Go to home page
Go to home page
Midland: The 144-inch conveyance pipe
Midland: The 144-inch conveyance pipe

Monthly report—April 2007

Completed Phase II Midland conveyance
 

Highlights of the month

  • Work activities on the Midland Phase II project during April included:
    • Completed installation of the Phase II portion of the 144-inch pipe. The total length of the 144-inch pipeline is 1,200 feet in this section.
    • The plumbing contractor continued to install roof drains and roof leaders on the RTF portion of the building. The HVAC contractor continued to install supply and return water lines for the unit heaters in the RTF section.
    • The electrical contractor continued to install switchgear and electrical conduits in the RTF portion of the building and grounding systems around the perimeter of the underground storage tank.
    • The metals subcontractor continued installing walkways and stairs in the vortex separator room.
    • Installation of storm drain piping around the site continues.
    • Concrete pours continued. This month the chemical room floor and tank retaining walls were placed. In total for the entire facility, 19,885 cubic yards of concrete have been placed of an estimated 23,000 cubic yards planned for the total facility.
    • As of April 30, 2007, a total of $42,566,243 has been paid on the four prime contracts, which is 79.5% of the total contract sum. The current sum of the prime contracts including approved change orders is $53,493,488.

  • Construction continued on the biosolids handling improvements at Metro.
  • County representatives attended a public hearing sponsored by the City Common Council's Finance, Taxation and Assessment Committee on April 19, 2007 concerning the proposed ACJ Intermunicipal Agreement. No vote has been taken yet by the City Council on the agreement.
  • Bids were opened this month for two ACJ projects slated to begin construction this spring:
    • Clinton Phase I Conveyances: Bids opened April 17, two bids received.
    • Sewer separation for CSO #050 (Parkway/Rockland): Bids opened April 11, three bids received.

  • One bid was advertised this month: Midland Phase III - advertised April 23, 2007.
  • The County met its first required 12-month rolling average (April 2006-April 2007) for Stage II Phosphorus limits in its Metro effluent. The ACJ limit is 0.10 mg/L total phosphorus.

Progress of projects under construction

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—9/1/05 (revised) & Phase III Conveyance—5/01/07. Further Milestone revisions requested)

Phase II construction continues

Adding the brick façade to the RTF
Adding the brick façade to the RTF

The specialty metals subcontractor worked on installing walkways and stairs in the vortex separator room. The plumbing contractor continued to install roof drains and leaders in the RTF. The HVAC contractor continued to install supply and return water lines for the unit heaters in the RTF. The electrical contractor continued to install switchgear and conduit in the RTF, lighting in the underground storage tank, and conduit and panel boxes in the underground disinfection tank.

Total amount of concrete poured to date is 19,885 cubic yards of an estimated 23,000 yards for the completed facility. Concrete work this month included the chemical room floor, tank retaining walls, and equipment pads.

For the exterior walls and the interior walls, 100% of the concrete masonry units (CMU) have been installed. Work has begun on the exterior brick.

Installation of storm drain piping around the site continued this month.

Installation of sections of 144-inch pipe was completed.

Geotechnical monitoring instrumentation reports continue to be compiled and submitted to the County and consultants for review.

Upcoming work

Work anticipated for May 2007 includes:

  • Continued backfilling of the 144-inch pipe.
  • Installation of roofing system.
  • Continued placement of exterior bricks.
  • Continued installation of switchgear and conduit and panel boxes where required.
  • Continued installation of supply and return lines, unit heaters, and HVAC ductwork in the RTF.
  • The plumbing contractor will continue installation of drains and roof leaders in the RTF.

For Midland Phase III this month, bids were advertised on April 23 and will be opened June 6.

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of the construction's impact along each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 ft in diameter near West Castle Street to 4 ft in diameter near Newell Street.

Biosolids handling improvements

Transfer pumps in the Sludge Dewatering Building, March 2007
Transfer pumps in the Sludge Dewatering Building, March 2007

Construction continued on the new Biosolids Handling Improvements at the Metro site. The general contractor continued installation of piping in the Digester Control House and worked on alignment of pumps and motors for the gravity belt sludge feed pumps and centrifuge feed pumps as required.

The electrical contractor (Ridley) worked on installation of lighting and fire alarms in the office area of the sludge dewatering facility, roughing in the lighting and fire alarms in the addition to the facility, and programming of the PLC.

Sewer separation: Rockland-Parkway area

Parkway Drive, looking toward South Avenue (Nov 2006)
Parkway Drive, looking toward South Avenue (Nov 2006)

Sewer separation for CSO basin 050 involves installation of 4200 feet of new sewer pipeline. Construction began in spring '07. The project is scheduled to be completed in the fall of 2008. The entire project is estimated to cost $4 million.

Work underway (April 2007)

The following actions were completed recently:

  • Bids were opened April 11, 2007.
  • Three bids were received and are currently under review.

Projects in design stage

Clinton conveyances and RTF (CSO)

(ACJ date—Construction completion—2012)
Conveyance-related work RTF-related work
Continued work on property acquisition and easement activities.
 
Bids opened April 17. Two bids were received.
95% design documents submitted to DEC for review and approval on March 2.
 
Design review meeting held with DEC on March 26.
 
Meetings held to discuss stormwater management plans.

The goal of the Clinton project is to address the abatement of eleven CSOs between Fayette and Oneida Streets with a facility located near downtown Syracuse. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility. It also includes a recommended plan and site near Clinton Street between the elevated railroad tracks and Onondaga Creek.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—new stipulated completion date Jan 1, 2012)
Conveyance-related work RTF-related work
Continued work on 95% design.
 
Continued work on geotechnical report including micro-tunneling design.
 
Continued work on easement and property acquisition activities.
Design review meeting with NYS DEC on the 50% design on both Upper and Lower Basin RTFs was held on April 26, 2007.

The Harbor Brook CSO Abatement Facilities Plan recommends specific technologies and sites that includes two regional storage and treatment facilities, five underground floatables control facilities, upgrading one pump station, and installation of conveyance pipeline to transport CSO flow to the facilities. The two sites identified for purchase for the storage and treatment facilities are on vacant privately owned land.

Other activities

Planning is underway for the 6th Annual Onondaga Lake Day to be held Saturday, June 2, 2007 at Onondaga Lake Park. The County will have multiple displays for this Onondaga Lake Partnership event.

Completed projects

Siphon rehabilitation, 1998-99
Siphon rehabilitation, 1998-99

Projects completed since July 2002—not included in Interim Projects—are the following:

Major milestones met for CSO Interim Projects

The following is a summary of the projects completed under Appendix B page 10-12 of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these "interim" projects were completed well ahead of the major milestone date, and all except two met the major milestone date. The projects are listed below chronologically by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
Project changed: Facility plan drafted and published 3/02
Project changed and milestone revised to 1/1/12 under ACJ amendment signed 12/14/06
Kirkpatrick St. pump station upgrade and force main
Construction delays. Project completed by 11/1/02.
11/1/02

Major milestones met for Metro Interim Projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Summary of sampling program

Sampling conducted this month included biweekly tributary sampling conducted April 3 and 17, and special Onondaga Creek sampling for the Midland dewatering project collected April 9 and 26 at Dorwin Avenue.
Fishing under the Thruway, April 2007
Fishing under the Thruway, April 2007

Biological monitoring — Fisheries & macroinvertebrates

The 2007 monitoring season began April 1.

Contracts

New contracts

None to report.

Amendments to existing contracts

Project management

Contract with CDM/C&S amended to include project management services for sewer separation area CSO 051. Contract amendment amount: $162,401.00. Executed: 4/26/07.

Property management services

Contract with Wolf Construction Management Services amended to include property management services for Midland Phase III Conveyances & Harbor Brook CSO Abatement projects. Contract amendment amount: $82,000.00. Executed: 4/24/07.

Midland Avenue conveyances

Contract with Environmental Engineering Associates, LLP (EEA) amended to include design and construction administration for Phase III. Contract amendment amount: $1,961,701.00. Executed: 4/26/07.

Change orders

None to Report.

Legislative action

To promote public education, 15 billboards—including this at I-690—and newspaper ads during April & May encourage residents to reduce nonpoint source pollution
To promote public education, 15 billboards—including this at I-690—and newspaper ads during April & May encourage residents to reduce nonpoint source pollution

Action items of the County Legislature in the month of April:

  • Appropriated $15,477,760 of the proceeds authorized to be issued pursuant to Bond Resolution No. 231-99 to provide funds for construction of Phase I Conveyances and other related expenses of the Clinton Street Conveyances and Regional Treatment Facility project.
  • Calling a public hearing in connection with proposed improvements to the Clinton Street Conveyances and Regional Treatment Facility project.

Upcoming for May legislative session

  • Approving the increased cost of certain improvements for the Clinton Street Conveyances & Regional Treatment Facility for the Onondaga County Sanitary District.
  • Authorizing the issuance of an additional $79,942,042 bonds of the County of Onondaga, New York, to pay the increased cost of certain improvements for the Clinton Street Conveyances and RTF project in and for said county.
  • Authorizing the acquisition of real property to enable the County of Onondaga to comply with requirements set forth in the Onondaga Lake Amended Consent Judgment (ACJ) for the construction, operation and maintenance of the Midland Avenue Sewer Improvement project at a cost of $5,500.

Upcoming for May committee

No items.

Funding

Graduate students from SUNY ESF collect fish from Onondaga Lake for research, April 2007
Graduate students from SUNY ESF collect fish from Onondaga Lake for research, April 2007

Grants

State Bond Act funds

Payments received this month from State Bond Act Funds: None to report. Total received to date in State Bond Act funds: $93,143,909.

Federal EPA funds

Midland Avenue Conveyances & RTF: Received request in the amount of $1,880,144 on 4/26/07 for a total amount received of $23,205,539. Total received to date in Federal EPA Funds: $77,634,445.

Federal Army Corps of Engineers funds

None to Report. Total received to date from Army Corps of Engineers funds: $9,255,873.

Loans

The following reimbursement payments were received from EFC during the month of April:
 

Midland Avenue Conveyances & RTF   Received request in the amount of $3,429,687 on 4/13/07 for a total amount received of $18,429,687.
 

Biosolids Handling Improvements   Received request in the amount of $11,916,319 on 4/13/07 for a total amount received of $11,916,319.
 

Sewer separation (CSO 038, 040)   Received Request in the amount of $20,946.57 on 4/13/07.
 

Sewer separation (CSO 047, 048)   Received Request in the amount of $479,898.97 on 4/13/07.

Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $159,069,198 (short term), $42,656,038 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Grants and loans applied for, not yet approved
Grants received
Financial status report (dates, budgets, costs)

—Midland photos courtesy of Ken Jackson and Joe Lorah, C&S-CDM


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection