Go to home page
Go to home page
Pouring concrete in underground storage tank of Midland RTF
Pouring concrete in underground storage tank of Midland RTF

Monthly report—August 2005

Four CSO points closed
 

Highlights of the month

  • Work activities on the Midland Phase II project during August included:
    • Continued pouring of the vertical walls for the underground disinfection tank that was begun in June. About 95% of the walls are complete with a total of 2858 cubic yards of concrete poured.
    • Excavation of soil material continued for the underground storage tank area that has now reached the final subgrade elevation.
    • Concrete pours began on August 4 with the first horizontal base mat.
    • Dewatering of the site continues.
    • Installation of sheeting along the 144-inch pipeline route continued with 410 linear feet installed to-date.

  • Work on the Tallman-Onondaga sewer separation project has been completed with punch list items sent to contractor. Street restoration was completed this month on Lincoln Avenue, which was the last remaining street to be restored in the project. Installation of sewers is complete in all four CSO basins, and cured-in-place liner installed where designed in Onondaga Avenue in basin 046A and along Eloise Terrace in basin 046B.
     
    This project eliminates four existing combined sewer overflows that had discharged into Onondaga Creek.
  • On August 22, the County forwarded the Harbor Brook CSO Abatement Project Facility Plan (Aug 2005) final draft facilities plan and Harbor Brook Environmental Information Document (Aug 2005) for the Harbor Brook combined sewer overflow abatement project to the NYSDEC and placed copies of the report in libraries in the project area. Copies were also mailed to city councilors and county legislators. Public meetings are scheduled for September.

Progress of projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ Completion date for ammonia full-scale—11/3/03—revision requested)
(ACJ Completion date for phosphorus removal stage II—4/1/05—on schedule)

All major construction work on the project is now complete, and contractors are working on punch list items.

Activities related to start-up of HRFS phosphorus removal system:

  • BAF effluent is now flowing through the HRFS influent channel, through all four trains and the effluent channel.
  • The 30-day performance test on the HRFS facility began in February and was completed in March. Results are under review and analysis by the County and the project's consultant, EEA.
  • October 1 is the target to initiate testing under the next step of the phosphorus pilot study.

The ammonia removal/phosphorus removal upgrade to Metro was fully completed in 2004. This project is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive effects on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Tallman-Onondaga sewer separation (CSO)

(ACJ milestone date July 1, 2012 completion)
Lincoln Avenue, paving complete (from Midland)
Lincoln Avenue, paving complete (from Midland)

Construction continues. By the end of August, the following were completed on this project:

  • Placement of all mainline sewers and new storm sewers and laterals in all four basins is completed.
  • Cured-in-place pipe liner was installed in combined sewers along Onondaga Avenue and Eloise Terrace.
  • Street restorations are complete.
  • Post-construction videotapes are complete in all basins.

This project separated four combined sewer areas in the Tallman-Midland-Onondaga Avenue area and eliminated CSOs 038 and 040 in the Tallman-Midland area and 046A and 046B near Onondaga Avenue on the city's west side. C.O Falter was the successful bidder on the contract.

The total construction of the project was estimated at $4.9 million with 70%-30% reimbursement from the U.S. Army Corps of Engineers. Under this project, new sewers were installed and, in most areas, existing combined sewers were converted for use by stormwater only. Four sewer overflow discharge points (038,040, 046A, and 046B) no longer discharge a combination of untreated sewage and stormwater to Onondaga Creek.

Midland conveyances and RTF (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07, milestone revisions requested)

Construction continues

Workers at the bottom of the Midland underground storage tank
Workers at the bottom of the Midland underground storage tank

Work continued this month on the placement of vertical concrete walls for the underground disinfection tank. By the end of the month, approximately 95% of the walls for the tank had been poured—totaling 2858 cubic yards of concrete.

Excavation work continued for the underground storage tank that has reached the final subgrade elevation in the southwest and northern quadrants with all tie-backs for the support of excavation system installed.

Dewatering of the site continued with discharge through an integrated header system.

Installation of sheeting continued along the route of the CSO pipeline. So far, about 410 linear feet of steel sheeting have been installed along this 144-inch pipeline route that will convey combined sewer flow to the storage and treatment facility.
Driving an 8-ft casing pipe in the bottom of a tank at Midland (July 2005)
Driving an 8-ft casing pipe in the bottom of a tank at Midland (July 2005)

As of August 31, 366 calendar days were expended on the project which is 29.8% of the total contract days of 1225, and $14,835,426 has been expended on the four prime contractors.

Upcoming work

Work anticipated for September 2005 includes:

  • Completion of the wall pours for the underground disinfection tank
  • Continued excavation of the underground storage tank to subgrade
  • Continuation of installation of the storage tank slabs and start of wall pours
  • Continued sheet driving for the 144-inch CSO conveyance pipe
  • Installation of sheeting for the 66-inch Bellevue Avenue regulator
  • Installation of bypass for 36-inch water line.

Midland Phase III activities

  • Phase 1A and Phase 1B archeological work plan completed by subconsultant and under review by EEA
  • Draft geotechnical data report completed by subconsultant and under review by EEA
  • Draft supplemental environmental information document completed by subconsultant and under review by EEA
  • 25% plan and profile design continues, engineering report and basis of design being prepared
  • Planning continues for part two of the geotechnical investigation program.

Projects in facility planning stage

Clinton conveyances and RTF (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—milestone revision requested.)

  • Following review of the comments received from the State DEC (dated May 27, 2005) on the Clinton Street CSO Abatement Project Facility Plan (Feb 2005 draft) and accompanying Clinton CSO Abatement: Environmental Information Document (Feb 2005), the County responded to the comments in a letter dated July 22, 2005. Following DEC's review of the response, the document will be finalized.
     
    The Facility Plan recommends construction of a regional treatment facility using vortex technology and high-rate disinfection with dechlorination at the Clinton station site. Conveyance pipes will connect the CSOs to the facility and also serve as inline storage.
  • The County issued two requests for proposals on April 22 concerning the Clinton and Harbor Brook CSO abatement projects. One RFP covers design, engineering and construction services for the regional treatment facilities. The second RFP covers design, engineering, and construction services for the conveyances associated with each project.
     
    Proposals were received on May 27, and the County sent the notice of award to EEA and CDM/C&S on August 5 and is currently in the process of finalizing the contracts:
    • EEA was awarded the design services contract for
    • the regional treatment facilities.
    • CDM/C&S was awarded the design contract for the
    • conveyances associated with each project.
    Regarding the regional treatment facilities, the contract for Clinton RTF covers only predesign services including the archeological and geotechnical work and the contract for Harbor Brook will cover all design services.

The initial draft facility plan was released to the public in March 2002. The 2004 plan includes a specific recommendation for technology and siting. The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams streets to be served by a Clinton area facility located near downtown Syracuse. The facility plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility and includes a recommended plan and site behind the elevated railroad tracks from the Armory Square area.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—not implementable—milestone revision requested )

Final draft facilities plan and EID submitted to DEC

Watershed of Harbor Brook
Watershed of Harbor Brook

On August 22, the County forwarded copies of the Harbor Brook CSO Abatement Project Facility Plan (Aug 2005) and the accompanying Harbor Brook Environmental Information Document (Aug 2005) to the State DEC following receipt and response to DEC's review and comments. Copies were placed in area libraries and sent to city councilors and county legislators. The plan specifies a recommended alternative which includes storage and treatment at two regional facilities (one near Grand Avenue and Delaware Street and the other on State Fair Boulevard), upgrading of two pumping stations, and five floatables control facilities.

Public meetings on the Facility Plan and Environmental Information Document were scheduled for September 14 and 15.

Request for proposals issued for next steps

The County issued two requests for proposals on April 22 concerning the Clinton and Harbor Brook CSO abatement projects. One RFP covers design, engineering, and construction services for the regional treatment facilities, and the second RFP covers design, engineering, and construction services for the conveyances associated with each project. Proposals were received on May 27, and the County sent the notice of award to EEA and CDM/C&S on August 5. County personnel are finalizing the contracts.

EEA was awarded the design services contract for the regional treatment facilities and CDM/C&S was awarded the design contract for the conveyances associated with each project. Regarding the regional treatment facilities, the contract for Clinton RTF covers only predesign services including the archeological and geotechnical work; the contract for Harbor Brook covers all design services.

The initial draft Harbor Brook facility plan was released in March 2002. The draft plan outlined and evaluated alternative technologies and sites for facilities to abate and treat the eighteen CSOs that release into Harbor Brook. The current Facility Plan recommends specific technologies and sites.

Other activities

Onondaga Lake Partnership

The County continues to be an active member of the Lake Partnership with participation in the Executive Committee, the Project Committee, and the Outreach Committee.

A display was put together this month for use by the Outreach Committee at a booth for the State Fair. Articles on the Midland project and the leaf bag program were written and photos supplied for the Partnership's upcoming newsletter.

Completed projects

Major milestones met for CSO interim projects

The following is a summary of the projects completed under Appendix B pages 10-12 of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.


 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Sampling conducted this month included:

  • Routine biweekly tributary sampling conducted on August 9 and 23
  • Special weekly double lake samplings of the nearshore and South Deep completed on August 2, 8, 17, 22, and 30
  • Special high-flow sampling event was completed on August 31. With this event, the County has completed five of its required minimum of five tributary high-flow events to be sampled annually.

Biological monitoring

The following fisheries-related sampling took place as required under the AMP:

  • Biweekly pelagic larvae sampling on week of August 1. This completed event 8 of 8 required pelagic larvae sampling.
  • Juvenile seine event 3 of 6 for littoral young-of-the-year during the week of August 11. Dr. John Ferrante of NYSDEC accompanied the sampling crew on August 12. Initiated event 4 of 6 for the littoral young-of-the-year the week of August 29.
  • Attended the weekly Wednesday night bass tournaments on August 3, 7, and 10 to collect weigh-in data including length and tag recapture data
  • Completed identification and QA/QC of larval fish collected during the ’05 monitoring season
  • Completed event 2 of 3 for the Onondaga Creek fisheries assessment with tributary backpack electrofishing on August 18 and 19.

Contracts

New contracts: None to report.

Amendments to existing contracts: Clinton Street CSO abatement:
Contract with Environmental Engineering Associates, LLP (EEA) amended for assistance in public outreach programs
Contract amendment amount: $5,130.00. Executed 8/9/05.

Change orders: none to report.

Legislative action

Action items of the County Legislature in August: No items.

Upcoming for September legislative session: No items.
Upcoming for September committee: No items.

Funding

Grants

State Bond Act funds:
Payments received this month from State Bond Act funds: None to report.
Total received to date in State Bond Act funds: $80,318,203.

Federal EPA funds: None to report.
Total received to date in Federal EPA funds: $57,663,773.

U.S. Army Corps of Engineers funds: None to report.
Total received to date from U.S. Army Corps of Engineers funds: $7,069,365.

Loans

The following reimbursement payments were received from EFC during August: None to report.
Total reimbursement monies received to date through EFC loans for the funded ACJ projects: $158,149,241 (short term), $10,303,528 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Lake Improvement Project Office
Grants and loans applied for—not yet approved
Grants received
Financial status report

—Midland photos by Ken Jackson


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection