Go to home page
Go to home page
Attaching metal studding along the west roof line for the BAF ammonia treatment facilities
Attaching metal studding along the west roof line for the BAF ammonia treatment facilities

Monthly report—September 2003

Start-up of ammonia treatment
 

Highlights of the month

  • During September, contractors continued to make progress on construction of the new ammonia/phosphorus removal facilities at Metro and began transitioning to the start-up phase of the BAF project. Start-up activities were completed in the following areas related to the BAF (ammonia removal facilities): compressed air system, three backwash waste pumps, and eight Hoffman Blower units. Other systems receiving some start-up activities included the PLC blower controls, butterfly valves, device net, and cell air grids.
     
    Structural and mechanical work also continued on the HRFS facility and construction of the foundations and structural steel work began on the Chemical Building and Operations Center. By the end of August, about 97% of the total structural concrete for the entire complex had been installed totaling 25,584 cubic yards.
  • Displayed Urban Best Management Practices educational materials available to schools and teachers at the Central New York chapter meeting of the Science Teachers' Association held at the SUNY College of Environmental Science and Forestry. The UBMP program is managed by the County and funded through the Onondaga Lake Partnership.
  • Displayed and distributed information about the Urban Best Management Practices program at a meeting of local officials on September 10 sponsored by the Central New York Regional Planning and Development Board on municipal storm water regulations and available public education and public involvement programs.
  • Prepared for and took part in Legislative Budget Review. Department of Water Environment Protection and LIPO budgets were reviewed on September 16th.
  • Semi-annual meeting of County's Technical Lake Advisors was held on September 9 and 10.

Progress of projects under construction

Pouring the slab-on-deck for the HRFS facilities. Note conduit and sleeves in place.
Pouring the slab-on-deck for the HRFS facilities. Note conduit and sleeves in place.

Ammonia removal/phosphorus removal combined project (Metro)

(ACJ Completion date for ammonia full-scale—11/3/03—schedule revision requested)
(ACJ Completion date for phosphorus removal Stage II—4/1/05—on schedule)

Summary of structural work to date on major component facilities

BAF structure (ammonia removal). This month a total of 44 cubic yards of concrete was placed in the upper level of the BAF complex. All concrete work is now substantially complete.

HRFS facility (phosphorus removal). In September, structural work continued with a total of 357 cubic yards of concrete installed. All structural concrete work is now substantially complete.

UV disinfection facility. The contractor completed the brick veneer work and installation of the precast roof planks.

Secondary effluent pump station and chemical gallery. All structural work at this facility is now substantially complete.

Chemical/operation building. In September, 107 cubic yards of concrete was poured on the remainder of the grade beams for this facility. Installation began on the structural steel framework.

Summary of mechanical work

BAF facility. Start-up activities began this month on the BAF facilities. All eight Hoffman Blowers were successfully tested between September 8-15. Other component parts were also checked out as part of start-up activities with USFilter/Krüger personnel present.
Installing drain lines at the UV building
Installing drain lines at the UV building

Burns Brothers has substantially completed the installation and insulation of the roof drains and Edward Joy has installed the roof ventilator fans. JW Danforth continues installation of the air grids in the north BAF and all but 5 cells have been completed.

HRFS facility. Mechanical work continued this month with the installation of the lamella support bracket in tank #3. Edward Joy has installed about 50% of the heat loop and unit heaters in the galleries so that heat will be available for start-up of the BAF facility and UV structure.

Secondary effluent pump station. Essentially the mechanical work in the secondary effluent pump station is complete. Final electrical and architectural work remain.

Architectural work

BAF facility. Work on the spray-on insulation is now substantially complete. The contractor has installed most aluminum support framing for the architectural panels and the BAF roofing is substantially completed.

Other structures. Brick veneer work is substantially complete on the UV structure. The contractor has substantially completed interior painting in the secondary effluent pump station and painting of the walls and ceiling in the low lift pump station boiler room and stairwell is complete as well.

Other information

Meetings are held on various aspects of the construction on a regular basis with biweekly progress, start-up and construction progress and weekly meetings of contract superintendents for coordination and periodic meetings with equipment supplier, USFilter/Krüger, involving County staff, engineering and construction management contractors and USFilter/Krüger personnel.

This is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive impacts on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

 See more construction photos.

Brighton Avenue sewer separation project (CSO)

West Brighton Avenue at South Avenue, newly paved and painted (Aug 2003)
West Brighton Avenue at South Avenue, newly paved and painted (Aug 2003)

(ACJ Project milestone—January 1, 2012—Project ahead of schedule)
Pipe installation and restoration work completed. The contractor has completed all necessary site restoration work including street paving, sidewalks and seeding and planting of grass buffer strip between the street and sidewalk. A total of 2,864 feet of mainline sewer in the roads was installed in the project along with 1,760.5 feet of lateral sewers to houses, 39 feet of new copper water service and 15 new manholes and 12 new catch basins hoods.

Brighton Avenue was resurfaced and reopened in time for the start of school buses at the end of August. During September, a repair was made to a former combined line (now used for storm water only) which necessitated a street cut and resurfacing in one area on Marguerite Avenue.

This sewer separation project involved about 8 blocks on the City's south side and about 100 homes. Work included installation of a new mainline sewer and conversion of existing combined lines to use for storm water only. Lead water services encountered during sewer construction were replaced in the right-of-way by the County to reduce extent of lead services. With the project completed, two former combined sewer overflows (numbers 053 and 054) no longer release combined untreated sewage and storm water to Onondaga Creek when it rains. The overflows now only release storm water. All wastewater goes to Metro for treatment.

Projects in design stages

Midland conveyances and regional treatment facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07)
City's decision to appeal federal ruling threatens further delays. The City's appeal will not be heard in the Circuit Court of Appeals until some time this fall. Despite this decision by the City, the County is proceeding with necessary testing on the properties acquired and moving ahead on acquiring necessary private properties. Testing is conducted to help assess properties prior to demolition and gather necessary subsurface information needed for finalizing design.

Work continues on 95-100% design documents for next phase of construction. Work continues on the 100% design documents. Meetings were held this month concerning comments on draft design documents with the County, revised conveyance alignment at Midland and Blaine intersection, geotechnical issues on Phase II construction, telemetry and flow monitoring requirements for the Phase II RTF, and water line relocations.

A supplemental ground water pump test was completed at the Blaine/Oxford site, and the Geotechnical Data Report containing the results of the supplemental geotechnical investigation was submitted to the County by the design engineer.

Additional ten sewer separation areas (CSO)

Click on image for enlarged map with locations of the overflow elimination plan.
Click on image for enlarged map with locations of the overflow elimination plan.

Design documents received by County. Design documents were finalized and forwarded to the County for the additional ten areas in the City of Syracuse proposed for sewer separation under the ACJ. Funding for this design effort was through the U.S. Army Corps of Engineers. Design documents for the Brighton Avenue and the Water Street projects were completed under this contract and finalized earlier so that projects could be moved along into construction. Water Street and the Brighton Avenue projects are now complete.

The next CSOs slated for sewer separation are #038 and 040 in the Tallman/Midland area and #046A near Onondaga Street.

RFP for engineering services on next separation projects. A notice of award was sent this month to Spectra Engineering for this work. Currently in process of finalization of contract with County.

Projects in facility planning stage

Clinton conveyances and regional treatment facility (CSO)

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003—milestone revision requested.)
The following work activities were accomplished this month:

  • Draft Phase II/III archeological work plan transmitted to the County for review on September 25.
  • Continued development of Environmental Information Document and SEQR related information.
  • Draft Phase I Environmental Assessment for Clinton Station site transmitted to County for review on September 8th.
  • Continued conceptual design development and coordinated with sewer system modeling consultant, Brown and Caldwell, on modeling related to alternatives analysis and optimization studies.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams Streets to be served by a Clinton area facility located near downtown Syracuse. The Clinton CSO Abatement Facility Plan (March 2002 draft) evaluates alternative technologies to address the overflows and alternative sites for a storage/treatment facility.

Harbor Brook CSO abatement project (CSO)

(ACJ completion date for In-Water system—7/1/02—not implementable—milestone revision requested)
This month, the County worked with the project consultant, Brown and Caldwell to develop a comprehensive list of project tasks to be completed to finalize the Facility Plan for this project and a schedule for completion. Contract amendment in development and finalization.

The draft Harbor Brook CSO Abatement Facilities Plan was released in March 2002. The draft plan outlines and evaluates alternative technologies including the in-water system for abating and treating the 18 CSOs which release into Harbor Brook. This draft plan also identifies potential sites for CSO abatement facilities.

During 2003, the County will continue to proceed with public participation activities with interested residents and organizations in the Harbor Brook area and hopes to finalize the Facility Plan with a recommended alternative and necessary environmental review by the end of 2003.

Other activities

Urban best management practices project

Scene from UBMP video urging residents to keep motor oil out of the city's sewers.
Scene from UBMP video urging residents to keep motor oil out of the city's sewers.

The new 30-second public service announcement encouraging the public to reduce street debris and litter aired on local television stations during August and arrangements were made this month for more airings in October. Good responses have been received from viewers. Funding for the project was secured through the Onondaga Lake Partnership from the Corps of Engineers and matched with County funds.
Click here to view the video.
 
Skimmer boat in operation (2002)
Skimmer boat in operation (2002)

Onondaga Creek floatables control skimmer vessel

Collection activities continued on a once-a-week basis during September. Over 9 tons of trash has been collected to date this year by the skimmer operation.

A post-bid meeting was held on July 7 with the apparent low bidder and a notice-of-intent-to-award was sent to Alpha Boats concerning the 5-year contract to provide maintenance and collection services in the harbor area. A meeting was held with Alpha Boats on September 4th to discuss details of contract finalization. Contract to be finalized.

County works with Lake Partnership

New educational materials produced by the County with OLP support were displayed for science teachers.
New educational materials produced by the County with OLP support were displayed for science teachers.

The County continues to have representatives attend and participate in the monthly meetings of the three subcommittees of the Partnership—Resource, Project and Outreach and the Executive Committee.

Completed projects

Major milestones met for CSO interim projects

The year 2002 was important in the Amended Consent Judgment program because ten CSO-related projects met their major milestone completion date of July 1, 2002 (ACJ, Appendix B pages 10-12). Some of these interim projects were completed well ahead of the major milestone dates, and all but two met the major milestone. The Kirkpatrick Street Pump Station and the Harbor Brook In-water System required milestone extensions. New York State is reviewing the County's requests for the extensions.

The projects are listed below by date completed:
 
Project Completion date
Evaluation of siphon crossings May 1999
Hiawatha regional treatment & storage facility July 2001
Newell regional treatment facility
  Disinfection tested and report filed
July 2001
Teall Brook floatables control facility December 2001
Evaluation of CSO toxicity May 2002
Erie Boulevard storage system upgrade June 2002
Onondaga Creek floatables control facility
  Skimmer boat in operation beginning summer ’02
June 2002
Harbor Brook floatables control facility July 2002
Harbor Brook in-water system
     Project changed. Facility plan drafted and published
Mar 2002
     See note 1.
Kirkpatrick Street pump station upgrade and force main
     Construction delays. Project completed by requested milestone revision date of Nov 1, 2002
Nov 1, 2002
1. Milestone revision requested and under review by State.

Brighton Avenue sewer separation project (CSO)

(ACJ Project milestone—January 1, 2012—Project completed 2003)
Pipe installation and restoration work was completed. Under this $2.1 million project, 2,864 feet of mainline sewer was installed in the streets along with a total of 1,760.5 feet of lateral sewers to eighty-four houses, thirty-nine new copper water service lines in the right-of-way, fifteen new manholes, and twelve new catch basins hoods. The project was completed on time and under budget.

This sewer separation project involved about eight blocks on the City's south side. Work included installation of a new mainline sewer and conversion of existing combined lines to use for stormwater only. The County replaced lead water services encountered during sewer construction to reduce lead services.

With the project completed, two former combined sewer overflows (053 and 054) no longer release combined untreated sewage and stormwater to Onondaga Creek when it rains. The overflows now only release stormwater. All wastewater from these areas goes to Metro for treatment.

Major milestones met for Metro interim projects

Under Appendix A of the ACJ, certain improvement projects at Metro were designated as interim projects and given a major milestone date for completion of July 1, 2002. All six projects were completed by the milestone date and most well ahead of schedule. The projects are listed below by date completed:
 
Project Completed
Phase II plant improvements January 1999
Aeration system upgrade January 2000
Odor control and residual handling December 2000
Digester modifications—Phase III Improvements December 2000
Chemical storage April 2001
Digital system improvements December 2001

Ambient Monitoring Program

Summary of sampling program

Tributary, lake, river, fish sampling

No report this month.

Executive summary annual report distributed

The Technical Lake Advisors meeting was held September 9 and 10. Plans underway for participation in Lake Partnership's Fisheries Roundtable on October 25.

Letters were received in August from the State DEC giving approval to the following: the County's 2001 Annual Report on the Ambient Monitoring Program, the County's 2002 Annual Report on the Ambient Monitoring Program and the County's proposed 2003 Ambient Monitoring program which began April 1, 2003.
Click here for the executive summary of the 2002 annual report.

Contracts

New contracts

None to report.

Amendments to existing contracts

Full-scale ammonia/phosphorus removal

Contract with CME Associates amended for additional testing.
Contract amendment amount: $60,000. Executed 9/4/03.

Midland Avenue conveyances & RTF

Contract with Environmental Engineering Associates (EEA) amended to include the physical hydraulic model study.
Contract amendment amount: $694,332. Executed 9/4/03.
 
Contract with Allied American Abstract amended for additional title abstracts.
Contract amendment amount: $7,500. Executed 9/18/03.

Change orders

Full-scale ammonia/phosphorus removal

Contract with Pike Construction amended for installation of mechanical slide gates.
Total change order amount: $429,975. Executed 9/11/03.

Legislative action

Action items of the County Legislature in the month of September:
No items presented.

Upcoming for October Legislative session:
Authorizing the acquisition of property for the construction, operation, and maintenance of Phase II of the Midland Avenue conveyances & RTF project.

Upcoming for October committee session:
Amending the 2003 County budget to accept funds from Niagara Mohawk Power Corporation for environmental remediation on the ammonia/phosphorus removal project.
Request additional funding for Inner Harbor skimmer operation to complete ’03 season through November.

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds:
Midland Avenue conveyances & RTF—Request #23 for $53,296.58 received on 9/12/03 for aggregate of $2,893.993.45.
Total received to date in State Bond Act funds—$46,921,688.

Federal EPA funds:
Payments received this month from Federal EPA funds:
None to report.
Total received to date in Federal EPA funds—$37,923,376.

Federal Army Corps of Engineers funds:
Sewer separation—Request #5 for $437,879.78 received on 9/18/03 for aggregate of $1,383.328.
UBMP—Request #6 for $17,974.18 received on 9/18/03 for aggregate of $66,535.07
Total received to date from U.S. Army Corps of Engineers funds—$5,490,428.

Loans

The following reimbursement payments were received from EFC during the month of September:

Full-scale ammonia/phosphorus removal—Request #15 for $1,950,577.398 received on 9/30/03 for aggregate of $91,195,654.62.
Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $127,264,854 (short term), $8,678,670 (long term).

—Metro photos by Joe Lorah


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection