Go to home page
Go to home page
Preparations below grade for the 144-inch pipeline at Midland RTF
Preparations below grade for the 144-inch pipeline at Midland RTF

Monthly report—January 2007

Midland Phase III Design sent to DEC
 

Highlights of the month

  • Work activities on the Midland Phase II project during January included:
    • Continued installation of the 144-inch pipe. By the end of January, 625 feet of this pipeline has been installed. When completed, the total length of the 144-inch pipeline will be 1200 feet.
    • Placement of the concrete masonry units (blocks) is underway throughout the treatment facility. By the end of January, 95% of the exterior walls and 85% of the interior walls had been completed.
    • Placement of the outside architectural concrete panels around the exterior walls of the RTF was completed this month. Also, the first level of the precast concrete roofing panels was installed this month over the RTF.
    • Contractors continued to install switchgear and electrical conduits, HVAC ductwork, plant water piping, and lighting in various parts of the facility.
    • Concrete pours continued this month for walls in the vacuum flushing chambers. In total for the entire facility, 19,500 cubic yards of concrete have been placed of an estimated 23,000 cubic yards planned for the total facility (84.8%).
    • As of January 31, 2007, a total of $38,218,150 has been paid on the four prime contracts, which is 71.4% of the total contract sum. The current sum of the prime contracts including approved change orders is $53,493,488.

  • Construction continues on the biosolids handling improvements at Metro. By the end of January, the new Sludge Blend Tank Building was about 98% complete. All pumps and piping are installed in the pump room, and the blend tank mixers and exterior stairs are now in place. The electrical contractor is completing electrical and instrumentation connections. Work continues on the sludge dewatering facility as well. Old equipment has been replaced with new equipment including centrifuges, gravity belt thickeners, feed pumps, and associated piping.
    Parkway Drive, site of part of the next sewer separation project (Nov 2006)
    Parkway Drive, site of part of the next sewer separation project (Nov 2006)

  • The Syracuse City Council passed the intermunicipal agreement regarding CSO 050 sewer separation project in January. The project involves portions of the following streets: Parkway Drive, Rockland Avenue, East Bissell Street, Temple Place, and South Avenue. Advertisements for bids are scheduled for March 2007 with construction to begin Spring 2007.
  • Final design documents on Midland Phase III were completed this month and submitted to DEC for review and approval on January 16, 2007.

Progress of projects under construction

Midland conveyances and RTF (CSO)

(ACJ completion date—Phase II RTF—9/1/05 (revised) & Phase III Conveyance—5/01/07. Further Milestone revisions requested)

Phase II construction continues

The first level of precast concrete roofing panels was installed over the RTF, and the lower set of architectural concrete panels have been set completely around the exterior walls. The specialty metals subcontractor began installation of the weir assemblies for the vortex separators, and the electrical contractor continued to install switchgear and conduits in the RTF and lighting in the underground storage tank. The plumbing contractor is installing roof drains and leaders in the RTF, and the general contractor continued to install concrete walls in the vacuum flushing chambers.

The total amount of concrete poured to date is 19,500 cubic yards of an estimated 23,000 cubic yards for the completed facility (84.8%).
Midland RTF, looking north
Midland RTF, looking north

Installation of sections of 144-inch pipe continued, and installation of concrete masonry unit walls in the RTF area continued as well. So far, 625 feet of the 144-inch pipe has been placed. To-date, 95% of the concrete blocks for the exterior walls and 85% for the interior walls of the treatment facility are complete.

Geotechnical monitoring instrumentation reports continue to be compiled and submitted to the county and consultants for review.

Upcoming work

In February, placement of walls for vacuum flushing chambers will continue. The upper pre-cast concrete roofing system is scheduled for placement in late February. Additional work anticipated for February 2007 includes continued installation of:

  • Sections of the 144-inch pipe
  • Concrete slabs in the odor control room and chemical room
  • Interior CMU walls and upper level walls in the RTF
  • Switchgear in the RTF and lighting in the underground storage tank by electrical contractor
  • HVAC ductwork in the RTF
  • Plant set drains and roof leaders in the RTF by the plumbing contractor.

Midland Phase III activities this month

  • Completed 100% Phase III design documents and submitted to DEC for review and approval on January 16
  • Continued coordination activities with utility owners on relocation of utilities
  • Continued work on property acquisitions and easements.

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of time that construction will take place along each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 feet in diameter near West Castle Street to 4 feet in diameter near Newell Street.

Biosolids handling improvements

New pumps in the Sludge Dewatering Facility
New pumps in the Sludge Dewatering Facility

Construction continues on the new biosolids handling improvements at the Metro site. The general contractor is 98% complete with the new Sludge Blend Tank Building. All pumps and piping has been installed in the pump room, and the blend tank mixers are in place. The electrical contractor is completing electrical and instrumentation connections. The HVAC contractor has installed the new steam and condensate lines and heaters. The plumbing contractor has installed and insulated new water lines.

Work also continues on the improvements and renovations to the Sludge Dewatering Facility. New equipment installed this month includes centrifuges, gravity belt thickeners, and feed pumps. New polymer storage and sludge storage tanks have also been installed, and painting continues on the second floor in the office-laboratory-lunch room area. The electrical contractor has installed control panels. The HVAC contractor is continuing to install new HVAC ductwork. The plumbing contractor is running new water lines.

Next sewer separation project—Parkway-Rockland CSO 050

Sewer separation for CSO basin 050 involves installation of approximately 4200 feet of new sewer pipeline. The following actions were completed recently:

  • Intermunicipal agreement authorized at December meeting of County Legislature.
  • Agreement approved by Common Council in January.

Advertisement for bids now scheduled for March 2007 following DEC approval of final design documents. Construction to begin spring 2007 and scheduled to be completed in fall of 2008.

Projects in design stage

Clinton conveyances and RTF (CSO)

(ACJ dates—Commence construction of conveyances and RTF—10/28/04 (revised)—Further milestone revision requested)
Conveyance-related work RTF-related work
Continued work on property acquisition and easement activities
 
100% contract documents submitted to DEC for review on December 22
 
Continued work on needed property acquisitions and easements
Continued work on 95% RTF design for submittal
 
Facility plan addendum regarding CSO closures submitted to DEC on December 26 following meeting with DEC on December 21

The goal of the project is to abate eleven CSOs between Fayette and Oneida streets. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility. It recommends:

  • In-line storage and a regional treatment facility (RTF) with a vortex separator as the most cost-effective approach
  • Construction on a site between the elevated railroad tracks and Onondaga Creek southwest of the MOST on West Jefferson Street.

Harbor Brook CSO abatement (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—Milestone Revision requested)
Conveyance-related work RTF-related work
Continued work on 95% design.
 
Continued work on geotechnical report including micro-tunneling design
 
Continued work on easement and property acquisition activities
Continued design activities required for the 50% design submittal on both upper and lower basin RTFs.
 
Archeological Phase II historical research draft report submitted by consultants to County for review and comment
 
Facility plan addendum regarding CSO closures submitted to DEC on December 28 following meeting with DEC on December 21

The Facility Plan recommends two regional storage and treatment facilities (RTFs), five underground floatables control facilities, upgrading one pump station, and installation of conveyance pipelines to transport CSO flow to the facilities. The Facility Plan also identifies two sites, both are privately owned vacant land, for purchase for sites of the RTFs.

Other activities

Nothing to report.

Completed projects

Work in progress, Tallman-Onondaga sewer separation (Nov 2004)
Work in progress, Tallman-Onondaga sewer separation (Nov 2004)

The following projects have been completed since July 2002. They are not classified as interim projects.

Major milestones met for CSO interim projects

The following is a summary of the projects completed under the Amended Consent Judgment (Appendix B pages 10-12). Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
Project changed: Facility plan drafted and published 3/02
Project changed and milestone revised to 1/1/12 under ACJ amendment signed 12/14/06
Kirkpatrick St. pump station upgrade and force main
Construction delays. Project completed by 11/1/02.
11/1/02

Major milestones met for Metro interim projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Summary of sampling program

Onondaga Lake winter scene with falling snow

  • Biweekly tributary sampling conducted January 9 and 23
  • Special Onondaga Creek samples relating to the Midland dewatering project were collected on January 3, 16, and 30 at Dorwin Avenue.
  • No lake sampling was conducted this month because of harsh weather and insufficient ice cover on the Lake.

Biological monitoring

For the fisheries and macroinvertebrate programs, field and laboratory activities are complete for the 2006 monitoring season. Activities this month included equipment preparation and equipment repairs to get ready for the 2007 monitoring season that begins April 1, 2007.

Event-based sampling

One tributary high-flow event was sampled on January 9, 2007. This is the first of the required minimum of five tributary high-flow events to be sampled each calendar year.

Contracts

New contracts

None to report.

Amendments to existing contracts

Project management

Contract with CDM/C&S amended for project management services for urban best management practices program (UBMP).
Contract amendment amount: $8,000. Executed: 1/10/07.

Contract with CDM/C&S amended for program management services for 2006.
Contract amendment amount: $87,000. Executed: 1/10/07.

Property appraisal services

Contract with Pomeroy Appraisal Associates, Inc. amended for property appraisals of easements and acquisitions.
Contract amendment amount: $12,000. Executed: 1/18/07.
Metal work on a vortex at Midland RTF
Metal work on a vortex at Midland RTF

Change orders

None to report.

Legislative action

Action items of the County Legislature in January: No items.

Upcoming for February legislative session: No items.

Upcoming for February committee: No items.

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds:
Midland Avenue conveyances and RTF: Received request in the amount of $780,973.22 on 1/5/07 for total received of $14,337,566.

Total received to date in State Bond Act funds: $93,143,909.

Federal EPA funds

Midland Avenue conveyances and RTF: Received request in the amount of $1,256,873 on 1/30/07 for total received of $20,794,890.

Total received to date in Federal EPA funds: $75,186,978.

Federal Army Corps of Engineers funds

Sewer separation—CSOs 047, 048: Received request in the amount of $390,356.86 on 1/17/07 for total received of $5,849,873.
Rough water on Onondaga Lake in January

Total received to date from U.S. Army Corps of Engineers funds: $9,255,873.

Loans

The following reimbursement payments were received from EFC during the month of January: None to report.

Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $159,069,198 (short term), $11,793,293 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Grants and loans applied for—not yet approved
Grants received
Financial status report

—Midland photos courtesy of Ken Jackson and Joe Lorah, C&S-CDM


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection