Go to home page
Go to home page
Installing sheeting on perimeter of Midland RTF site. One million pounds of sheeting have been installed.
Installing sheeting on perimeter of Midland RTF site. One million pounds of sheeting have been installed.

Monthly report—January 2005

Sheeting installed at Midland
 

Highlights of the month

  • During January, construction work on Phase II of the Midland RTF and conveyances project focused on completing installation of sheeting around the existing 48-inch Main Interceptor Sewer. All of the 54-inch replacement pipe and necessary manholes, fittings, and pump for the bypass system are on the site and ready to go. The contractor also began installing the temporary power service that will operate the bypass pumping operation.
  • As scheduled, Krüger began the required 30-day cold weather performance testing on the BAF (ammonia removal process) at Metro on January 8. The County has continued to operate the BAF process since January 2004 with the system successfully achieving or exceeding ACJ ammonia removal requirements.
  • The Metro plant's full flow of BAF-treated effluent continued to be put through the new high-rate flocculated settling (HRFS) phosphorus removal system with preparations this month for the 30-day performance test on the HRFS scheduled to begin on February 8.
  • Work is still suspended on the Tallman-Onondaga sewer separation project due to winter weather conditions. Work will recommence in the spring and include finishing remaining separation activities and final street restorations. This project is designed to eliminate four existing combined sewer overflows which currently discharge into Onondaga Creek.
  • The County forwarded copies of the Harbor Brook CSO abatement facility plan and the accompanying environmental information document to DEC on December 30, 2004. The plan is currently under review by DEC.

Progress of projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ completion date for ammonia full-scale—11/3/03—Revision requested)
(ACJ Completion date for Phosphorus Removal Stage II—4/1/05—on schedule)

Construction

All major construction work on the project is now completed, and contractors are working on punch list items.

Start-up of HRFS phosphorus removal system

BAF effluent is now flowing through the HRFS influent channel—through all four trains and the effluent channel.

Krüger continued work this month on equipment testing, adjusting chemical, polymer and sand dosages as well as adjusting and calibrating the automated control system and SCADA system in preparation for the 30-day performance test to begin on February 8.

Plant Operations Center

All equipment and personnel were moved from the old Plant Operations Building into the new Plant Operations Center on the weekend of November 13 and have been fully functioning from the new facility since that time. The electrical contractor and representatives of USFilter Controls Division returned to the site in late January to complete a few remaining items in the final integration of the SCADA systems and computerized controls.

The ammonia removal/phosphorus removal upgrade to Metro was fully completed in 2004. This project is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive impacts on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Tallman-Onondaga sewer separation (CSO)

(ACJ milestone date July 1, 2012 completion)

Construction shut down for winter

Construction was shut down due to winter weather on this project to separate four combined sewer areas in the Tallman-Midland-Onondaga Avenue area. Binder course was placed on all of the roads disturbed by construction this fall, and final road restoration (including milling and top course) is planned for the spring.

This project is designed to eliminate CSOs 038 and 040 in the Tallman-Midland area and 046A and 046B near Onondaga Avenue on the city's west side. C.O. Falter was the successful bidder on the contract.

The total construction of the project is estimated to cost $4.9 million with 70%-30% reimbursement from the U.S. Army Corps of Engineers. Under this project, new sewers will be installed and, in most areas, existing combined sewers will be converted for use by stormwater only. When finished, these four sewer overflow discharge points (038, 040, 046A, and 046B) will no longer discharge a combination of untreated sewage and stormwater to Onondaga Creek.

Midland conveyances and regional treatment facility (CSO)

Two plastic pipes bypass the Main Interceptor Sewer to permit replacement of the 48
Two plastic pipes bypass the Main Interceptor Sewer to permit replacement of the 48" brick-concrete MIS with a 54" HDPE pipe.

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07 Milestone revisions requested)

Construction continues

Construction during the month primarily focused on work related to the replacement of the 48-inch Main Interceptor Sewer in the area of construction of the treatment and storage facility. Activities included continuing to install the sheeting and bracing for the support-of-excavation around the existing Main Interceptor Sewer. Once the sheeting is in place, the area will be excavated, and the existing concrete and brick sewer will be replaced with a new 54-inch HDPE pipeline. A temporary pipeline will be installed to bypass the MIS during construction of the new pipeline. All necessary replacement pipe, manholes, fittings and the bypass system with pipe, pump, and manifold are on site and ready to be placed when sheeting and bracing is completed on the full extent of the MIS through the site.

Excavation for the main area of the treatment and storage facility may begin during February.

Other construction-related activities included beginning the installation of temporary power service for the bypass operation, preparation of the base pad for the new pole barn for Centro, and coordination activities with all utility companies concerning the future work planned at the intersection of Blaine Street and Midland Avenue.

Two dewatering wells have been installed and production rates were tested. Results are being analyzed.

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—Milestone revision requested.) Work is underway to finalize the facility plan and accompanying environmental information document for submittal to State DEC for review and comment as well as for public distribution soon.

Contacts continue between County and a subcommittee of the Armory Square Association to discuss the status and impacts of the Clinton facility plan. Issues discussed with County project staff including the project's proposed schedule and mitigation measures.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams Streets to be served by a Clinton area facility located near downtown Syracuse. The facility plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility and will propose a recommended plan and site.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system—7/1/02—Not implementable—Milestone Revision requested )

Facility plan and EID submitted to DEC

The County forwarded copies of the Harbor Brook CSO abatement facility plan and the accompanying environmental information document to DEC for review and comment on December 30, 2004. The plan specifies a recommended alternative that includes storage and treatment at two regional facilities, upgrading of two pumping stations, and five floatables control facilities.

The initial draft Harbor Brook CSO Abatement Facilities Plan was released in March 2002. The draft plan outlined and evaluated alternative technologies and sites for facilities to abate and treat the eighteen CSOs that release to Harbor Brook. The 2004 Plan identifies specific technologies and sites.

Other activities

Quarterly reports forwarded to DEC

Maltbie Street facility, located on Onondaga Creek bank
Maltbie Street facility, located on Onondaga Creek bank

Quarterly performance reports were forwarded to DEC from the County in January on the following completed projects:
 
- Burnet floatables control facility
- Butternut floatables control facility
- Erie Boulevard storage system
- Hiawatha regional treatment facility
- Maltbie Street floatables control facility
- Teall Brook floatable control facility.

Completed projects

Major milestones met for CSO interim projects.
The following is a summary of the projects completed under Appendix B pages 10-12 of the Amended Consent Judgment. Each of these ten CSO-related projects had a major milestone completion date of July 1, 2002. Some of these interim projects were completed well ahead of the major milestone date, and all except two met the major milestone date.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.


 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient monitoring program

Monthly report—January   2005

Summary of sampling program

Sampling conducted this month included:

  • Routine biweekly tributary sampling conducted on January 11 and 25
  • Lake sampling was conducted on January 4 in the South Deep
  • No river sampling conducted this month
  • A minimum of five high-flow tributary sampling events are required each year and to-date five events have been sampled (3/3, 3/8,5/25, 8/30, and 9/9).

Fisheries sampling activities conducted this month included the sorting of macroinvertebrates from the tributary samples collected in July 2004 was completed. Ten sites were sampled with forty samples requiring sorting.

Other activities

Additional monies may be available from the U.S. Army Corps of Engineers to cover an additional sewer separation project in Syracuse. Information on the proposed area (CSO 050 near South Avenue) and the required intermunicipal agreement is being compiled.

Contracts

New contracts: None to report.

Amendments to existing contracts: None to report.

Change orders: Full-scale ammonia/phosphorus removal:

  • Contract with The Pike Company amended for costs associated with concrete encasing piping in HRFS, BAF & Plant Operations Center.
    Contract amendment amount: $85,595.00. Executed 1/7/05.
  • Contract with Burns Brothers, Inc. amended for various modifications including installation of booster pump on the sand recirculation pumps in the HRFS and installation of permanent water connection for the polymer system.
    Contract amendment amount: $58,950.39. Executed 1/7/05.

Legislative action

Action items of the County Legislature in January: No items.

Upcoming for February legislative session: Amending the 2005 county budget to accept funds from Niagara Mohawk for environmental remediation on the ammonia/phosphorous removal project ($4,300,000).

Upcoming for February committee: No items.

Funding

Grants

State Bond Act funds
Payments received this month from State Bond Act funds: None to report.
Total received to date in State Bond Act funds: $70,402,415.

Federal EPA funds
Payments received this month from Federal EPA funds: None to report.
Total received to date in Federal EPA funds: $49,218,599.

Federal Army Corps of Engineers funds: None to report
Total received to date from U.S. Army Corps of Engineers funds: $5,995,576.

Loans

The following reimbursement payments were received from EFC during the month of January:
Midland Ave RTF & Phase II Conveyances: Received Request #3 in the amount of $992,376.98 on 1/10/05 and Request #4 in the amount of $2,235,015.76 on 1/24/05 for aggregate total received of $5,490,586.35.
Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $148,567,732 (short term), $9,216,380 (long term).

: Photos by Joe Lorah and Bob Bellandi


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection