Go to home page
Go to home page
Steady progress at Midland RTF
Steady progress at Midland RTF

Monthly report—October 2006

DEC approves Clinton & Harbor Brook plans
 

Highlights of the month

  • Work activities on the Midland Phase II project during October included:
    • Installation continued on the 144-inch pipe. The pipe is laid in sections that are 12-feet in length, and each weighs 65,000 pounds.
    • Roof completed on underground storage tank this month
    • Continued installation of underground conduits, HVAC ductwork, drain lines, and lighting conduits in various parts of the facility
    • Concrete pours for vertical concrete columns of the RTF are now complete. For the entire facility, 18,927 cubic yards of concrete have been placed of an estimated 23,000 cubic yards planned for the total facility (82%).
    • Continued installation of CMU walls in the RTF
    • As of October 31, 2006, $34,649,097 has been paid on the four prime contracts, which is 64.9% of the total contract sum.

  • Design activities on the Midland Phase III project included:
    • Continued preparation of the 100% Phase III conveyance design documents
    • Continued coordination with various utility owners on relocation of utilities
    • Draft Phase IB archeological report received and under review in-house.

  • Construction continues on the South Avenue-Bissell sewer separation project involving sewers in the area of South Avenue, Bissell, and Centennial Drive. This project has eliminated two existing combined sewer overflows—047 and 048.
    • Installation of new mainline sanitary sewers and laterals is now completed.
    • Street restoration and sidewalks completed in October. Work is undergoing final inspection and punch-list development.

  • Construction continues on the biosolids handling improvements project at Metro. During October, installation continued on the new process piping. The contractor also completed paving behind the Sludge Dewatering Building and began construction of new addition to the building.
    Mayor Driscoll and County Executive Pirro announce the 2006 Leaf Bag program to reduce nonpoint pollution. (Liz Loftus of Onondaga County Public Libraries in back.)
    Mayor Driscoll and County Executive Pirro announce the 2006 Leaf Bag program to reduce nonpoint pollution. (Liz Loftus of Onondaga County Public Libraries in back.)

  • The fifth annual free leaf bag program for city residents was kicked off with a press conference with the county executive and the mayor on Friday, October 13 at the Soule Branch Library. The Onondaga County Department of Water Environment Protection delivered the bags to all the libraries and community centers in the city throughout October with refills as needed. This year, a total of 35,000 bags are available under a special grant program funded by Onondaga County and the U.S. Army Corps of Engineers aimed at reducing urban nonpoint pollution reaching Onondaga Lake.
  • The Onondaga Lake Partnership held its annual progress meeting on Monday, October 30 at the Genesee Grand Hotel. The meeting was very well attended and featured the progress made this year on Lake-related issues including the positive effects of the County's new ammonia-phosphorus removal facilities.

Progress of projects under construction

The 144-inch pipe (lower) and the 78-inch Midland Trunk Sewer
The 144-inch pipe (lower) and the 78-inch Midland Trunk Sewer

Midland conveyances and RTF (CSO)

(ACJ completion date—Phase II RTF—9/1/05 [revised] & Phase III Conveyance—5/01/07. Further milestone revisions requested.)

Phase II construction continues

Concrete pours continued this month and were completed for the vertical concrete columns in the RTF and the roof of the underground storage tank. The concrete base slab has been placed for the vacuum flushing chamber. The total amount of concrete poured to date is 18,927 cubic yards of an estimated 23,000 cubic yards for the completed facility (82%).

Installation of sections of 144-inch pipe continued. Installation of CMU walls in the RTF area continued as well.

The geotechnical monitoring instrumentation reports continue to be compiled and submitted to the County and consultants for review.

The electrical contractor continued to install conduit and panels in the electrical gallery for the RTF area and conduit lighting in the underground storage tank. The plumbing contractor has installed floor drains and piping in the vortex and odor control rooms.

Upcoming work

Work anticipated for November 2006 includes:

  • Continued installation of sections of the 144-inch pipe
  • Continued installation of concrete footers and slabs in the vortex separator room, odor control room, chemical room, and walls where required
  • Continued installation of CMU walls in the RTF
  • Continued installation of conduits in the RTF electrical room and installation of HVAC ductwork in the storage tank after final closure of the tank itself
  • Continued installation of drainage piping in the chemical storage room and plant water lines in the underground storage tank.

Midland Phase III activities this month:

  • Continued to progress 100% Phase III design
  • Continued coordination activities with utility companies
  • Phase IB archeological report received in draft for review.

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of time that construction will take place along each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 feet in diameter near West Castle Street to 4 feet in diameter near Newell Street.

Biosolids handling improvements

Fittings awaiting installation in the new Sludge Blending Building (Sep 26)
Fittings awaiting installation in the new Sludge Blending Building (Sep 26)

Construction work continues:

  • Construction continues on the new biosolids handling improvements at the Metro site.
  • Paving was completed near Sludge Dewatering Building, and construction began this month on the new addition to that building.
  • The concrete pad was set for new stairs in blend tank building.
  • Continued installation of new process piping in tank pump room and running new steam and condensate lines in the Sludge Dewatering Building.

Current sewer separation project—Bissell-South Avenue

West Bissell Street prepared for repaving (Sep 27)
West Bissell Street prepared for repaving (Sep 27)

C.O. Falter is the general construction contractor for this $1.9 million sewer separation project. Work is being conducted along Onondaga Creek near Bissell, Onondaga Avenue, South Avenue, and Centennial Drive.

Installation of the all new mainline sewers and laterals is now completed in both basins.

Interior service connection work has been completed on all five private properties where needed.

Street and sidewalk restoration completed this month. Final inspections and punch-list work is yet to be done.

Projects in facility planning stage

Clinton conveyances and RTF (CSO)

(ACJ dates—Commence construction of conveyances and RTF—10/28/04 [revised]. Further milestone revision requested.)
Conveyance-related work RTF-related work
Continued work on property acquisition and easement activities
 
Completed 95% design documents and submitted them to DEC. Review meeting to be scheduled.
EEA completed the 50% design documents and submitted them to Onondaga County for review on October 20.
 
Onondaga County coordinated with conveyance consultants to ensure proper interfacing of the conveyances and the RTF.

A formal letter was received dated October 6, 2006 from the NYSDEC approving the Facility Plan.

The goal of the project is to abate eleven CSOs between Fayette and Oneida streets. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility. It recommends:

  • In-line storage and a regional treatment facility (RTF) with a vortex separator as the most cost-effective approach
  • Construction on a site between the elevated railroad tracks and Onondaga Creek southwest of the MOST on West Jefferson Street.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—Milestone Revision requested)
Conveyance-related work RTF-related work
Continued work on 95% design
 
Continued work on geotechnical report
 
Continued work on acquisition process and easements needed
Continued work on RTF facility layouts
 
Continued design activities required for the 50% design submittal
 
Continued work on acquisition process and easements needed

A formal letter was received dated October 6, 2006 from the NYS DEC approving the Facility Plan.

The Facility Plan recommends two regional storage and treatment facilities (RTFs), five underground floatables control facilities, upgrading one pump station, and installation of conveyance pipelines to transport CSO flow to the facilities. The Facility Plan also identifies two sites, both are privately owned vacant land, for purchase for sites of the RTFs.

Other activities

Annual free leaf bag program

Funded by Onondaga County and a grant through the U.S. Army Corps of Engineers, free leaf bags were again made available to city residents to pick up at branch libraries and community centers in Syracuse beginning in mid-October. The kick-off press conference was held on Friday, October 13. Newspaper ads and billboards were produced and appeared the week of October 15. Bags were distributed and refills made through WEP.
Billboard on South Salina Street near Valley plaza promoting the County's leaf bag program
Billboard on South Salina Street near Valley plaza promoting the County's leaf bag program

A total of 35,000 bags are available this year. Distribution points report a steady stream of customers picking up the bags. People generally seem to be more familiar with the program and the importance of keeping leaves out of the streets, sewers, and Lake.

Rain gauges available

Funded through the same grant as the leaf bags, the Onondaga County Department of Water Environment Protection has rain gauges available for use by individuals or in school classrooms. The gauges have an message printed on them to remind people that pollution can come to the Lake with rain and runoff and suggests ways they can help cut down on this type of nonpoint source pollution.
Monthly report—October   2006

A recent article in a special insert to the local newspaper produced by the Onondaga Lake Partnership included a story about the gauges. As a result, numerous calls and emails have been received, and about 500 gauges have been distributed so far.

Onondaga Lake Partnership annual progress meeting

Held on Monday, October 30, this year's OLP annual meeting focused on the progress made this year on Onondaga Lake issues. The County's progress with completion of the ammonia-phosphorus removal facilities and their successful operation and completion of other ACJ projects including sewer separation were noted.

A revised format for the meeting allowed people to go into small group sessions to ask more in-depth questions. There were five topic groups, and the County helped to lead and facilitate the group on wastewater improvements. Other topic groups were recreation, hazardous waste remediation efforts, watershed improvements, and outreach and education programs. This year's meeting was very well attended with over 200 people.

Completed projects

The following projects have been completed since July 2002. They are not classified as interim projects.

Major milestones met for CSO interim projects

The following is a summary of the projects completed under the Amended Consent Judgment (Appendix B pages 10-12). Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
Project changed: Facility plan drafted and published 3/02
Project changed and milestone revised to 1/1/12 under ACJ amendment signed 12/14/06
Kirkpatrick St. pump station upgrade and force main
Construction delays. Project completed by 11/1/02.
11/1/02

Major milestones met for Metro interim projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Summary of sampling program

  • Biweekly tributary sampling conducted October 3, 17, and 31
  • Special Onondaga Creek samples relating to the Midland dewatering project were collected on October 9 and 23 at Dorwin Avenue.
  • The Lake South Deep was sampled on October 10, 24, and 30. Both the South Deep and North Deep were sampled on October 22 and 26.
  • On October 16, WEP conducted a special in situ trial study with the consultant QEA to evaluate the mixing dynamics of Onondaga Creek and Nine Mile Creek in the Lake as a follow-up to the Onondaga Lake water quality model project peer review recommendation.

Biological monitoring

  • Completed event six of six of the juvenile seine events on the weeks of October 9 and 13 (to be completed every 3 weeks from July to October). This work is not complete for this year.
  • Completed field collection efforts for the zebra mussel survey and lab efforts throughout October.
  • Continued laboratory sorting of the Lake macroinvertebrate samples collected in July.

Event-based sampling

Completed the third of the three required storm event-based monitoring efforts on Nine Mile Creek and Onondaga Lake. Dates covered were October 19-22, 2006. A total accumulation of 0.36 inches of rain in 20 minutes was measured at the Metro automated weather station. The sampling criteria is 0.35 inches in 1 hour. All three required events are now completed.
Nov ’05
Nov ’05

Contracts

New contracts

None to report

Amendments to existing contracts: Program management

Contract with CDM/C&S amended for project management services relating to the Midland Avenue conveyances & RTF project ($445,000) and sewer separation (CSO 050, $172,312).
Contract amendment amount: $617,312, executed: 10/16/06.

Change orders

None to report

Legislative action

Legislature: Action items in October

Adopting a determination and findings pursuant to Article 2 of the New York Eminent Domain Procedure Law and authorizing the acquisition of property for the Harbor Brook project.

Legislature: Upcoming for November

Authorizing the standardization of the Calgon Phoenix carbon adsorption odor control system for the Clinton and Harbor Brook projects.

Committee: Upcoming for November

Authorizing an intermunicipal agreement with the City of Syracuse for sewer separation for CSO basin 050.

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds:
None to report.

Total received to date in State Bond Act funds: $92,362,936.

Federal EPA funds

Midland Avenue conveyances and RTF
Received request in the amount of $1,468,218 on 10/18/06 for total received of $18,950,832.
Total received to date in Federal EPA funds: $73,342,920.

Federal Army Corps of Engineers funds

None to report.
Total received to date from U.S. Army Corps of Engineers funds: $8,418,676.

Loans

The following reimbursement payments were received from EFC during October:
Sewer separation: CSO 038, 040, 046A, and 046B:
Received request in the amount of $7,836.96 on 10/13/06 for total received of $1,486,886 (long term).
Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $159,069,198 (short term), $11,790,415 (long term).
 
Nov ’05
Nov ’05

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Lake Improvement Project Office
Grants and loans applied for—not yet approved
Grants received
Financial status report

— Midland photos courtesy of Ken Jackson and Joe Lorah, CDM


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection