Go to home page
Go to home page
Installing the 144
Installing the 144" pipe into the underground storage tank

Monthly report—August 2006

South Avenue sewers installed
 

Highlights of the month

  • Work activities on the Midland Phase II project during August included:
    • Installation continued on the 144-inch pipe. The pipe is laid in sections that are 12 feet in length, and each weighs 65,000 pounds.
    • Concrete pours continued for the vertical walls of the RTF. To date, 18,504 cubic yards of concrete have been placed of an estimated 23,000 cubic yards planned for the total facility (80.5%).
    • Stainless steel ductwork continues to be installed in the underground storage tank by the HVAC contractor. Rebar, forms, and supports continued to be installed in the storage tank and concrete placed for the tank's roof structure.
    • The electrical contractor continued to install conduit and panels in the electrical gallery and underground duct banks on the site.
    • As of August 31, 2006, $32,283,774 has been paid on the four prime contracts, which is 60.5% of the total contract sum.

  • Design activities on the Midland Phase III project included:
    • Continued to progress Phase III conveyance design.
    • An eminent domain hearing was held on September 5 prior to the full meeting of the County Legislature.
    • 95% design documents were completed and submitted to NYSDEC for review and comment.

    Worker in sewer separation trench, West Bissell Street
    Worker in sewer separation trench, West Bissell Street

  • Construction continues on the South Avenue-Bissell sewer separation project involving sewers in the area of South Avenue, Bissell Street, and Centennial Drive. Installation of new sanitary sewers along the portion of South Avenue in CSO 048 and West Bissell are now completed.
     
    Internal separation projects to take place in one multifamily house and four businesses are scheduled for September. This full project when completed will eliminate two existing combined sewer overflows—047 and 048.
  • Construction continues on the biosolids handling improvement project at Metro. During August, concrete placement was completed for the blend tanks, and concrete was placed on the roof deck of the blend tanks. Paving began in the project area. The electrical contractor completed installation of conduits in the electric room of the Sludge Dewatering Building and is currently installing grounding cables for the blend tanks. The HVAC contractor began running new steam and condensate lines, and the plumbing contractor installed roof drains on the pump room.
  • The floatables-control skimmer vessel in Syracuse's Inner Harbor operated twice a week during August. Due to the heavy rains and storms, over 13 tons of floatable debris has been collected and disposed of so far this year. This is ahead of last year's volumes.

Progress of projects under construction

Midland conveyances and RTF (CSO)

(ACJ completion date—Phase II RTF—9/1/05 (revised) & Phase III Conveyance—5/01/07. Further Milestone revisions requested)

Phase II construction continues

Concrete pours continued this month for vertical walls in the RTF and the roof of the underground storage tank. Total amount of concrete poured to date is 18,504 cubic yards of an estimated 23,000 cubic yards for the completed facility (80.5%).
Under construciton: Roof of the underground storage tank
Under construciton: Roof of the underground storage tank

Dewatering of the site continued with daily sampling and flow rates taken at the eleven wells in the area where the 144-inch conveyance pipe will be installed.

Sections of 144-inch pipe continued to be installed this month.

Geotechnical monitoring instrumentation reports continue to be compiled and submitted to Onondaga County.

The electrical contractor continued to install conduit and panels in the electrical gallery for the RTF area and the underground duct banks.

The HVAC contractor continued installation of the stainless steel in the underground storage tank.

Upcoming work

Work anticipated for September 2006 includes:

  • Continued installation of sections of the 144-inch pipe
  • Continued wall pours in treatment facility, vortex separators, and wet well areas
  • Completion of the cast-in-place roof on the underground storage tank
  • Begin installation of CMU walls in the RTF electrical room area
  • Continue installation of 66-inch pipe from storage tank toward Bellevue Avenue regulator structure
  • Continue installation of conduits with RTF electrical room, HVAC ductwork in storage tank, and begin drainage pipe installation in odor control room.

Midland Phase III activities

  • Continued to progress Phase III design
  • Submitted 95% design documents to NYSDEC for review
  • Eminent domain hearing held.

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of time that construction will take place along each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 feet in diameter near West Castle Street to 4 feet in diameter near Newell Street.

Biosolids handling improvements

Construction continued on the new biosolids handling improvements at the Metro site. During August, the contractor completed the blend tanks and placed the concrete roof deck on the blend tanks. Also the contractor completed placement of the CMU block and the exterior brick façade for the pump room of the sludge blend tank building. The electrical contractor completed installation of the bus duct at the sludge dewatering facility for connection of the switchgear to the new transformer and completed installation of the conduits in the electric room of the Dewatering Building.

Paving began in the project area, and the concrete truck unloading pad was completed. Precast architectural wall panels were installed along the roof perimeter of the Sludge Blend Tank Building this month.

Current sewer separation project—Bissell-South Avenue

Trenching along West Bissell for sewer separation
Trenching along West Bissell for sewer separation

C.O. Falter is the general construction contractor for this $1.9 million sewer separation project. Work is being conducted along Onondaga Creek near Bissell, Onondaga Avenue, South Avenue, and Centennial Drive.

Installation of the new mainline sewers was completed this month in the CSO 048 portion of South Avenue and West Bissell. The next area to received sewers is another portion of South Avenue and a portion of West Kennedy Street, covering the CSO 047 area.

Projects in facility planning stage

Clinton conveyances and RTF (CSO)

(ACJ dates—Commence construction of conveyances and RTF—10/28/04 (revised)—Further milestone revision requested.)
Conveyance-related work RTF-related work
Continued work on property acquisition and easement activities
 
Worked to complete 95% design documents
Continued work on RTF facility layout and site considerations
 
Held 25% design review meeting with County and NYSDEC on August 31, 2006
 
Coordinated with conveyance consultants to ensure proper interfacing of the conveyances and the RTF

The goal of the project is to abate eleven CSOs between Fayette and Oneida streets. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility. It recommends:

  • In-line storage and a regional treatment facility (RTF) with a vortex separator as the most cost-effective approach
  • Construction on a site between the elevated railroad tracks and Onondaga Creek southwest of the MOST on West Jefferson Street.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—Milestone revision requested)
Conveyance-related work RTF-related work
Consultant continued working on easement descriptions
 
Continued work on 95% design
 
Continued work on geotechnical report
Continued work on Phase II environmental site assessments for Harbor Brook RTF sites
 
Completed work on property survey/site acquisition investigation for RTF sites
 
Continued work on RTF facility layouts
 
Continued final design activities required for the 50% design submittal
 
Revised layout of upper Harbor Brook RTF

The Facility Plan recommends two regional storage and treatment facilities (RTFs), five underground floatables control facilities, upgrading one pump station, and installation of conveyance pipelines to transport CSO flow to the facilities. The Facility Plan also identifies two sites, both are privately owned vacant land, for purchase for sites of the RTFs.

Other activities

No report.

Completed projects

The following projects have been completed since July 2002. They are not classified as interim projects.

Major milestones met for CSO interim projects

The following is a summary of the projects completed under the Amended Consent Judgment (Appendix B pages 10-12). Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
Project changed: Facility plan drafted and published 3/02
Project changed and milestone revised to 1/1/12 under ACJ amendment signed 12/14/06
Kirkpatrick St. pump station upgrade and force main
Construction delays. Project completed by 11/1/02.
11/1/02

Major milestones met for Metro interim projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Shoreline at southern tip of Onondaga Lake, evening of August 30
Shoreline at southern tip of Onondaga Lake, evening of August 30

Ambient monitoring program

Summary of sampling program

Sampling conducted this month included:

  • Biweekly tributary sampling conducted August 8 and 22.
  • Special weekly samples relating to the Midland dewatering project were collected on August 15 and 28 at Dorwin Avenue.
  • Completed special weekly sampling in the Lake nearshore on August 1, 7, 15, 21, and 29. The Lake South Deep was sampling on August 1, 15, and 29.
  • The monthly river sampling was conducted on August 3.

Monthly report—August    2006

Biological monitoring:

  • Completed events seven and eight of the Wednesday night Salt City Bassmaster Tournament tagging on August 2 and 9.
  • Completed events three and four of six of the juvenile seine events on the weeks of August 7 and 28 (to be completed every 3 weeks from July to October).
  • Completed sampling of macroinvertebrates and habitat assessment in the ten tributary locations. Completed sampling at ten of ten sites. Completion had been delayed because of elevated flows and high water in July.
  • Completed aerial flights and subsequent field verifications for macrophytes on August 9. This task had been postponed in July due to unfavorable weather and flight conditions and failure to achieve adequate water clarity because of high tributary flows to Onondaga Lake.

Contracts

New contracts

None to report.

Amendments to existing contracts

None to report.

Change orders

None to report.

Legislative action

Action items of the County Legislature in August:

  • Calling a public hearing pursuant to Article 2 of the New York Eminent Domain Procedure Law before considering the acquisition of property for the Midland Avenue project
  • Calling a public hearing pursuant to Article 2 of the New York Eminent Domain Procedure Law before considering the acquisition of property for the Harbor Brook project
  • Adopting a determination and findings pursuant to Article 2 of the New York Eminent Domain Procedure Law and authorizing the acquisition of property for the Clinton Street project
  • Appropriating $2,239,100 of the proceeds of the bonds authorized to be issued pursuant to bond resolution no. 231-99 to provide funds for property acquisition and other related expenses of the Clinton Street conveyances and RTF project
  • Authorizing the issuance of an additional $49,890,420 bonds of the County of Onondaga to pay the increased cost of certain improvements for the Midland RTF.

Upcoming for September legislative session:

  • Adopting a determination and findings pursuant to Article 2 of the New York Eminent Domain Procedure Law and authorizing the acquisition of property for the Midland Avenue project.
  • Authorizing the acquisition of real property to enable the County of Onondaga to comply with requirements set forth in the Onondaga Lake Amended Consent Judgment for the construction, operation, and maintenance of the Midland Avenue project ($218,100).

Upcoming for September committee: Adopting a determination and findings pursuant to Article 2 of the New York Eminent Domain Procedure Law and authorizing the acquisition of property for the Harbor Brook project.

Funding

Monthly report—August    2006

Grants

State Bond Act funds: Payments received this month from State Bond Act funds: None to report.
Total received to date in State Bond Act funds: $92,362,936.

Federal EPA funds: Received request for $1,768,680 on 8/8/06 and request for $1,376,717 on 8/28/06 for total received of $17,275,025. Total received to date in Federal EPA funds: $71,468,700.

Federal Army Corps of Engineers funds: None to report. Total received to date from U.S. Army Corps of Engineers funds: $8,418,676.

Loans

The following reimbursement payments were received from EFC during August: None to report. Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $159,069,198 (short term), $10,303,528 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Lake Improvement Project Office
Grants and loans applied for—not yet approved
Grants received
Financial status report

—Midland photos courtesy of Ken Jackson, CDM


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection