO interim projects

The following is a summary of the projects completed under Appendix B, pages 10-12, of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date. The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility Dec 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook CSO abatement Milestone revision to Jan 1, 2013 under ACJ amendment signed Dec 14, 2006
Kirkpatrick St. pump station upgrade and force main Nov 1, 2002

Major milestones met for Metro Interim Projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements Jan 1999
Aeration system upgrade Jan 2000
Odor control and residual handling Dec 2000
Digester modifications—Phase III Improvements Dec 2000
Chemical storage Apr 2001
Digital system improvements Dec 2001

Ambient Monitoring Program

Tributary sampling

  • Biweekly tributary sampling was conducted on May 13 and 27.
  • The Program has completed six high-flow sampling events for 2008.
  • Special Onondaga Creek samples relating to dewatering activities on the Clinton project were collected at Dorwin Avenue and on Adams and Water streets on May 5 and 19.

Lake sampling

  • Lake weekly sampling events were conducted on May 12 and 28.
  • South deep sampling events were conducted on May 6 and 20.
  • Lake bacteria sampling was conducted on May 14. (Five samples are to be collected each month at each of the lake's sampling locations in both Class B and Class C sections.)

Fisheries sampling

  • The Program performed pelagic larvae sampling on May 5 and 22. This is done every 2 weeks from April through July.
  • Spring electrofishing sampling (done once in the spring and once in the fall) was conducted May 18, 19, and 20.

Contracts

May 2008
May 2008

New contracts

Legal services

Contract with The Wladis Law Firm. P.C. for general environmental legal services relating to the Federal Clean Water Act.
Contract amount: $11,673.00. Executed: 5/20/08.

Amendments to existing contracts

Legal services

Contract with Melvin & Melvin, PLLC amended for ongoing legal services relative to various ACJ projects.
Contract amendment amount: $50,000.00. Executed: 5/14/08.

Program management

Contract with CDM/C&S amended for ACJ program management for the period 1/1/08-6/30/08.
Contract amendment amount: $95,000.00. Executed: 5/7/08.

Contract with John Clare amended for ACJ project management for the period 4/21/08-5/23/08.
Contract amendment amount: $8,010.40. Executed: 5/9/08.

Harbor Brook CSO abatement

Contract with Environmental Engineering Associates (EEA) amended for additional design services, including additional surveys and geotechnical work, RTF re-designs and construction cost evaluations.
Contract amendment amount: $131,885.00. Executed: 5/20/08.

Contract with Environmental Engineering Associates (EEA) amended to reduce contract amount for work not completed.
Contract amendment amount: ($398,361.57). Executed: 5/20/08.

Clinton RTF and conveyances

Contract with Environmental Engineering Associates (EEA) amended for additional design services including archeological evaluations and construction cost analysis.
Contract amendment amount: $174,504.00. Executed: 5/20/08.

Change orders

None to report.

Legislative action

Action items of the County Legislature in May: No items.

Upcoming for June legislative session: No items.

Upcoming for June committee: No items.

Funding

Grants

State Bond Act funds

None to report.
Total payments received to date in State Bond Act funds - $110,448,961.

Federal EPA funds

None to report.
Total received to date in Federal EPA funds - $83,040,897.

Federal Army Corps of Engineers funds

None to report.
Total received to date from US Army Corps of Engineers funds - $11,468,159.

Loans

The following reimbursement payment was received from EFC during May:
Clinton Street Conveyances & RTF: Received Request in the amount of $2,678,842.04 on May 30 for total received of $2,678,842.04.

Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $161,748,040 (short term), $33,996,308 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Grants and loans applied for—not yet approved
Grants received
Financial status report


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection