Go to home page
Go to home page
Storm drainage work at Metro—supporting the new ammonia and phosphorus removal facilities
Storm drainage work at Metro—supporting the new ammonia and phosphorus removal facilities

Monthly report—March 2004

UV system operating
 

Highlights of the month

  • The BAF system is reducing ammonia levels in the Metro effluent and is on target successfully to meet effluent compliance levels for ammonia by the ACJ date of May 1, 2004. The ammonia removal system (BAF—biological aerated filters) was put into operational mode with seeding of the filter beads in January.
  • Another project milestone was achieved this month with the completion of the 14-day performance period for the new ultraviolet disinfection system before April 1, 2004 as required by the DEC permit. This system is now disinfecting 100% of the BAF effluent.
  • Beneficial occupancy has been taken on the Secondary Effluent Pumping Station and the BAF facility.
  • Bids were opened on March 11 for the building demolition contract related to the Phase II Midland project which was put tor bid on February 10. A post-bid/pre-award meeting was held March 25 with apparent low bidder Empire Dismantlement Corporation. Letter of intent to award will be sent to contractor in April.
  • Bids were advertised for the construction contract for the Phase II Midland Regional Treatment Facility and conveyances on March 5, 2004. A pre-bid conference was held on March 24. Approval by DEC on plans and specifications was received March 17, 2004. Addendums prepared. Bid opening is currently scheduled for early May.
  • Planning underway for Onondaga Lake Partnerships third annual Lake Day to be held Saturday, June 5, 2004 at Onondaga Lake Park near the new Griffin Visitors Center.

Progress of projects under construction

Backwash pumps for the BAF
Backwash pumps for the BAF

Ammonia removal/phosphorus removal combined project (METRO)

(ACJ Completion date for ammonia full-scale 11/3/03 schedule revision requested)
(ACJ Completion date for phosphorus removal stage II 4/1/05 on schedule)

Summary of structural work

BAF structure (ammonia removal). All structural concrete work is complete.

HRFS facility (phosphorus removal). All structural concrete work is complete.

UV disinfection facility. All structural concrete work is complete.

Secondary effluent pump station. All structural concrete work at this facility is substantially complete.

Operations-Chemical Building. Structural concrete work is complete. Work continued on the installation of concrete masonry block with substantial completion accomplished this month. The brick veneer and glass block work continued on the Plant Operations Center entryway facing Hiawatha Boulevard. The masonry, brick veneer, and glass block work is now substantially complete on the Chemical Building.

Summary of mechanical work

BAF facility. The BAF facility continued to accept 100% of the Metro secondary effluent flow. Effluent ammonia levels continued to decline during the month as biomass grew.

HRFS facility. The mechanical work including installation of the process equipment and piping is now substantially complete. Work on insulation continued this month along with installation of the balance of PVC piping for process chemicals and installation of the power and control wiring for process equipment.

Secondary Effluent Pump Station. Mechanical work in this structure is substantially complete.

UV structure. The required 14-day performance testing was completed on the UV disinfection equipment.

Architectural work

BAF facility. Architectural work continued this month on this structure with installation of the BAF louvers and exterior alucobond panels. The work is 85% complete.
Workers install Alucabond panels on the east side of the UV facility
Workers install Alucabond panels on the east side of the UV facility

Other structures. Architectural work is substantially complete on the Secondary Effluent Pump Station, and the Low Lift Pump Station. This month, the floors were coated and walls painted in the outfall area of the UV structure. Remaining work on the UV facility include louvers, exterior wall panels, and flashing. On the Operations-Chemical Building, 90% of all the interior metal stud wall partitions were completed by the end of the month. Exterior wallboard was installed in preparation for the exterior wall panels on the chemical-operations center.

Other information

The contractor resumed work installing the storm drainage system on site.

The 14-day performance period for the boilers in the Low Lift Pump Station is underway.

Many meetings continue to be held on various aspects of the construction, punch list items, and start-up activities with appropriate contractors, consultants, and County personnel.
Pumps, rated at 500 horsepower, in the Secondary Effluent Pump Station
Pumps, rated at 500 horsepower, in the Secondary Effluent Pump Station

This is the largest and most costly project in the program and will have the greatest positive impacts on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro discharge.

This is the largest and most costly single project
in the Amended Consent Judgment program

and will have the greatest positive effect on the water quality of Onondaga Lake
by removing more ammonia and phosphorus
from the Metro effluent discharge.

Brighton Avenue sewer separation project (CSO)

(ACJ project milestone—January 1, 2012—project completed)
Pipe installation and restoration work completed: Under this $2.1 million project, 2864 feet of mainline sewer was installed in the streets along with 1760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. Lead water services encountered during sewer construction were replaced in the right-of-way by the County to reduce extent of lead services. With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater goes to Metro for treatment.

Projects in design stages

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date Phase II RTF—5/01/04 & Phase III conveyance—5/01/07 revisions requested)

Further work progresses on Phase II. During this month, the following were undertaken to progress the project:

  • Activities related to bidding the demolition contract for this project and activities related to finalizing the final plans and specifications of the documents for the construction phase of the project.
  • Meetings were held with CNYRTA concerning geotechnical issues and finalization of the purchase agreement, meetings with Syracuse Housing Authority (SHA), and preparation of a draft agreement between the County and SHA concerning housing and relocation of residents during construction.
  • Design engineers, EEA, finalized the design for the conveyance flushing system, continued to progress utility location identification, and prepared items for the bids and addendums.

Other meetings held

Additional meetings were held this month between County staff, program managers (CDM/C&S), and design engineers (EEA) regarding construction schedule, coordination, sequencing, and staff assignments.

Additional sewer separation areas (CSO)

Finalization of the bid documents for the next sewer separation project continues. The next CSOs slated for sewer separation are 038 and 040 in the Tallman-Midland area and 046A and 046B near Onondaga Avenue. Spectra Engineering continued this month to work on finalizing contract documents for the project.

The County plans to go to bid on this project in April. The intermunicipal agreement has been signed on this project by both the County and the City and approved through their respective legislatures.

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates Commence construction of conveyances and RTF May 1, 2003 milestone revision requested.)
Finalized environmental information document and SEQR-related information for Armory Square site. County and City officials met for discussions on project. No resolution reached.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams streets to be served by a Clinton area facility located in downtown Syracuse. The facility plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for in-water system 7/1/02. Not implementable. Milestone revision requested)
This month, the design consultants, Brown & Caldwell, worked on the following items:

  • Further development of environmental information document and SEQR-related information for the project by subconsultant EcoLogic.
  • Archeological consultant requested to finalize Phase IA archeological report and work plan for Phase IB for submittal to State Office of Historic Preservation.
  • Work to identify areas to be slated for archeological investigations within potential sites and confirm property owners to be notified
  • Maps created to construction extent for use by EcoLogic for EID, by Sear-Brown for traffic study, and by Hartgen for archeological investigations
  • On March 3, conducted field verification of locations of regulators, catch basins, and potential FCF sites for the middle basin combined sewer overflows
  • Developed cost analysis for middle basin FCFs as compared to sewer separation
  • Meetings with County staff to decide further monitoring needs and site size plans.

The draft Harbor Brook CSO Abatement Facilities Plan was released in March 2002. The draft plan outlines and evaluates alternative technologies including the in-water system for abating and treating the eighteen CSOs that release to Harbor Brook. This draft plan also identifies potential sites for CSO abatement facilities.

Other activities

Partnership activities continue

Plans began this month for Onondaga Lake Day to be sponsored by the Onondaga Lake Partnership on Saturday, June 5. County Outreach Committee representative, Sue Miller, was asked to lead planning for the day's events.

Onondaga Lake Partnership activities continue with County representatives taking part in meetings and discussions of the three committees plus the Executive Committee as a Senior Partner member of the Partnership.

Completed projects

Major milestones met for CSO interim projects

The year 2002 was important in the Amended Consent Judgment program because ten CSO-related projects met their major milestone completion date of July 1, 2002 (ACJ, Appendix B pages 10-12). Some of these interim projects were completed well ahead of the major milestone dates, and all but two met the major milestone. The Kirkpatrick Street Pump Station and the Harbor Brook In-water System required milestone extensions. New York State is reviewing the County's requests for the extensions.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.

Brighton Avenue sewer separation project (CSO)

(ACJ Project milestone—January 1, 2012—Project completed 2003)
Pipe installation and restoration work was completed. Under this $2.1 million project, 2,864 feet of mainline sewer was installed in the streets along with a total of 1,760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods. The project was completed on time and under budget.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. The County replaced lead water services encountered during sewer construction to reduce lead services.

With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater from these areas goes to Metro for treatment.

Major milestones met for Metro interim projects

Under Appendix A of the ACJ, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date and most well ahead of schedule. The projects are listed below by date completed:
 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient monitoring program

Activities this month include:

  • Transmitted the proposed 2004 year Ambient Monitoring Sampling Plan to DEC and ACJ parties on March 4, 2004 for implementation on April 1, 2004.
  • Lake Technical Advisory Committee meeting held on March 31. Meeting focused on 2003 sampling results and 2004 program plans.

Sampling conducted this month included:

  • Two special high-flow tributary sampling events held March 3 and March 8, 2004. (This completes two of the five required for the year.)
  • Quarterly extended tributary sampling event completed March 23
  • Lake winter sampling conducted March 31 following ice-out during previous weekend
  • River monitoring on March 18 in four locations including lake outlet, Seneca River at Plainville Bridge, Seneca River at Route 48 bridge, and Seneca River at Route 370 bridge.

Contracts

New contracts: None to report.

Amendments to existing contracts: Midland Avenue conveyances & RTF
Contract with Environmental Engineering Associates, LLP amended to conduct an exploratory utility location program. Contract amendment amount: $22,000. Executed 3/11/04.

Change orders: Full-scale ammonia/phosphorus removal
Contract with The Pike Company amended to include installation of booster pump, changes to APL piping, and joint construction in BAF walls. Contract amendment amount: $90,806.00. Executed 3/11/04.
Contract with The Pike Company amended to include installation of additional rebar, raising chimney on Low Lift Pump Station, and installation of nonrising gates for BAF cells. Contract amendment amount: $96,868.00. Executed 3/31/04.

Sewer separation (CSOs 053/054):
Contract with C.O. Falter Construction Corp. amended to include additional costs of plumbing permits and additional asphalt needed for restoration. Contract amendment amount: $43,753.54. Executed 3/18/04.

Legislative action

Action items of the County Legislature in the month of March:
Authorizing an intermunicipal agreement with the City of Syracuse for the Tallman Street sewer separation project.

Upcoming for April legislative session:
No Items.

Upcoming for April committee: - No items.

Funding

Grants

Main entrance to the Operations Building
Main entrance to the Operations Building

State Bond Act funds

Payments received this month from State Bond Act funds:
Full-scale ammonia/phosphorus removal request #6 in the amount of $5,588,621.62, Request #7 in the amount of $5,5685,383.55. Request #8 in the amount of $8,824,077.53 received on 3/23/04 for total aggregate received of $33,598,082.70. Total received to date in State Bond Act funds: $54,895,526.

Federal EPA funds

Payments received this month from Federal EPA funds:
Full-scale ammonia/phosphorus removal request #15 in the amount of $4,823,126 received on 3/19/04 for total aggregate received of $45,028,588. Total received to date in Federal EPA funds: $46,464,451.

Federal Army Corps of Engineers funds

None to report. Total received to date from U.S. Army Corps of Engineers funds: $5,490,428.

Loans

The following reimbursement payments were received from EFC during the month of March: None to report. Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $158,115,456 (short term), $9,088,289 (long term).

Metro photos by Joe Lorah


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection