Go to home page
Go to home page
Gallery level of BAF complex looking north
Gallery level of BAF complex looking north

Monthly report—February 2004

Ammonia levels reduced
 

Highlights of the month

  • On February 4, after 21 days of operation, the BAF system showed evidence of successful nitrification. As the system has come more and more on line with growth of biomass on the filtration media, the ammonia levels in the effluent have steadily declined. The system is on target successfully to meet effluent compliance levels for ammonia by the ACJ date of May 1, 2004. The ammonia removal system (BAF—biological aerated filters) was put into operational mode with seeding of the filter beads in January.
  • Work to finish the HRFS (phosphorous removal) portion of the facility continued this month with installation of sand recirculation pumps and process piping. About 95% of the process piping is complete to-date.
  • The construction documents for Phase II of the Midland Avenue Regional Treatment Facility and Conveyances Project were submitted to DEC on February 6. Upon DEC approval, the project will be put to bid.
  • The County put to bid the building demolition contract on February 10 for the Phase II Midland construction. A pre-bid meeting and site visit was held on the contract on February 18. Bids will be opened March 11.

 See construction photos from February.

Progress of projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ Completion date for Ammonia Full Scale—11/3/03—schedule revision requested)
(ACJ Completion date for Phosphorus Removal Stage II—4/1/05—on schedule)

Summary of structural work to date on major component facilities

BAF structure (ammonia removal): All structural concrete work is complete.

HRFS facility (phosphorus removal): All structural concrete work is complete.

UV disinfection facility: All structural concrete work is complete.

Secondary effluent pump station: All structural concrete work is substantially complete.

Operations-Chemical Building: Structural concrete work is complete. Work continued on the installation of concrete masonry block with substantial completion accomplished this month. The brick veneer work continued on the Chemical Building.

Summary of mechanical work this month

Effluent piping and sand recirculating piping in the HRFS effluent gallery
Effluent piping and sand recirculating piping in the HRFS effluent gallery

BAF facility: During February, a preliminary punch list prior to substantial completion was issued to contractors. All contractors were working on the list. The BAF facility continued to accept 100% of the Metro secondary effluent flow. Krüger continued to work on establishing effective levels of biomass in each of the eighteen BAF cells. Effluent ammonia levels declined during the month as biomass grew.

HRFS facility: The mechanical work continues ahead of schedule for the HRFS facility. Approximately 95% of the process piping is complete to-date in the HRFS facility. Ridley Electric is installing the balance of the lighting and is working on installing the power and control wiring for the process equipment. Work on insulation also continued this month.

Secondary Effluent Pump Station: Mechanical work in this structure is substantially complete.

UV structure: Performance testing was started on the UV disinfection equipment. Electrical work is substantially complete. HVAC contractor performed start up testing and balancing of equipment. Plumbing is substantially complete.

Architectural work this month

BAF facility: Architectural work continued this month on this structure with installation of the BAF louvers and exterior alucobond panels. The work is 85% complete.

Other structures: Architectural work is substantially complete on the Secondary Effluent Pump Station and the low lift pump station. This month, the floors were coated and walls painted in the outfall area of the UV structure. Remaining work on the UV facility includes louvers, exterior wall panels, and flashing. On the Operations-Chemical Building, 90% of all the interior metal stud wall partitions were completed by the end of the month. Exterior wallboard was installed in preparation for the exterior wall panels on the Operations-Chemical Building.

Other information

The contractor resumed work installing the storm drainage system on site. More than 75% of the drainage system is now complete with the contractor continuing to haul and dispose of excavated stockpile of material from the site.

Many meetings continue to be held on various aspects of the construction, punch list items, and start-up activities with appropriate contractors, consultants, and county personnel.

This is the largest and most costly single project
in the Amended Consent Judgment program
and will have the greatest positive effect on the water quality
of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Brighton Avenue sewer separation project (CSO)

(ACJ Project milestone—January 1, 2012—Project completed)

Pipe installation and restoration work completed: Under this $2.1 million project, a total of 2,864 feet of mainline sewer was installed in the streets along with a total of 1,760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. The County replaced lead water services encountered during sewer construction to reduce extent of lead services. With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater goes to Metro for treatment.

Projects in design stages

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07 Revisions requested)
Motor being lifted from pump base at Secondary Effluent Pump Station
Motor being lifted from pump base at Secondary Effluent Pump Station

Further work progresses on Phase II. During this month, the following activities were undertaken to progress the project: contract documents for building demolition were finalized and put to bid on February 10 with a pre-bid meeting on February 18, coordination meetings continued with CNYRTA regarding site impacts and restoration, design work continued on conveyance flushing system, finalized Phase II environmental assessment transmitted to County by consultant on February 27, and continued to progress completion of Phase II construction contract documents submitted to DEC on February 6.

Other meetings held. Additional meetings were held this month between County staff, program managers (CDM/C&S), and design engineers (EEA) regarding construction schedule, coordination, sequencing and staff assignments.

Additional sewer separation areas (CSO)

Finalization of bid documents for next sewer separation project continues. The next CSOs slated for sewer separation are #038 and 040 in the Tallman/Midland area and #046A and #046B near Onondaga Avenue. Spectra Engineering continued this month to work on finalizing contract documents for the project. The County plans to go to bid on this project this spring.

The County Legislature approved the intermunicipal agreement on this project at its early March meeting. Discussions continued during the month with the City to obtain approval of the agreement which needs Common Council approval before bidding the project. Voting on the agreement by the Council is anticipated for March.

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—milestone revision requested.)
Clinton combined sewer area
Clinton combined sewer area

Activities this month. The County's design consultant, EEA, worked with the County to finalize the facility plan with a recommended site and technology which was submitted to the County on February 27.

Continued development of environmental information document and SEQR-related information.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams streets to be served by a Clinton area facility located near downtown Syracuse. The facility plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for In-Water system- 7/1/02—Not implementable—Milestone Revision requested )

This month, the design consultants, Brown & Caldwell, continued to work on the following items:

  • Development of environmental information document and SEQR-related information for the project with sub-consultant, EcoLogic
  • Archeological consultant requested to finalize Phase IA archeological report and work plan for Phase IB for submittal to State Office of Historic Preservation
  • Work to identify areas to be slated for archeological investigations within potential sites and confirm property owners to be notified.

The Harbor Brook CSO Abatement Facilities Plan was released in March 2002. The draft plan outlines and evaluates alternative technologies including the in-water system for abating and treating the eighteen CSOs which release into Harbor Brook. This draft plan also identifies potential sites for CSO abatement facilities.

Other activities

Partnership activities continue

Onondaga Lake Partnership activities continue with County representatives taking part in meetings and discussions of the three committees plus the Executive Committee as a Senior Partner member of the Partnership. Current discussions focus on upcoming projects and use of Partnership budget funds.

Completed projects

Major milestones met for CSO interim projects

The year 2002 was important in the Amended Consent Judgment program because ten CSO-related projects met their major milestone completion date of July 1, 2002 (ACJ, Appendix B pages 10-12). Some of these interim projects were completed well ahead of the major milestone dates, and all but two met the major milestone. The Kirkpatrick Street Pump Station and the Harbor Brook In-water System required milestone extensions. New York State is reviewing the County's requests for the extensions.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.

Brighton Avenue sewer separation project (CSO)

(ACJ Project milestone—January 1, 2012—Project completed 2003)
Pipe installation and restoration work was completed. Under this $2.1 million project, 2,864 feet of mainline sewer was installed in the streets along with a total of 1,760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods. The project was completed on time and under budget.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. The County replaced lead water services encountered during sewer construction to reduce lead services.

With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater from these areas goes to Metro for treatment.

Major milestones met for Metro interim projects

Under Appendix A of the ACJ, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date and most well ahead of schedule. The projects are listed below by date completed:
 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient monitoring program

Installing fireproof sheeting along the south side of the Operations Building
Installing fireproof sheeting along the south side of the Operations Building

Activities this month include:

  • Submitted fourth quarter report for Ambient Monitoring Program for 2003 to DEC
  • Staff met with DEC representative Dr. John Ferrante, regarding review comments on draft 2004 AMP work plan.

Contracts

New contracts

None to report.

Amendments to existing contracts

Midland Avenue conveyances & RTF:
Contract with Spectra Engineering amended to include design on CSO 046B.
Contract amendment amount: $105,055. Executed 2/6/04.

Change orders

Full-scale ammonia/phosphorus removal
Contract with The Pike Company amended to include acceleration of SEPS, modifications to clarifier bridge and aluminum grating.
Contract amendment amount: $68,285.00. Executed 2/27/04.

Contract with Ridley Electric amended to include furnishing temporary operations room & monitoring of SEPS, BAF and UV.
Contract amendment amount: $91,140.00. Executed 2/27/04.

Legislative action

Action items of the County Legislature in the month of February:
No items.

Action items for March legislative session:
Authorizing an intermunicipal agreement with the City of Syracuse for the Tallman Street sewer separation project.

Upcoming for March Committee:
No items.

Funding

Grants

State Bond Act funds:
Payments received this month from State Bond Act funds: None to report.
Total received to date in State Bond Act funds: $48,297,443.

Federal EPA funds:
Payments received this month from Federal EPA funds:
None to report.
Total received to date in Federal EPA funds: $41,641,326.

Federal Army Corps of Engineers funds:
UBMP: Request in the amount of $82,378.56 received on 2/4/04.
Total received to date from U.S. Army Corps of Engineers funds: $5,490,428.

Loans

The following reimbursement payments were received from EFC during the month of February:

  • Full-scale ammonia/phosphorus removal: Request #20 in the amount of $6,147,301.35 received on 2/9/04 for total aggregate received of $53,705,257.93.
  • Harbor Brook FCF: Request #2 in the amount of $35,343.69 received on 2/4/04 for total aggregate received of $312,595.
  • Kirkpatrick Street PS/Force Main: Request #2 in the amount of $203,154.20 received on 2/4/04 for total aggregate received of $738,983 (long term loan).

Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $143,115,456 (short term), $9,088,289 (long term).

Metro photos by Joe Lorah


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection