Go to home page
Go to home page
Pouring new sidewalks on Parkway Drive after separating sewers (Nov 2007)
Pouring new sidewalks on Parkway Drive after separating sewers (Nov 2007)

Monthly report—December 2007

Constructon & bid activity
 

Highlights of the month

  • Work activities on the Midland Phase II project during December included:
    • Electrical contractor is completing the final power and signal connections to equipment throughout the RTF.
    • Plumbing contractor is completing the insulation and labeling of piping and tagging of valves.
    • The boilers are on and undergoing a 14-day testing period.
    • The HVAC contractor has completed installation of duct work throughout the RTF.
    • The general contractor continues field testing of the process equipment in place.
    • Painting continues in the interior of the RTF.
    • Fencing is complete.
    • Blaine Street will be opened in early January.

    As of December 31, 2007, $51,845,419 has been paid on the four prime contracts which is 95.7% of the total contract sum. The current sum of the prime contracts including approved change orders is $54,160,484.

  • Construction continued on the sewer separation project for CSO 050 (Parkway-Rockland). Work accomplished this month included:
    • Installation of 100 linear feet of storm sewer on Temple Place, two stormwater manholes, one sewer manhole, and a new catch basin.
    • All sewer laterals for the entire CSO area 050 have now been completed.
    • Pre-winter road restoration efforts were completed this month on Parkway, Shelbourne, Bellaire, and Temple that included replacement asphalt to road elevation, installation of sidewalks and handicap ramps at intersections.

    Installation of a new storm sewer on East Bissell Street is scheduled for January, weather dependent. Final milling and paving of the streets are slated for spring 2008.

  • Construction continued on the Clinton conveyances Phase I project:
    • By the end of the month, the contractor had completed installation of the 60-inch West Onondaga Street conveyance line (west) and installation of a portion of the 27-inch sewer conveyance line along Dickerson Street.
    • The contractor began installation of the 66-inch sewer conveyance.
    • Installation of sheeting along the conveyance routes also continued along with installation of manholes.
    • The micro-tunneling subcontractor continued installation of microtunneling shafts.

    This $15 million project involves installation of conveyance pipelines in areas near the Clinton Street RTF—not including pipelines in the Armory Square area or on the Trolley Lot.

  • Bid advertisement for the Clinton conveyances Phase 2A project was published November 20, 2007. The bid opening date extended to January 9, 2008. (Bids were opened on January 9, and four bids were received. The apparent low bidder is Delaney Construction at $3,578,908. This bid is under the engineer's estimate of $3,692,000. Bids are currently under review.)
  • Bids were opened on October 10 for the Clinton Street CSO abatement RTF project. Three bids were received for the general contractor, three for the electrical contract, two each for the HVAC and plumbing contracts. Bidders were asked to extend their bids again—until February 1, 2008—to allow the County more time for review. Review is currently ongoing.

Progress of projects under construction

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—9/1/05 (revised) & Phase III Conveyance—5/01/07. Further Milestone revisions requested)

Phase II construction continues

Erecting a fence adjacent to Onondaga Creek (Oct 2007)
Erecting a fence adjacent to Onondaga Creek (Oct 2007)

Work continues to complete this facility on schedule for start-up activities slated for January 2008. The boilers are on and undergoing a 14-day test period. The HVAC contractor has completed the installation of duct work and has begun testing of the HVAC system. Completion work continues on insulating and labeling the piping and tagging valves. Fencing is now completed. Interior painting continues within the RTF.

Upcoming work

Work anticipated for January 2008 includes:

  • Complete interior painting and final cleaning
  • Completion of pipe labeling, pipe insulating, and valve tagging
  • Completion of electrical work
  • Complete testing of various equipment and systems including PLCs, HVAC, and boilers.

Midland Phase III activities

  • Pre-construction meeting on building demolition contract held 12/12/07
  • Notice to proceed issued to Titan Wrecking and Environmental, LLC. of Kenmore, NY for the building demolition contract on 12/26/07. Contract involves demolition of four structures related to the Harbor Brook project and six structures related to the Midland Phase III project.
  • Work continues to prepare bid documents for re-bidding of the Phase III project.

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of time that construction will take place along each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 feet in diameter near West Castle Street to 4 feet in diameter near Newell Street.

Biosolids handling improvements

The co-generation equipment was delivered on September 7 and installed. Approval from National Grid is required before start-up.

Sewer separation: Rockland-Parkway area

Sewer separation for CSO basin 050—the Rockland Avenue-Parkway Drive area of Syracuse—involves installation of 4200 feet of new sewer pipeline. Construction began on July 9, 2007 at the intersection of Rockland and Hunt. The project is scheduled to be completed in the fall of 2008 at an estimated cost of $3.2 million.

Work underway (December 2007)

Paving Parkway Drive (Nov 2007)
Paving Parkway Drive (Nov 2007)

Construction continues to progress

  • Pipe installation work continued with 100 linear feet of storm sewer on Temple Place and a new catch basin.
  • One sewer manhole and two storm sewer manholes were also installed.
  • Completed pre-winter restoration of Parkway, Shelbourne, Bellaire, and Temple Place that included replacement of asphalt to existing road elevation, sidewalks, and green space disturbed during construction.
  • Notice sent to residents of Bissell to advise on upcoming construction—later delayed to January due to weather.

Clinton Phase I conveyances

Construction began at the end of July and is continuing.

Construction continues to progress

  • Completed installation of 60-inch West Onondaga Street conveyance sewer line excluding portion within Gifford Street
  • Installed 27-inch sewer line along Dickerson Street and continued construction of cast-in-place manhole on West Onondaga Street
  • Installation of sheeting continues and, installation of microtunneling shafts continue.
  • Completed the pipe jacking under West Street.

Working at the location of a new catch basin in West Onondaga Street (Nov 2007)
Working at the location of a new catch basin in West Onondaga Street (Nov 2007)

Upcoming work

Work anticipated for January includes:

  • Continue installation of sheeting and bracing systems along line
  • Continued installation of dewatering wells and sewer pipes
  • Begin sewer and manhole work in Gifford Street
  • Continue restoration work as weather allows.

Projects in design stage

Phase II conveyances and RTF (CSO)

(ACJ date: construction complete 2012)
Phase II Conveyance-related work RTF-related design work
Contract for 2A put out for bid on November 20, 2007. Bids to be opened January 9, 2008. (Bids were opened on that date, and the following four bids were received:
- Delaney at $3,578,908 (apparent low bidder)
- Bongiovanni at $4,983,040
- Falter at $5,574,101
- Tuscarora at $10,734,150
Engineers estimate: $3,692,000)
 
Contract 2A covers the railroad crossing near RTF to the rear of the MOST.
 
2B project will cover the West Jefferson Street to Fayette Street pipeline and creekwalk.
 
Project field office is located in the MOST.
RTF advertised for bids on August 8.
 
Pre-bid meeting held on August 22.
 
Bids were opened October 10, and three bids received for the general construction contract. Falter was apparent low bidder at $65,615,101.
 
All bids for general, electrical, plumbing, and HVAC are currently under review by the County. Total of low bids for all four prime contracts is $75,938,541. At County's request, bidders have agreed to another time extension to allow County additional time for review. This extension goes to February 1, 2008.

The goal of the project is to abate eleven CSOs between Fayette and Oneida streets. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility. It recommends:

  • In-line storage and a regional treatment facility (RTF) with a vortex separator as the most cost-effective approach
  • Construction on a site between the elevated railroad tracks and Onondaga Creek southwest of the MOST on West Jefferson Street.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—new stipulated completion date Jan 1, 2012)
Conveyance-related work RTF-related work
No activity this month Pre-construction meeting held on December 12, 2007 with Titan on building demolition contract. Buildings slated for demolition include four buildings at corner of Grand and Delaware needed for Harbor Brook Upper RTF project.

The Facility Plan recommends two regional storage and treatment facilities (RTFs), five underground floatables control facilities, upgrading one pump station, and installation of conveyance pipelines to transport CSO flow to the facilities. The Facility Plan also identifies two sites, both are privately owned vacant land, for purchase for sites of the RTFs.

Other activities

DEC issues approval of 2006 annual report

In a letter dated December 26, 2007, the DEC issued its approval of the County's Final 2006 Annual Report for the County's Onondaga Lake Ambient Monitoring Program.
AMP 2006 Annual Report (10 MB)

Completed projects

Digester at Metro rehabilitated (2000)
Digester at Metro rehabilitated (2000)

Projects completed since July 2002—not included in Interim Projects—are the following:

Major milestones met for CSO interim projects

The following is a summary of the projects completed under Appendix B, pages 10-12, of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date. The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
Project changed: Facility plan drafted and published 3/02
Project changed and milestone revised to 1/1/12 under ACJ amendment signed 12/14/06
Kirkpatrick St. pump station upgrade and force main
Construction delays. Project completed by 11/1/02.
11/1/02

Major milestones met for Metro Interim Projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Sampling conducted this month included:

  • Biweekly tributary sampling conducted on December 11 and 26
  • Special Onondaga Creek samples relating to the Midland dewatering project were collected at Dorwin Avenue and Water Street on December 3 and 14.
  • South Deep sampling conducted on December 13
  • Tributary sampling on December 26 qualified as a high-flow event and was event six of the minimum of five tributary high-flow sampling events required annually.

Fisheries sampling

Completed laboratory identification of the pelagic larval fish that was collected from April to July 2007.

Contracts

New contract

Midland Avenue conveyances & RTF

Contract with Titan Wrecking & Environmental, LLC for the demolition of buildings relating to the Midland Avenue Conveyances & RTF project ($256,450) and the Harbor Brook CSO Abatement project ($227,850)
Contract amount: $484,300. Executed: December 14, 2007

Amendments to existing contracts

ACJ project management

Contract with CDM/C&S amended for continued project management on the Midland Avenue conveyances and RTF, Clinton Street CSO abatement, sewer separation, and biosolids handling improvements projects through 2008.
Amendment amount: $972,337. Executed December 28, 2007

Change orders

Midland Avenue conveyances & RTF

Contract with Murnane Building Contractors amended to include the addition of flexible flap valves at the disinfection tank outfall and cleanup of the disinfection tank.
Amendment amount: $92,438. Executed December 3, 2007

Legislative action

Action items of the County Legislature in December:
No items
Dec 2006
Dec 2006

Upcoming for January legislative session:
No items

Upcoming for January committee:
A resolution calling a public hearing in connection with proposed improvements to the Midland Avenue conveyances and RTF project at an estimated increased cost of $25,586,423.

Funding

Grants

State Bond Act funds

Midland Avenue Phase II conveyances and RTF: Received request in the amount of $90,119.53 on December 18, 2007 for a total received of $23,427,686.

Total payments received to date in State Bond Act funds: $102,234,029.

Federal EPA funds

Midland Avenue Phase II conveyances and RTF: Received request in the amount of $1,099,513.33 on December 18, 2007 for a total received of $27,657,588.

Total received to date in Federal EPA funds: $82,329,119.

Federal Army Corps of Engineers funds

None to report.

Total received to date from U.S. Army Corps of Engineers funds: $9,669,728.

Loans

The following reimbursement payment was received from EFC during December:
Sewer separation (CSO 038, 040, 046A, and 046B): Received request in the amount of $3,218.82 on December 11, 2007.

Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $159,069,198 (short term), $33,995,704 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Grants and loans applied for—not yet approved
Grants received
Financial status report


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection