Go to home page
Go to home page
New portion of 54-inch Main Interceptor Sewer at Midland
New portion of 54-inch Main Interceptor Sewer at Midland

Monthly report—April 2005

2005 sewer separation starts
 

Highlights of the month

  • During April, construction work on Phase II of the Midland RTF and Conveyances project continued.
    • Work focused on completing replacement of a section of the Main Interceptor Sewer that crosses the project site. The pipe is being replaced in two sections. The first section on the northern part of the site was completed last month. Work was begun last month on the second section to be replaced and continued this month. So far, work completed on the second section includes removal of the existing pipe, hook-up of the bypass system to this section, and beginning installation of the new 54-inch HDPE pipe. Sheeting, bracing, and excavation to the top of the pipe was completed during March.
    • Also, 26,000 tons of soil material were excavated for the disinfection tank and continuation of the support of excavation system including the second level of tie-backs in the area.
    • A new traffic light was installed on South Avenue near the Southwest Community Center.
    • Midland Avenue was closed between Bellevue and West Castle streets. Notifications were distributed to emergency agencies and bus operations on April 27. Buses had already changed routes because of construction detours caused by the nearby Tallman Street sewer separation project. This portion of Midland will remained closed until June 2006 to allow construction to take place.

  • Under contract with the County, Alpha Boats began its 2005 season of trash removal in the Inner Harbor and along Creek and the immediate lakeshore during April. The vessel and crew worked well last year collecting over 21 tons of floatable debris. During April and May, the boat is on a once-a-week collection schedule.
  • Meeting held on April 26 between County representatives and officers of the Armory Square Association regarding the Clinton CSO Abatement Plan. Various mitigation measures were discussed.
  • Requests for proposals were issued by the County on April 22 for the engineering, design, and construction services for the Clinton and Harbor Brook CSO projects as described in the recently released facilities plans. A pre-proposal meeting was scheduled for May 10, and proposals are due on Friday, May 27.
    Sewer separation, 2004
    Sewer separation, 2004

  • Work recommenced this month on the Tallman-Onondaga sewer separation project following the winter hiatus. Work will include finishing remaining separation activities and final street restorations. This project is designed to eliminate four existing combined sewer overflows that currently discharge to Onondaga Creek.

Progress of projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ Completion date for ammonia full-scale—11/3/03—Revision requested)
(ACJ Completion date for Phosphorus Removal Stage II—4/1/05—on schedule)

Construction. All major construction work on the project is now completed and contractors are working on punch list items.

Activities related to the start up of the HRFS Phosphorus Removal System.

  • BAF effluent is now flowing through the HRFS influent channel, through all four trains and the effluent channel.
  • The 30-day performance test on the HRFS facility began in February and was completed in March. Results are under review and analysis by the County and the project's consultant, EEA.
  • October 1 is the target to initiate testing under the next step of the Phosphorus Pilot Study.

Installing the forms for the concrete fillets in the HRFS settling tanks, April 2004
Installing the forms for the concrete fillets in the HRFS settling tanks, April 2004

The Ammonia Removal/Phosphorus Removal Upgrade to Metro was fully completed in 2004. This project is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive impacts on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Tallman-Onondaga sewer separation (CSO)

(ACJ milestone date July 1, 2012 completion)

Construction recommences after winter shut down. Construction began again on this project on April 18th following shut down of this project during the winter months.

During April, the following activities took place: work was initiated on the Tallman Street sewers and cured-in-place pipe liner was completed along Onondaga Ave. and Eloise Terrace. The contractor will be completing post construction videotapes along Onondaga Ave. and Midland Ave. during May prior to final road restoration that includes milling and placement of the top course of asphalt. In the fall of '04, binder course was placed on all of the roads disturbed by construction to date and final road restoration was planned for this spring.
Onondaga Avenue during sewer separation in November 2004
Onondaga Avenue during sewer separation in November 2004

This project will separate four combined sewer areas in the Tallman/Midland/Onondaga Ave. area and eliminate CSOs #038 and #040 in the Tallman/Midland area and #046A and #046B near Onondaga Ave. on the City's west side. C.O Falter was the successful bidder on the contract.

The total construction of the project is estimated to cost $4.9 million with 70-30 reimbursement from the U.S. Army Corps of Engineers. Under this project, new sewers will be installed and in most areas, existing combined sewers will be converted for use by storm water only. When finished, these four sewer overflow discharge points (# 038,040, 046A and 046B) will no longer discharge a combination of untreated sewage and storm water to Onondaga Creek.

Midland Conveyances and Regional Treatment Facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07 Milestone revisions requested)

Construction continues

Construction during the month primarily focused on work related to the replacement of the 48" Main Interceptor Sewer where it crosses the construction site. The pipe will be replaced in two sections. During March, the first section of MIS on the northern end of the site was replaced and the excavation refilled. Work that began on replacement of the second section in March continued during April. Work completed this month included the removal of the existing MIS in that area and installation of a portion of new 54" pipe along with installation of three manholes.
Workers installing internal steel supports in the Midland trench site, April 2005
Workers installing internal steel supports in the Midland trench site, April 2005

In addition, a total of 26,000 tons of soil material was excavated and hauled off site from the area of the future disinfection tank for the facility.

Construction conditions encountered caused the closure of Midland Ave. between Bellevue and West Castle Streets about one month earlier than previously planned. Notifications of the closure were distributed to bus companies and emergency services on April 27th. This portion of Midland will remain closed until June 2006. Bus routes had been previously detoured due to nearby construction activities on the Tallman Sewer Separation project.

Public participation

  • A four-page newsletter compiled by the County was mailed to over 300 businesses and residences and local officials in the vicinity of the Midland project. The newsletter contained detailed information on the project and upcoming construction activities along with photos from the site.
  • Presentation given by Sue Miller to class at Syracuse University on the Midland Project on April 14th.

Traffic Light installed

Installation was completed this month on the a traffic light on South Ave. to improve the safety for pedestrians crossing in the vicinity of the Southwest Community Center. The County agreed to install this light because additional traffic is being detoured on South Ave. due to nearby construction of the Midland project.

Upcoming construction activities

  • Completion of sheeting and replacement of the second section of the main interceptor sewer that crosses the site.
  • Continuation of excavation on the main facility site.
  • Start of sheeting for new CSO conveyance pipe.

Projects in facility planning stage

Clinton Conveyances and Regional Treatment Facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—Milestone revision requested.)

  • Clinton Street CSO Abatement Project Facility Plan (Feb 2005 draft) and accompanying were submitted to the State DEC for review and comment on March 1, 2005. The report recommends construction of a regional treatment facility using vortex technology and high-rate disinfection with dechlorination at the Clinton station site. Conveyance pipes will connect the CSOs to the facility and also serve as inline storage.
  • Presentation on project given to Environmental Protection Committee of the County Legislature on April 12.
  • Contacts continued with a meeting on April 26 between the County and a subcommittee of the Armory Square Association to discuss the status and effects of the Facility Plan. Issues discussed with County project staff including the project's proposed schedule and mitigation measures.
  • The County issued two requests for proposals on April 22 concerning the Clinton and Harbor Brook CSO abatement projects. One RFP covers design, engineering, and construction services for the regional treatment facilities. The second RFP covers design, engineering, and construction services for the conveyances associated with each project. Proposals are due May 27.
  • Press coverage was received this month on the proposed project.

The initial draft facility plan was released to the public in March 2002. The 2004 plan includes a specific recommendation for technology and siting. The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams streets to be served by a Clinton area facility located near downtown Syracuse. The Facility Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility and includes a recommended plan and site near the Armory Square area.

Harbor Brook CSO abatement project (CSO)

completion date for in-water system—7/1/02—Not implementable—Milestone Revision requested )

Facility plan and EID submitted to DEC

The County forwarded copies of the Harbor Brook CSO abatement facility plan and the accompanying environmental information document to DEC for review and comment on December 30, 2004. The plan specifies a recommended alternative which includes storage and treatment at two regional facilities (one near Grand Avenue and Delaware Street and the other on State Fair Boulevard), upgrading of two pumping stations, and five floatables control facilities.

DEC Comment letter received

In a letter dated March 29, DEC forwarded comments to the County on the draft facility plan and EID submitted to DEC in December 2004. The comments are under review by the County.

RFPs issued for next steps

The County issued two requests for proposals on April 22 concerning the Clinton and Harbor Brook CSO abatement projects. One RFP covers design, engineering, and construction services for the regional treatment facilities, and the second RFP covers design, engineering and construction services for the conveyances associated with each project. Proposals are due May 27.

The initial draft Harbor Brook facility plan was released in March 2002. The draft plan outlined and evaluated alternative technologies and sites for facilities to abate and treat the eighteen CSOs that release to Harbor Brook. The 2004 plan recommends specific technologies and sites.

Other activities

Midland Phase III activities

Design activities are underway by EEA and their subconsultants for Phase III of the Midland project that includes construction of a CSO conveyance to pick up six overflow points between Dearborne Avenue and Newell Street.

During April, subconsultant Brown and Caldwell continued to conduct computer modeling analyses of the proposed conveyance to determine necessary pipe sizes.

The environmental services subconsultant completed site walk-through and initiated work on the supplemental environmental information document. Initiated design of regulator connections and a street cut has been applied for related to future necessary soil borings for geotechnical testing.

Completed projects

Major milestones met for CSO Interim Projects. The following is a summary of the projects completed under Appendix B pages 10-12 of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.


 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Summary of sampling program

  • Routine biweekly tributary sampling conducted on April 19 and an extended tributary sampling was completed on April 5 that also qualified as a high-flow event.
  • Sampling in the South Deep of the lake was completed on April 14, and a double lake sampling of the North and South Deep was completed on April 26.
  • No river sampling conducted this month.
  • With completion of a high-flow sampling event on April 5, the County has completed four of its required minimum of five tributary high-flow events to be sampled annually.

Biological monitoring

During the week of April 25, the County completed its first pelagic larvae sampling event under the fisheries program. Eight such samplings are required annually.

Proposed 2005 Ambient Monitoring Program approved by DEC

A letter was received March 29 from DEC giving approval of the County's proposed 2005 Ambient Monitoring Program. The official monitoring season began April 1.

Contracts

New contracts: None to report
Amendments to existing contracts: None to report.

Change orders

Full-scale ammonia/phosphorus removal.
Contract with Burns Brothers, Inc amended for various modifications including relocation of water supply and drain, underground pipe supports, and additional time needed to complete project.
Contract amendment amount: $81,813.27. Executed 4/27/05.

Legislative action

Action items of the County Legislature in April: No items.
Upcoming for May legislative session: No items
Upcoming for May committee: No items.

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds: None to report.
Total received to date in State Bond Act funds: $80,318,203.

Federal EPA funds

None to report
Total received to date in Federal EPA funds: $51,826,514.

Federal Army Corps of Engineers funds

Sewer separation (CSOs 038, 040, 046A, and 046B): Received request #4 in the amount of $118,123.15 on 4/27/05 for aggregate total received on all sewer separation projects $3,663,365.
Total received to date from U.S. Army Corps of Engineers funds: $7,069,365.

Loans

The following reimbursement payments were received from EFC during the month of April:

Midland Avenue Phase II Conveyances & RTF
Received request #6 in the amount of $687,422.69 on 4/19/05 for total aggregate received of $8,182,237.93.
Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $152,197,436 (short term), $10,205,703 (long term).

Appendixes

 Chronology of project construction starts
 Contractors for construction projects
Lake Improvement Project Office
Grants and loans applied for—not yet approved
Grants received
Financial status report

—Photos by Joe Lorah


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection