At Midland: Aligning steel sheeting for the Bellevue conveyance crossing of Onondaga Creek
At Midland: Aligning steel sheeting for the Bellevue conveyance crossing of Onondaga Creek

Monthly report—May 2006

New sewer separation work begins
 

Highlights of the month

  • Work activities on the Midland Phase II project during May included:
    • Installation of underground electrical duct bank from the underground disinfection tank toward the Tallman Street regulator continued this month and is now 75% complete.
    • Continuation of the concrete pours for the vertical walls of the RTF. For the entire facility, 16,397 cubic yards of concrete have been placed of an estimated 23,000 cubic yards planned for the total facility (71%).
    • Four concrete sections of roofing were placed this month on the underground storage tank and rebar. Forms and supports continue to be installed in the tank.
    • The electrical contractor installed conduit and panels in the electrical gallery and underground duct banks on the site.
    • Dewatering and testing continue before the start of installation of 144-inch pipe. Three additional dewatering wells are being installed.
    • As of May 31, 2006, $27, 679,319 has been paid on the four prime contracts. This is 51.9% of the total contract sum.

  • Design activities on the Midland Phase III project included:
    • Continued to progress Phase III conveyance design
    • Completed part 2 subsurface investigation program including soil and sonic borings
    • Submitted 50% design drawings to utility companies for utility coordination
    • Met with City of Syracuse DPW for city water and sewer relocations.
    • County is in the process of acquiring five properties needed for the Phases III project. The County has closed on one property to-date.

  • A notice to proceed for the next sewer separation project to be constructed this season around South Avenue, Bissell, and Centennial Drive was issued to C.O. Falter Construction on May 9, 2006. A preconstruction meeting was held on May 10, and work began on obtaining the preconstruction video of existing conditions. This project will eliminate two existing combined sewer overflows—047 and 048.
  • Construction continues on the biosolids handling improvements at Metro. During May, concrete continued to be placed for the wet well in the new sludge blend tank building, and the contractor has completed laying the 10-inch underground lines for the waste-activated sludge between the thickener gallery and the new sludge dewatering facility addition. The electrical contractor is continuing to run electrical conduits through the galleries.
  • County submitted the 50% design and engineering report on the Clinton Street CSO conveyances project to the State DEC for their review.
  • Began annual operation of floatables control skimmer vessel in Syracuse Inner Harbor on May 4. The vessel operates once a week during May and two times a week in the summer months of June-August. Over 23 tons of trash were collected in the 2005 season.

Progress of projects under construction

Workers install the roof decking for the storage tank, Midland
Workers install the roof decking for the storage tank, Midland

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—9/1/05 (revised) & Phase III Conveyance—5/01/07. Further milestone revisions requested)

Phase II construction continues

Concrete pours continued this month for vertical walls in the RTF and the roof of the underground storage tank. Total amount of concrete poured to date is 16,397 cubic yards of an estimated 23,000 yards for the completed facility (71%).

Dewatering of the site continued with daily sampling and flow rates taken at the eight existing wells. Three additional dewatering wells were installed this month in the area where the 144-inch conveyance pipe will be installed.

Geotechnical monitoring instrumentation reports continue to be compiled and submitted to the County.

The electrical contractor continued to install conduit and panels in the electrical gallery and the underground duct banks. Installation of the underground electrical duct bank from the underground disinfection tank toward the Tallman Street regulator structure is 75% complete.

Installation of supports and formwork continues in the underground storage tank area.

Midland Avenue bridge will remain closed through the fall of 2006 due to construction activities. Emergency services and others, including the city school district, were notified that the closure will continue.

Upcoming work

Work anticipated for June 2006 includes:

  • Continuation of installation of conduit in the treatment facility and underground duct banks
  • Continuation of wall pours in treatment facility and wet well areas
  • Continue installation of supports and formwork and more sections of the cast-in-place roof on the underground storage tank
  • Commence installation of sheeting and the first half of the 66-inch pipe from the storage tank toward the creek
  • Continue with dewatering pump test—needed before installation of 144-inch pipe.

Midland Phase III activities

  • Continued to progress Phase III design
  • Completed part 2 subsurface investigation program including sonic and soil borings
  • Commenced property acquisition activities for five properties needed. Purchase completed for one of the properties.
  • Submitted 50% design drawings to utility companies for utility coordination
  • Met with City of Syracuse DPW representatives regarding coordination of city water and sewer relocations.

Construction on the Phase III pipeline will begin at the West Castle Street end and progress over 2½ years toward West Newell Street. No single area will be affected for the full 2½ years, and the length of the disturbance for each street depends on the size of the pipe to be installed. The pipeline ranges in size from 12 feet in diameter near West Castle Street to 4 feet in diameter during the latter stages of construction near West Newell Street.
Aerial photo of Midland construction site, May 2006<br> (Photo by John Cavanaugh of Photoworks Aerial Photography)
Aerial photo of Midland construction site, May 2006
(Photo by John Cavanaugh of Photoworks Aerial Photography)

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—10/28/04 (revised)—Further milestone revision requested)
 
Conveyance-related design work RTF-related design work
50% design drawings and engineering report for conveyances received by County and sent to DEC for review on May 1
 
Continued work on easement descriptions and additional survey work
 
Continued work on geotechnical report including micro-tunneling final design
 
Meetings held on needed property acquisitions between County and design engineers
Completed field work for sonic borings at the RTF site
 
Continued work on RTF facility layout and site considerations
 
Continued work on geotechnical design considerations
 
Completed property survey and site acquisition maps and descriptions for RTF site

The goal of the Clinton project is to address the abatement of eleven CSOs between Fayette and Oneida streets to be served by a Clinton area facility located near downtown Syracuse. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility and includes a recommended plan and site near Clinton Street between the elevated railroad tracks and the creek.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—not implementable—milestone revision requested)
 
Conveyance project activities RTF-related design work
Continued exploring micro-tunneling option and collecting information on its implementation on this project in the Park Avenue area
 
25% design drawings and engineering report received and under review by County
 
Meetings held between County and design engineers on proposed property acquisitions
 
Consultant began easement descriptions
Geotechnical reports for lower Basin RTF site under review
 
Continued work on Phase II environmental site assessments for Harbor Brook RTF sites
 
Continued work on property survey/site acquisition investigation for RTF sites
 
Continued work on RTF facility layouts

The Facility Plan recommends specific technologies and sites that includes two regional storage and treatment facilities, five underground floatables control facilities, upgrading one pumping station, and installation of conveyance pipeline to transport CSO flow to the facilities. The two sites identified for purchase for the storage and treatment facilities are on vacant privately owned land.

Biosolids handling improvement

Construction continues on the new biosolids handling improvements at the Metro site. During May, the contractor, C.O. Falter completed placing concrete for the wet well in the new sludge blend tank building and completed laying the 10-inch pipe line for waste activated sludge between the thickener gallery and the new sludge dewatering facility addition.

The electrical contractor is continuing to run electrical conduits through the galleries and has placed the concrete pad for the new transformer to be adjacent to the sludge dewatering facility.
Biosolids construction site, May 2006
Biosolids construction site, May 2006

Next sewer separation project—Bissell-South Avenue

An availability session for the public was held by the County on Monday, May 8 at the Southwest Community Center on this sewer separation project.

The notice to proceed was issued to C.O. Falter Construction on May 9. The project will separate sewers that feed into CSOs 047 and 048 located along Onondaga Creek. Streets affected by construction will include East and West Bissell, Onondaga Avenue, and South Avenue.

During May, the contractor completed the required preconstruction video of the existing conditions and combined sewers. Installation of the new sewers is scheduled to begin in the middle of June. All work is required by the contract to be completed by November 6, 2006.

Other activities

Publicity banner downtown for Onondaga Lake Day, May 2006
Publicity banner downtown for Onondaga Lake Day, May 2006

Onondaga Lake Partnership

The annual Onondaga Lake Day event sponsored by the Partnership has been scheduled for Saturday, June 3, 2006 from 10:00 a.m. to 3:00 p.m. at Onondaga Lake Park. The County is participating in a variety of ways to assist the Partnership with this program.

Completed projects

The following projects have been completed since July 2002. They are not classified as interim projects.

Major milestones met for CSO interim projects

The following is a summary of the projects completed under the Amended Consent Judgment (Appendix B pages 10-12). Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer '02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
Project changed: Facility plan drafted and published 3/02
Project changed and milestone revised to 1/1/12 under ACJ amendment signed 12/14/06
Kirkpatrick St. pump station upgrade and force main
Construction delays. Project completed by 11/1/02.
11/1/02

Major milestones met for Metro interim projects

Under Appendix A of the Amended Consent Judgment, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date, and most were completed well ahead of schedule. The projects are listed below by date completed:
 
Project Date completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient monitoring program

Summary of sampling program

Sampling conducted this month included:

  • Routine biweekly tributary sampling conducted on May 2, 16, and 31
  • Completed special weekly sampling of the nearshore and South Deep stations on May 1, 15, and 30. Also conducted Lake south deep sampling only on May 9 and 23,
  • No special event-based sampling this month.

Biological monitoring

Continued fisheries monitoring activities for the new sampling year. Completed events two and three of eight for the pelagic larvae sampling on May 10 and 24. This type of sampling is to be completed biweekly from April to July.

Completed events one, two, three, and four of five of the special larval walleye sampling event near Ninemile Creek to determine if walleye are naturally reproducing in Onondaga Lake and its tributaries. Sampling was done of May 4, 12, 19, and 24 with a special walleye trawl. This sampling was conducted based on Technical Advisory Committee discussions.

Contracts

Placing concrete in the north wall of the influent channel at the Midland RTF
Placing concrete in the north wall of the influent channel at the Midland RTF

New contracts

None to report.

Amendments to existing contracts

Harbor Brook conveyances

Contract with CDM/C&S amended to do test pit excavations to locate elevation of water main.
Contract amendment amount: $9,636. Executed: 5/2/06.

Harbor Brook RTF

Contract with Environmental Engineering Associates, LLP (EEA) amended for subsurface soil and groundwater investigations.
Contract amendment amount: $68,068. Executed: 5/8/06.

Change orders

None to report.

Legislative action

Action items of the County Legislature in May:

  • Authorizing and ratifying the County of Onondaga to act as lead agency for the Clinton Street sewer improvement project under the State Environmental Quality Review Act (SEQRA) and the State Environmental Review Process (SERP), determining the classification of a Type I action, adopting a negative declaration, and authorizing the publication, circulation, service and filing of the environmental assessment form, DEID, and the negative declaration.
  • Appropriating $1,900,000 of the proceeds for the bonds authorized to be issued pursuant to bond resolution no. 231 dated September 7, 1999 to provide funds for engineering and other related expenses of the Clinton Street conveyances and regional treatment facility projects ($1,900,000).

Upcoming for June legislative session:

  • Authorizing the acquisition of real property to enable the County of Onondaga to comply with requirements set forth in the Onondaga Lake Amended Consent Judgment for the construction, operation, and maintenance of Phase III of the Midland Avenue regional treatment facility and conveyances project ($304,800).
  • Calling for a public hearing for the purpose of considering an increase in the cost of proposed improvements for the Midland Avenue project.

Upcoming for June committee:

  • Calling a public hearing pursuant to Article 2 of the New York Eminent Domain Procedure Law before consideration of the acquisition of property for the Clinton Street sewer improvement project.
  • Approving the increased cost of certain improvements for the Midland RTF.
  • Authorizing the issuance of an additional $49,890,420 bonds of the County of Onondaga to pay the increased cost of certain improvements for the Midland RTF.

Funding

Onondaga Lake: May 2003
Onondaga Lake: May 2003

Grants

State Bond Act funds

Payments received this month from State Bond Act funds: None to report.
Total received to date in State Bond Act funds: $92,362,936.

Federal EPA funds

Midland Avenue Phase II Conveyances and RTF:
Received request in the amount of $1,491,066.00 on 5/9/06 for total amount received of $12,638,562.

Full-scale ammonia/phosphorus removal:
Received request in the amount of $384,125.00 on 5/9/06 for total amount received of $53,809,550.
Total received to date in Federal EPA funds: $66,448,112.

Federal Army Corps of Engineers funds

None to report.
Total received to date from U.S. Army Corps of Engineers funds: $8,394,750.

Loans

The following reimbursement payments were received from EFC during the month of May:
None to report.

Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $159,069,198 (short term), $10,303,528 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Lake Improvement Project Office
Grants and loans applied for—not yet approved
Grants received
Financial status report

—Midland photos courtesy of Ken Jackson, CDM,
except as noted


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection