Go to home page
Go to home page
A concrete wall is poured for the underground storage tank at Midland RTF
A concrete wall is poured for the underground storage tank at Midland RTF

Monthly report—September 2005

Harbor Brook public meetings held
 

Highlights of the month

  • Work activities on the Midland Phase II project during September included completion of pouring of the vertical walls for the underground disinfection tank that was begun in June and continued concrete pours for the underground storage tank that began in August: eight wall sections and four base slabs have been completed. Dewatering of the site continues, and installation of sheeting along the 144-inch pipeline route continued.
  • Work on the Tallman-Onondaga sewer separation project has been completed. The contractor worked on punch list items this month—some completed, some remain to be done. All street restorations have been completed. Installation of sewers is complete in all four CSO basins, and cured-in-place liner has been installed where designed in Onondaga Avenue in basin 046A and along Eloise Terrace in basin 046B. This project eliminated four existing combined sewer overflows that previously discharged into Onondaga Creek.
  • Public information meetings on the Harbor Brook CSO Abatement Project Facility Plan (Aug 2005) were held on September 14 and 15. Over 700 notices of the meetings were sent to area residents and interested community groups and organizations. The public comment period on the draft plan ends October 17 after which a responsiveness summary will be compiled on the questions and comments raised by the public. The next step in the process will be a public hearing.

Progress of projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ Completion date for ammonia full-scale—11/3/03—Revision requested)
(ACJ Completion date for Phosphorus Removal Stage II—on schedule)
All major construction work on the project is now complete, and contractors are working on remaining punch list items.

Activities related to the start-up of the HRFS phosphorus removal system:

  • BAF effluent is flowing through the HRFS influent channel, through all four trains and the effluent channel.
  • The 30-day performance test on the HRFS facility began in February and was completed in March. Results are under review and analysis by the County and the project's consultant, EEA.
  • October 1 is the target to initiate testing under the next step of the phosphorus pilot study.

The ammonia-phosphorus removal upgrade to Metro was fully completed in 2004. This project is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive effects on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Tallman-Onondaga sewer separation (CSO)

Work is complete for sewer separation—Midland Avenue at Lincoln Avenue (Aug 2005)
Work is complete for sewer separation—Midland Avenue at Lincoln Avenue (Aug 2005)

(ACJ milestone date July 1, 2012 completion of all sewer separation projects) This project is now completed, and the contractor worked on punch list items this month. Some punch list items were completed; some remain to be done.

This project separated four combined sewer areas in the Tallman-Midland-Onondaga Avenue area and eliminated CSOs 038 and 040 in the Tallman-Midland area and 046A and 046B near Onondaga Avenue on the city's west side. C.O Falter was the successful bidder on the contract.

The total construction of the project is estimated to cost $4.9 million with 70%-30% reimbursement from the U.S. Army Corps of Engineers. Under this project, new sewers were installed, and in most areas existing combined sewers were converted to use by stormwater only. Now finished, these four sewer overflow discharge points (038, 040, 046A, and 046B) no longer discharge a combination of untreated sewage and stormwater to Onondaga Creek.

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07 Milestone revisions requested)

Work was completed this month on the placement of vertical concrete walls for the underground disinfection tank. Excavation and concrete pouring continued for the underground storage tank including completion of eight wall sections, four base slabs, and partial pours on three mud mats. Installation of sheeting for the wet well within the RTF footprint was also completed this month. Additional sheeting was installed on the east side of the wet well sheeting to stop excessive groundwater flow into the wet well excavation.
At Midland, work on the dewatering wet well
At Midland, work on the dewatering wet well

Installation of sheeting for the Bellevue regulator structure is complete, and installation of sheeting along the 144-inch pipeline has resumed beyond the cemented gravel layer encountered elsewhere on the route.

Dewatering of the site continued with daily sampling and flow rates taken.

Upcoming work

Work anticipated for October 2005 includes:

  • Continued excavation of the underground storage tank to subgrade
  • Continuation of installation of the storage tank slabs and wall pours
  • Continued sheet driving for the 144-inch CSO conveyance pipe
  • Installation of bypass for 36-inch water line.

Midland Phase III activities

  • Phase 1A and Phase 1B archeological work plan completed by subconsultant and under review by EEA
  • Draft geotechnical data report completed by subconsultant and under review by EEA
  • Draft supplemental environmental information document completed by subconsultant and under review by EEA
  • 25% plan and profile design continues—engineering report and basis of design being prepared
  • Planning continues for part two of the geotechnical investigation program.

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—Milestone revision requested.)

Following review of the comments received from the State DEC (dated May 27, 2005) on the Clinton Street CSO Abatement Project Facility Plan (Feb 2005 draft) and accompanying Clinton CSO Abatement: Environmental Information Document (Feb 2005), the County responded to the comments in a letter dated July 22, 2005. The report recommends construction of a regional treatment facility using vortex technology and high-rate disinfection with dechlorination at the Clinton station site. Conveyance pipes will connect the CSOs to the facility and also serve as inline storage. A meeting was planned for October 7 with DEC to discuss the draft plan and respond to questions. Following completion of DEC review, the document will be finalized and a public meeting scheduled.

The County is currently in the process of finalizing the design contracts for the Clinton and Harbor Brook projects. EEA was awarded the design services contract for the regional treatment facilities. CDM/C&S was awarded the design contract for the conveyances associated with each project. Regarding the RTFs, the contract for Clinton RTF covers only predesign services including the archeological and geotechnical work. The contract for Harbor Brook covers all design services.

The initial draft facility plan was released to the public in March 2002. The revised Facility Plan includes a specific recommendation for technology and siting. The goal of the Clinton project is to abate ten CSOs between Fayette and Adams streets to be served by a Clinton area facility located near downtown Syracuse. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility and includes a recommended plan and site behind the elevated railroad tracks from the Armory Square area.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—Milestone Revision requested)

Public meetings held on Facilities Plan and Environmental Information Document

One of the sites for a Harbor Brook CSO abatement facility, near Grand Avenue
One of the sites for a Harbor Brook CSO abatement facility, near Grand Avenue

Public meetings on the Harbor Brook CSO Abatement Project Facility Plan (Aug 2005) and Harbor Brook Environmental Information Document (Aug 2005) were held on September 14 and 15 at locations on the west side of the city near the proposed project sites. In addition to a direct mailing to over 700 residents and community groups near the project sites, the County placed paid advertisements in the Syracuse Post Standard and the Pennysaver newspapers. About twenty-five people attended each meeting. The public was given until October 17, 2005, to submit any comments or questions on the plan. At the close of the comment period, a responsiveness summary will be compiled.

Request for proposals issued for next steps

The County is currently in the process of finalizing the design contracts for the Harbor Brook and Clinton projects. EEA was awarded the design services contract for the regional treatment facilities and CDM/C&S was awarded the design contract for the conveyances associated with each project. Regarding the regional treatment facilities, the contract for Clinton RTF covers only predesign services including the archeological and geotechnical work, and the contract for Harbor Brook covers all design services.

The initial draft Harbor Brook facility plan was released in March 2002. The draft plan outlined and evaluated alternative technologies and sites for facilities to abate and treat the eighteen CSOs that release to Harbor Brook. The revised Facility Plan recommends specific technologies and sites.

Other activities

Onondaga Lake Partnership

The County continues to be an active member of the Lake Partnership with participation in the Executive Committee, the Project Committee, and the Outreach Committee. Articles are written and photos supplied for the Partnership's newsletter and work done in preparation for the upcoming annual progress meeting to be held November 2.

Completed projects

Major milestones met for CSO interim projects

The following is a summary of the projects completed under Appendix B pages 10-12 of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.


 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Sampling conducted this month included:

  • Routine biweekly tributary sampling conducted on September 7 and 30. The quarterly extended tributary sampling was completed on September 20.
  • Special weekly double lake samplings of the nearshore and South Deep were completed on September 6,13, 19, and 27.
  • No special high-flow sampling events were completed this month. The County has already completed all five of its required minimum of five annual tributary high-flow events.
  • Conducted monthly full three rivers sampling event on September 15 in Seneca, Oneida, and Oswego rivers to support completion of Three Rivers Water Quality Model. Sixteen river buoy monitoring locations were sampled along with three outlet sites and four WWTP effluent locations (Metro, Baldwinsville-Seneca Knolls, Wetzel Road and Oak Orchard).

Biological monitoring

The following fisheries-related sampling took place as required under the AMP this month:

  • Conducted events 4 and 5 of the juvenile seine events (6 required) the week of August 29.
  • Completed event 2 of the 2 required gill netting on October 3 postponed from September due to high winds on scheduled sampling date.
  • Completed event 2 of 2 for littoral zone electrofishing on the week of September 19.
  • Initiated laboratory sorting of macroinvertebrate samples collected in June 2005.

Technical Advisory Committee meets

The County's Onondaga Lake Technical Advisory Committee met on September 14 along with representatives of Atlantic States Legal Foundation, NYSDEC, USGS, and County staff. The meeting agenda focused on the status of the Honeywell remediation efforts, the County's 2005 AMP water quality data, and an update on the development of the Lake's water quality model. On September 13, the lake advisors along with others attended a workshop on the lake model which included breakout sessions to discuss spatial, temporal, and process resolution that the model needs to address salient water quality management questions.
Installing rebar at the location of the influent sump for the Midland RTF
Installing rebar at the location of the influent sump for the Midland RTF

Contracts

New contracts: None to report.

Amendments to existing contracts: None to report.

Change orders:
Full-scale ammonia/phosphorus removal: Contract with Ridley Electric Company amended for various modifications including rewiring pressure switches, additional light fixtures, and providing power and control wiring to overhead coiling doors. Contract amendment amount: $90,031.00. Executed 9/6/05.

Legislative action

Action items of the County Legislature in September: No items.

Upcoming for October legislative session: Approving the classification of a Type I action under the State Environmental Quality Review Act for the purpose of obtaining EFC funding, declaring lead agency status, accepting the long environmental assessment form, and making and declaring a negative declaration for the biosolids handling improvements Project.

Upcoming for October committee: No items.
 
Pouring concrete: Midland RTF construction site at right, Onondaga Creek in center
Pouring concrete: Midland RTF construction site at right, Onondaga Creek in center

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds:
Full-scale ammonia/phosphorus removal: Received request for retainage in the amount of $4,733,120 on 9/23/05 for total received of $47,331,203.
Total received to date in State Bond Act funds, $85,051,323.

Federal EPA funds

Midland Avenue Phase II conveyances & RTF Received requests in the amounts of $254,827 on 9/1/05 and $260,135 on 9/8/05 for total received of $6,970,323.
Full-scale ammonia/phosphorus removal: Received request in the amount of $68,652 on 9/8/05 for total received of $51,277,064.
Total received to date in Federal EPA funds, $58,247,387.

Federal Army Corps of Engineers funds

None to report.
Total received to date from U.S. Army Corps of Engineers funds: $7,069,365.

Loans

The following reimbursement payments were received from EFC during September:
Midland Avenue Phase II conveyances & RTF: Received request #11 in the amount of $919,956.45 on 9/2/05 for total received of $15,000,000.

Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $159,069,198 (short term), $10,303,528 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Lake Improvement Project Office
Grants and loans applied for—not yet approved
Grants received
Financial status report

—Midland photos by Ken Jackson


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection