Go to home page
Go to home page
Setting precast beams over HRFS hydrocyclone building
Setting precast beams over HRFS hydrocyclone building

Monthly report—November 2003

BAF construction nearly finished
 

Highlights of the month

  • During November, contractors continued to make progress on construction of the new ammonia/phosphorus removal facilities at Metro with construction substantially complete on the ammonia removal facility (BAF).
     
    The contractor hired by USFilter/Krüger to install the filter media with their specialty equipment arrived from France on November 3. To date, nine of the eighteen BAF cells have been successfully filled with filter media for the system. The polystyrene beads are delivered daily in trucks from West Virginia and then transferred into the cells. Completion to fill one cell with the necessary volume of media takes about 2 days. Work on the remaining BAF cells is expected to be completed during December.
     
    In related work, construction activities continued on the phosphorus removal facility (HRFS), the secondary effluent pump station, the UV disinfection structure and the Operations Building.
  • By the end of November, about 99% of the total structural concrete for the entire ammonia-phosphorus removal-disinfection facilities complex had been installed totaling 26,545 cubic yards.
  • 20,000 biodegradable leaf bags were distributed during October and November to city residents through libraries and community centers in the city under the Urban Best Management Practices Program funded through the Onondaga Lake Partnership and the County. This is the second year of the program. Use of the free leaf bags helps keep the leaves out of the sewers and reduce sewer overflows.

 See additional photos of construction during November 2003.

Projects under construction

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ Completion date for Ammonia Full Scale—11/3/03—schedule revision requested)
(ACJ Completion date for Phosphorus Removal Stage II—4/1/05—on schedule)
 
Structural work to-date on major component facilities
BAF structure (ammonia removal) All structural concrete work substantially complete
HRFS facility (phosphorus removal) ditto
UV disinfection facility ditto
Secondary effluent pump station ditto
Chemical/operation building Structural steel framework 95% complete

See construction photos of BAF and HRFS for this month.
Photos of the chemical and operations building, chemical storage, secondary effluent pump station, drainage and water lines
See a slide show of workers placing the sand silo in the chemical building.

Summary of mechanical work this month

Erecting scaffolding along the BAF building
Erecting scaffolding along the BAF building

BAF facility. Start up activities continued this month on the BAF facilities.

Krüger BAF process personnel were on site during the month to continue programming and check the logic controllers and system. Krüger's specialty subcontractor, Isobox Technologies from France, came on site and began media installation on November 14th.

Coordination meetings were held with County Codes Enforcement personnel, the Syracuse Fire Department, all other prime contractors and personnel from the County's existing Metro facility to finalize and communicate a safety plan put in effect during the installation of the polystyrene media.

Media installation was 50% complete by the end of November with Isobox personnel working 7 days per week to complete their portion of the work. Testing of the BAF cells and the secondary effluent pump station is planned for late December and early January.

Other mechanical work completed this month included: start up of the BAF cell exhaust louvers that were required to be operational during media installation, completion of the installation of the steam and condensate piping in the cross gallery and the heating loop to the Operations Building and the UV facility. Also the heat was turned on in the BAF and roof drains and all the water piping are now done.
Setting the motor for HRFS settling tank 1
Setting the motor for HRFS settling tank 1

HRFS facility. The mechanical work continued this month in the HRFS portion of the facility with the installation of the stainless steel piping and sand injection pumps in the influent gallery. Contractor Edward Joy also completed the heat loop and the installation of the unit heaters in the galleries and heat was made available for startup.

Secondary Effluent Pump Station. The mechanical and electrical work in this section is now substantially complete.

UV structure. Ridley Electric continued work on installing conduits and wiring and has energized the electrical panels in the UV structure. Plumbing contractor, Burns Bros., has completed the roof drains and their work is now substantially complete.

Architectural work this month

BAF facility. The contractor continued installing the bridge crane and support rails throughout the gallery this month. Roofing is now substantially complete and architectural work for the upper BAF effluent channel is also substantially complete.
Storm drain line connecting manholes 85 to 87
Storm drain line connecting manholes 85 to 87

Other structures. The painting contractor has substantially completed painting of the inside CMU walls in the UV structure and stairs and grating are now being installed. The roofing system for the UV structure was started this month. Architectural work for the pump station is now substantially complete and the contractor has installed aluminum wall panels on three sides of the building. Prime contractor Pike has finished the painting and floor coating on the low lift pump station.

Other information. Work began in October on the installation of the storm drainage system. Drainage work is now more than 50% complete with drainage completely installed on the north side of the HRFS and 50% of the west side of the BAF. This work is scheduled to be completed by the end of the year.

Meetings are held on various aspects of the construction on a regular basis including biweekly start up and construction progress meetings, weekly coordination meetings with contract superintendents and periodic meetings with equipment supplier, USFilter/Krüger, involving County staff, engineering and construction management consultants.

This is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive impacts on the water quality of Onondaga Lake

Brighton Avenue sewer separation project (CSO)

(ACJ Project milestone—January 1, 2012—Project ahead of schedule)
Pipe installation and restoration work completed The contractor has completed all necessary site restoration work including street paving, sidewalks and seeding and planting of grass buffer strip between the street and sidewalk. A total of 2,864 feet of mainline sewer in the roads was installed in the project along with 1,760.5 feet of lateral sewers to houses, 39 feet of new copper water service, 15 new manholes and 12 new catch basins hoods.
Delineating excavation on Bishop Avenue, July 2003
Delineating excavation on Bishop Avenue, July 2003

Brighton Avenue was resurfaced and reopened in time for the start of school buses at the end of August.

This sewer separation project involved about 8 blocks on the City's south side and about 100 homes. Work included installation of a new mainline sewer and conversion of existing combined lines to use for storm water only. Lead water services encountered during sewer construction were replaced in the right of way by the County to reduce extent of lead services. With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and storm water to Onondaga Creek when it rains. The overflows now only release storm water. All wastewater goes to Metro for treatment.

Projects in design stages

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07)
Further work progresses on Phase II during this month, the following activities were undertaken by the County's design consultant, EEA, to progress the project:

  • Continued to develop contract documents for Phase II building demolition needs
  • Completed the interpretive report on the ground water pumping test and transmitted to the County
  • Gave geotechnical reports to USGS and the consultants to the Central New York Regional Transportation Authority for their review and comment
  • Developed initial draft of updated excavation and dewatering feasibility study
  • Conducted further research into conveyance flushing systems and utility location.

In addition, information was compiled to assist in progressing a standardization resolution for Phase II odor control technology. The resolution was presented to the appropriate committees of the County Legislature during November.

Continued preparation of the draft Phase II environmental assessment.

Draft 100% contract documents were forwarded to DEC for review.

Other meetings held

A number of meetings were held to discuss the contract documents with County staff, construction managers—CDM/C&S—and the state DEC. On November 25th, a meeting was held with construction managers, CDM/C&S about site security and bid/payment structure for Phase II.

Additional ten sewer separation areas (CSO)

Sewer Separation projects moving forward Two projects designed under the design grant from the U.S. Army Corps of Engineers have been completed—the Water Street Project (closing CSO #024 and converting the discharge to storm water only) and the Brighton Avenue Project (closing CSOs #053 and #054 and converting the discharge to storm water only).
Streets included in the next sewer separation effort, Midland at Lincoln
Streets included in the next sewer separation effort, Midland at Lincoln

The next CSOs slated for sewer separation are #038 and 040 in the Tallman-Midland area and #046A and #046B near Onondaga Avenue.

Finalization of bid documents for next sewer separation project continues Spectra Engineering continued this month to review and update the design of the sewer separation projects slated for CSOs 038, 040, 046A and possibly 046B. The work involves reviewing and updating existing design documents including any necessary field verifications, preparing bid ready documents, meeting with other agencies involved including NiMo, City Water and DPW and handling construction inspection. A kick-off meeting for the new contract was held November 6th.

Projects in facility planning stage

The Leaf Management Program distributed 20 thousand leaf bags and kept countless leaves from entering sewers.
The Leaf Management Program distributed 20 thousand leaf bags and kept countless leaves from entering sewers.

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—milestone revision requested.)

The following work activities were accomplished this month:

  • Continued to work with County and subcontractor, Hartgen Associates, to finalize revised plans for necessary Phase II/III archeological field Reconnaissance work for the facility site and conveyance routes.
  • Continued development of environmental information document and SEQR-related information.
  • Continued to progress conceptual design development for project and revised draft facilities plan.
  • Continued to work with sewer system modeling consultant, Brown and Caldwell, on modeling related to alternatives analysis and optimization studies.

    The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams Streets to be served by a Clinton area facility located near downtown Syracuse. The facility plan evaluates alternative technologies to address the overflows and alternative sites for a storage/treatment facility.

    Harbor Brook CSO abatement project (CSO)

    (ACJ completion date for In-Water system—7/1/02—Not implementable—Milestone Revision requested)

    This month, the County continued to work with the project consultant, Brown and Caldwell to finalize contract amendment for this project to include necessary archeological investigations, preparation of draft EID/SEQR documentation, and finalization of facility plan.

    Presentation given by LIPO director and deputy director to combined classes at Fowler High School on November 18th about Midland and Harbor Brook projects.

    The draft was released in March 2002. The draft plan outlines and evaluates alternative technologies including the in-water system for abating and treating the 18 CSOs which release into Harbor Brook. This draft plan also identifies potential sites for CSO abatement facilities.

    Other activities

    Mimi Capetto, director of the McChesney Recreation Center, stands by while patrons collect free leaf bags.
    Mimi Capetto, director of the McChesney Recreation Center, stands by while patrons collect free leaf bags.

    Onondaga Creek floatables control skimmer vessel

    Collection activities continued on a once a week basis during November, and this was the final month of collection for the 2003 season. The skimmer operation was run by Central New York Aquatic Harvesting under contract with the County during the '02 and '03 seasons.

    Earlier this year, Alpha Boats was the successful bidder on a 5-year contract which has been signed to provide maintenance and collection services in the harbor area beginning in 2004.

    Lake Partnership annual progress meeting

    The County worked with others on the Lake Partnership to assist with the annual progress meeting of the Partnership for the public held on November 13 at the State Fairgrounds Center of Progress building. Major storm conditions reduced attendance at the meeting; however, about ninety people still attended. The County had a display of its Lake Improvement Projects and the Urban Best Management Practices Program. County staff were also part of the video presentation on the activities of the Partnership during the past year. The County Executive served on the panel and responded to questions from the public.

    The following day, County representatives attended the after-action review meeting with other Partnership members to discuss future priorities and activities.

    A presentation was given for the Partnership to members of the Syracuse Garden Club on November 17th by Sue Miller for the Outreach Committee.

    Meeting with DEC on Floatables Control projects A meeting was held between County staff and regional DEC personnel on November 19th to review the current status of various floatables control projects completed by the County under the Lake Improvement Program. Operations and maintenance procedures, operational histories and new reporting processes were described and discussed.

    Completed projects

    Major milestones met for CSO interim projects

    The year 2002 was important in the Amended Consent Judgment program because ten CSO-related projects met their major milestone completion date of July 1, 2002 (ACJ, Appendix B pages 10-12). Some of these interim projects were completed well ahead of the major milestone dates, and all but two met the major milestone. The Kirkpatrick Street Pump Station and the Harbor Brook In-water System required milestone extensions. New York State is reviewing the County's requests for the extensions.

    The projects are listed below by date completed:
     
    Project Completion date
    Evaluation of siphon crossings May 1999
    Hiawatha regional treatment & storage facility July 2001
    Newell regional treatment facility
      Disinfection tested and report filed
    July 2001
    Teall Brook floatables control facility December 2001
    Evaluation of CSO toxicity May 2002
    Erie Boulevard storage system upgrade June 2002
    Onondaga Creek floatables control facility
      Skimmer boat in operation beginning summer ’02
    June 2002
    Harbor Brook floatables control facility July 2002
    Harbor Brook in-water system
         Project changed. Facility plan drafted and published
    Mar 2002
         See note 1.
    Kirkpatrick Street pump station upgrade and force main
         Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
    Nov 1, 2002
    1. Milestone revision requested and under review by State.

    Brighton Avenue sewer separation project (CSO)

    (ACJ Project milestone—January 1, 2012—Project completed 2003)
    Pipe installation and restoration work was completed. Under this $2.1 million project, 2,864 feet of mainline sewer was installed in the streets along with a total of 1,760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods. The project was completed on time and under budget.

    This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. The County replaced lead water services encountered during sewer construction to reduce lead services.

    With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater from these areas goes to Metro for treatment.

    Major milestones met for Metro interim projects

    Under Appendix A of the ACJ, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date and most well ahead of schedule. The projects are listed below by date completed:
     
    Project Completed
    Phase II plant improvements January 1999
    Aeration system upgrade January 2000
    Odor control and residual handling December 2000
    Digester modifications—Phase III Improvements December 2000
    Chemical storage April 2001
    Digital system improvements December 2001

    Ambient Monitoring Program

    Summary of sampling program

    Tributary, lake, river, fish sampling: no report this month.

    Other activities

    • Prepared for upcoming meeting of the Biological Workgroup scheduled for December.
    • Initiated contract amendment for the river model tasks relating to the responses to peer reviewer for period 1/1/03 to 12/31/05 with QEA.
    • Contract fully executed with USGS for cooperative funding of the stream gauging stations' O&M costs for 14 stations and 1 lake station for the period 10/1/03 to 9/30/04.

    Contracts

    New contracts

    None to report.

    Amendments to existing contracts

    Clinton Street conveyances & RTF. Contract with Environmental Engineering Associates (EEA) amended for additional design work needed to complete EID and Facility Plan.
    Contract amendment amount: $75,884. Executed 11/10/03.

    Change orders

    None to report.

    Legislative action

    Action items of the County Legislature in November

    • Amending the 2003 County budget in the amount of $5850 to complete removal and disposal of CSO-derived floatables from the Syracuse Inner Harbor for the remainder of the 2003 season.
    • Amending the 2003 County budget to accept funds from Niagara Mohawk Power Corporation for environmental remediation on the ammonia/phosphorus project ($6,000,000).

    Upcoming for December committee & legislative session

    Authorizing the standardization of the Calgon Phoenix carbon adsorption odor control system for systems requiring carbon adsorption elements.

    Funding

    Grants

    State Bond Act funds: None to report. Total received to date in State Bond Act funds: $48,144,443.

    Federal EPA funds: Payments received this month from Federal EPA funds: Full-scale ammonia/phosphorus removal—Request for 2,318,308 received on 11/26/03 for aggregate of $38,805,821. Total received to date in Federal EPA funds: $40,241,684.

    Federal Army Corps of Engineers funds: None to report. Total received to date from U.S. Army Corps of Engineers funds: $5,490,428.

    Loans

    The following reimbursement payments were received from EFC during the month of November: Full-scale ammonia/phosphorus removal—Request #18 for $2,169,764.07 received on 11/17/03 for aggregate of $45,367,817.44. Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $134,778,016 (short-term), $8,790,518 (long term).

    —Metro photos by Joe Lorah


  • Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
     
    Susan Miller, Project Deputy Director
    Phone 315-435-2260   Fax 315-435-5023
     Onondaga County Dept of Water Environment Protection