|
|
Pouring concrete for a settling tank, part of the new HRFS phosphorus treatment facilities at Metro (Nov 5, 2002)
|
Monthly report November 2002
Kirkpatrick pump station completed
Construction continues at accelerated pace on new facilities
Placement of steel and concrete for the facilities is
moving at an accelerated rate on the ammonia removal
and ultraviolet disinfection facilities. This month,
the contractor continued work on the phosphorus
removal facilities as well with placement of slab on
grade and forming of the concrete tank walls.
Approximately 17,000 cubic yards of concrete had been
place by the end of November out of 27,000 cubic yards
expected for the whole project. Process piping for
the ammonia removal facilities is being installed, and
work on the secondary effluent pump station continued
with installation of the remainder of the base slabs
and placement of the concrete wet well walls and
header pipes. Work has also begun under the separate
contracts for electrical, plumbing and HVAC.
Decision issued by U.S. District Court re: Midland project
A decision was issued on November 20, 2002 by U.S.
District Court Judge Thomas J. McAvoy, in which he
found that the County had authority to condemn
property owned by the City which is needed for the
Midland CSO abatement Project. In the decision, the
Judge granted the City's motion for compensation for
the City and Syracuse Urban Renewal Agency, and the
parties were asked to submit appropriate documents to
allow the Court to determine the value of the
properties in question.
Niagara Mohawk begins work in Brighton Sewer Separation area
Niagara Mohawk crews began work this month to replace
the old cast iron gas main with a new main and make
changes in lateral hook ups to homes as necessary.
With the cooperation of NiMo, this work is being done
prior to the start of the installation of the new
sewer by the County's contractor. By replacing the
gas main first, it reduces the possibility of
disturbing the old more vulnerable main and causing a
disruption to services. NiMo work was slowed during
the month by inclement weather conditions. The
County's contractor is now slated to begin work in the
area after January 1, 2003 and is estimated to take
about 6 months. This sewer separation project
involves about 8 blocks on the City's south side and
about 100 homes. Residents will be informed as work
progresses.
Kirkpatrick project completed and operational
The new wet weather pumps were operational since
September 8, 2002. During September and October, the
wet weather pumps were utilized for 100% of both dry
weather and wet weather flow. As of October 31, 2002,
the replacement pumps and screens for the pump station
have been operating as well. As reported in a letter
to DEC dated November 8, 2002, the project was
complete and fully operational prior to November 1,
2002 (the requested new major milestone date). Punch
list and other evaluation activities continue.
|
|
Forms for beams are in place at the construction site for ammonia removal facilities (Nov 5, 2002)
|
(ACJ Completion date for Ammonia Full Scale11/3/03schedule concerns) (ACJ Completion date for Phosphorus Removal Stage II4/1/05on schedule)
Construction continues at accelerated pace.
Placement of steel and concrete is moving at an
accelerated rate in the ammonia removal and UV
portions of the facilities. Work has also started on
forming of concrete tank walls for the HRFS
(phosphorus removal facilities). The general
contractor proceeded to conduct hydrostatic testing of
the BAF tanks and sealing of walls as required for
water tightness.
Electrical work continues.
Installation of below-slab conduits continued this
month at the BAF (ammonia removal) complex. Work was
also continued on the main electrical substation.
HVAC work proceeds.
Three new boilers were set in the low lift pump
station boiler room. Temporary operation of Boiler #1
was initiated and the boiler successfully passed the
initial operations on natural gas. It will be operated
on natural gas until digester gas connections are
made.
Plumbing contractor begins.
Plumbing contractor, Burns Brothers, began work on
site during November with imbedded items in the
BAF/HRFS slabs.
|
|
Workers install the first layer of reinforcing steel rods in the electrical room (Nov 2002)
|
Dewatering continues.
Dewatering (under contract 2D) is continuing and the
system has lowered groundwater below the excavation of
all areas needed. It is anticipated that full-scale
dewatering and treatment will be discontinued by the
end of 2002. Dewatering and groundwater treatment for
miscellaneous trench excavations will be conducted on
an as needed basis.
Process equipment continues arriving.
Process equipment from US Filter/Krüger continues
arriving regularly on site and is turned over to the
general contractor for installation. Installation of
nozzle deck slabs has started. Discussion has begun
between the County and equipment manufacturer and the
design engineer regarding the start up and testing of
the BAF systems and installation of the media for the
BAF.
The following meetings were held this month:
Construction progress meeting were held weekly on Thursdays at 10 a.m.
Weekly meetings held between construction manager (CDM/C&S), design engineer and the County.
Modification review meetings held weekly.
Scheduling meetings held weekly with all prime contractors.
This is the largest and most costly single project in
the Amended Consent Judgment program and will have the
greatest positive impacts on the water quality of
Onondaga Lake by removing more ammonia and phosphorus
from the Metro effluent discharge.
(ACJ completion date7/1/02requested milestone revision met 11/1/02)
|
|
Landscaping along Kirkpatrick Street enhances the pump station's setting near the Inner Harbor (Oct 29, 2002)
|
Facility fully operation.
As of October 31, 2002, the dry weather replacement
pumps and screens were operating. During September and
October, the new wet weather pumps were operational
since September 8 and were utilized for 100% of both
dry and wet weather flow. Punch list items and
continued start up testing and monitoring is underway.
Milestone revision requested.
Because the project has expanded in scope since it was
originally conceived in the ACJ and unforeseen
hydrogeologic conditions have impacted the
construction schedule, the County requested that the
completion milestone be extended from July 1, 2002 to
November 1, 2002 by which time the County anticipated
the project would be fully operational. Decision on
the revision request is still pending. A letter was
forwarded to DEC on November 8, 2002, informing DEC
that the facility was complete and fully operational
by the November 1, 2002 date.
Niagara Mohawk continued work to install a new gas
main in the area this month. Work was slowed due to
weather delays and the need for crews to respond to
emergencies elsewhere. Work up to and including a
portion of Brighton Avenue, Marguerite and a portion of
Bishop will be completed before the County's
contractor begins work on the sewers. Contacts with
Niagara Mohawk were made throughout the month to
continue coordination of the two projects.
County construction is now scheduled to start on this
project in January based on NiMo's progress. The
entire project is estimated to be completed in 6-9
months, weather dependent. New sewer lines will be
installed and existing combined lines will be
converted to stormwater use only. Lead water service
lines encountered will be replaced by the County .
Much coordination will be necessary between the
County's contractor, NiMo, City Water and other
utilities.
(ACJ Completion Date7/1/02CompleteJanuary 2000)
Retrofitting a total of eight tanks was completed well
ahead of the required ACJ completion milestone. The
tanks are all fully operational with the new more
energy efficient and effective fine-bubble diffuser
aeration system. Lower ammonia levels reported in lake
corresponding with operation of new system.
(ACJ completion date7/1/02Completeahead of schedule)
(ACJ completion date7/1/02CompleteDecember 2001ahead of schedule)
New system in operation.
The new digital system is operational in all
locations. Certificate of Substantial completion was
submitted to NYSDEC. The contractor's warranty
continued through May 31, 2002.
(ACJ Completion date7/1/02CompleteDecember 2000ahead of schedule)
Project completed. This project, which was designed to
reduce odors at the headworks of Metro adjacent to
Hiawatha Boulevard, is completed and in operation.
Positive comments have been received from the public
on a noticeable reduction in odors as a result of this
project.
Phosphorus removal pilot project (Metro)
(ACJ milestone date for completion of pilot4/1/07 -
well ahead of schedule)
Final report in preparation.
The pilot was completed in December 2000. Currently
work continues on evaluation and analysis of data
compiled during the pilot operation which tested a
variety of phosphorus removal technologies. The County
is more than 6 years earlier than is called for in the
ACJ in carrying out this pilot project.
Status of ACJ Interim Projects with completion dates of July 1, 2002* |
Evaluation of Siphon Crossings Evaluated and rehabilitated
|
Complete
|
May 1999
|
Hiawatha Regional Treatment Facility Part A 30-inch CSO interceptor Part B Regional Treatment and Storage Facility Part C Underflow Force Main and Outfall pipeline
|
Complete
|
July 2001
|
Newell Regional Treatment Facility Disinfection Tested and Report filed
|
Complete
|
July 2001
|
|
Teall Brook Floatables Control Facility
|
Complete
|
Dec 2001
|
Evaluation of CSO Toxicity Evaluated and report approved
|
Complete
|
May 2002
|
|
Erie Boulevard Storage System Upgrade
|
Complete
|
June 2002
|
Onondaga Creek Floatables Control Facility Skimmer boat in operation summer 02 under contract. Long-term control will include purchase of boat by County.
|
Complete
|
June 2002
|
|
Harbor Brook Floatables Control Facility
|
Complete
|
July 2002
|
Harbor Brook In-Water System** Project changed, Facility Plan drafted
|
|
|
Kirkpatrick Street Pump Station Upgrade** Construction delays
|
|
|
*As described in Appendix B pp. 10-12 of the ACJlisted chronologically by date completed **Milestone revision requested
|
(ACJ Completion date7/1/02Complete June 2002 - Milestone met)
Construction completed, system operational. System is
fully operational. Project closeout activities
underway.
|
|
Gate 1 of Erie Boulevard storage system improvements near Niagara Mohawk Building
|
The project involved upgrading an existing large
diameter underground storm sewer previously
constructed to store combined sewage in storm
situations. Following a storm event, the combined flow
is released back to the sewer system for treatment at
Metro. The existing system had experienced operational
problems with control gates and was in need of
upgrading to function effectively. The project is now
complete and has successfully operated in storm
events.
(ACJ completion date5/1/00CompleteMay 2000)
Facility in operation. This $4.7 m facility was
completed by its ACJ milestone date of May 1, 2000 and
is in operation. This is the largest floatables
facility currently planned by the County and removes
floatable debris from both the Burnet and Butternut
trunk sewers to prevent their discharge into Onondaga
Creek. Quarterly reports on their operation are filed
with DEC.
(ACJ completion date7/1/02CompleteJuly 2002)
Construction complete. Construction was completed and
system is operational with three net bags in place.
County personnel have begun maintaining facility.
15-month performance period has started. Punch list
being worked on.
This project consists of a floating net-bag collection
system in the brook which includes 3 net bags to trap
floatables before they enter Onondaga Lake.
(ACJ completion date7/1/02Complete July 2001 - ahead of schedule)
Construction completed and operational. Construction
of all major structures of this facility is complete.
The facility was operational by July 2001.
(ACJ completion date5/1/99Complete May 1999)
Facility fully operational. This is the first
floatables control facility completed under the
Onondaga Lake ACJ program. Quarterly operation and
maintenance reports are filed with DEC.
(ACJ completion date7/1/02pilot disinfection project completed)
Newell Street CSO investigated under Midland project.
Abatement of the Newell Street CSO is currently being
evaluated under the Midland Phase II and III design
contracts with EEA.
(ACJ completion date7/1/02 -CompleteJune 2002)
Trash skimmer vessel in operation in harbor. The
County obtained the services of a private company, CNY
Aquatic Harvesting, to collect, remove and dispose of
floatable debris from the Inner Harbor beginning on
June 7. Coordinated operation with officials from the
Lakefront Development Corporation to coincide with the
scheduled events in the Harbor. The response of
officials and the public to the operation of the boat
and its ability to pick up the floatable debris and
improve the aesthetics of the harbor has been
extremely positive.
DEC reviewing skimmer vessel usage. In a letter dated
May 22, 2002 to DEC as per their request, the County
provided a detailed summary of the pilot project,
alternative solutions that were evaluated, and
information on the County's recommendation to use a
skimmer boat in conjunction with a boom in the Inner
Harbor to provide effective floatables containment and
collection. The letter concluded with a formal request
for approval from State DEC on the use of the boat
with or without booms as meeting the intent of the ACJ
requirement for control of CSO-derived floatables in
the harbor and Lake. The letter also contained a list
of additional benefits of selective placement and use
of booms in the harbor area. The information provided
in the letter and the report filed April 26th are
currently under review by DEC.
County looking into skimmer boat purchase for future
years. Work has begun on collecting information for
necessary authorizations and development of bid
specifications for purchase of a skimmer boat by the
County.
(ACJ completion date7/1/02CompleteMay 1999Milestone met)
Work completed May 28, 1999 well ahead of schedule.
(ACJ completion date7/1/02CompleteMilestone met)
Construction completed. Construction was completed on
this project in December 2001 and the facility is
operational. Project consists of an underground
floatables capture facility consisting of an automatic
screening device which directs floatables and
screenings to underflow sewer channel.
Completed
Former combined lines revised. One of two previous
combined lines in the Water Street area was relined and
now transports wastewater only. The other combined
line is now used for stormwater only.
Completion of this work has eliminated one additional
CSO on Onondaga Creek. From the start of the lake
improvement program, the County has reduced the number
of untreated CSOs from 66 to 57 which includes total
closure of 4 overflow points by sewer separation.
|
|
Appearance of West Street after sewer separation project
|
(ACJ completion date7/1/02Complete- December 1999Milestone met)
This was the first sewer separation project conducted
under ACJ and eliminated 3 CSOs on Onondaga Creek by
converting them to stormwater discharge only.
(ACJ completion datePhase II RTF5/01/04 & Phase III Conveyance5/01/07)
Report compiled on workshop on disinfection.
A report was compiled on the CSO Disinfection Workshop
sponsored by the County and held on October 15.
(Click here.) The
report summarizes presentations made and information
presented. Copies of the report were distributed to
local officials and interested groups and individuals.
Presentations were given by EPA, DEC, Syracuse
Research, Moffa/Brown Caldwell and representatives of
other municipalities at the workshop.
|
|
View of the north HRFS (phosphorus removal), looking toward the southwest BAF (ammonia removal) cells (Oct 30, 2002)
|
Further preliminary designs developed and information compiled
The County and their consultants prepared a number of
presentation boards and informational materials in
preparation for a public meeting scheduled and held by
the County Legislature on November 25 on the Midland
project.
In addition, the design engineers began to develop a
preliminary design for the County's current preferred
option which includes a combination of vortex and
below-ground storage in two separate areasone at
the original site and the other across the street.
Judge rules that County can condemn City property
The Honorable Thomas J. McAvoy in U.S. District Court,
issued his finding on November 20, 2002 that the
County has the authority to condemn City property
needed for the Midland project. The Judge also ruled
that the City and Syracuse Urban Renewal Agency should
receive compensation for the properties. The County
and City were asked by the Judge to submit appropriate
documents to allow the Court to determine the value of
the property.
Final Design work on hold
Design engineers completed the 95% design documents
for Phase II of the project which includes the RTF and
1000 FT of conveyance to the facility and plans which
were transmitted to the State DEC on December 3, 2001.
The County will not finalize the documents to 100%
until the County and City are able to reach agreement
and/or the Federal Court orders transfer of the needed
City property to the County or takes other action
which resolve the issue.
Design documents received by County
Design documents were finalized and forwarded to the
County for the additional ten areas in the City of
Syracuse proposed for sewer separation under the ACJ.
Funding for this design effort was through the U.S. Army
Corps of Engineers. Design documents for the Brighton
Avenue and the Water streets projects were completed
under this contract and finalized earlier so that
projects could be moved along into construction. Water
Street is completed, and the Brighton Avenue project is
underway.
(ACJ datesCommence construction of conveyances and RTFMay 1, 2003 Completion of conveyances 5/1/07 and RTF 1/1/12)
The following work activities were accomplished this
month: continued environmental review activities for
the Environmental Information Document, continued
development of preliminary detour plan for traffic,
and completed subsurface exploration testing on three
preferential sites for the project.
The goal of the Clinton project is to address the
abatement of ten CSO's between Fayette and Adams
Streets to be served by a Clinton Area Facility
located near downtown Syracuse. The Facilities Plan
evaluates alternative technologies to address the
overflows and alternative sites for a
storage-treatment facility. The current contract with
EEA also covers preparation of an Environmental Impact
Assessment and conceptual design.
(ACJ completion date - 7/1/02 - Revision requested)
Milestone revision requested. In a letter dated June
5, 2002 to DEC, the County provided a summary of the
history and status of this project with a milestone
revision request. The letter requested that all the
ACJ parties agree to a stipulated modification of the
ACJ that removed the in-water demonstration project
from the ACJ and established a new minor milestone
date of July 1, 2003 for submittal to DEC of a final
Facility Plan. This letter was follow up to the
County's presentation on the project given at the ACJ
All-parties meeting held on May 23.
At All-Parties meeting held on July 26, this project
and the need for a milestone revision was discussed.
The draft Facilities Plan issued in March 2002 by the
County indicates that the County cannot proceed with
implementation of the in-water system due to the
extent and type of contamination present in the area
and the fact that the contamination is on-going. As
the County has indicated previously to the ACJ parties
at previous all-parties' meetings, the County feels
these concerns make the project not technically
feasible at this time; therefore a milestone revision
is necessary.
The draft facility plan, which was released in March
2002 outlines and evaluates alternative technologies
including the in-water system for abating and treating
the 18 CSOs which release into Harbor Brook and
identifies potential sites for CSO abatement
facilities. The County will proceed with public
participation activities with interested residents and
organizations in the Harbor Brook area and could
finalize the Facility Plan with a recommended
alternative over the next year.
|
|
An executive summary of the 2001 ambient monitoring program was made widely available in November.
|
Bi-weekly tributary sampling events were conducted
November 6 and 19. Appropriate notification was
provided to DEC and ASLF prior to sampling dates.
Sampling in the Lake was conducted on November 7, 12,
and 26. The sampling on the 7th was the weekly
nitrogen sampling, on the 12th a double lake sampling
event was conducted and on the 26th the south deep
was sampled. Appropriate notification was provided to
DEC and ASLF prior to all sampling dates.
None to report.
All fisheries sampling events are completed for the
year.
During October, staff completed sorting the forty
tributary screen samples. On October 14th, the samples
were shipped to Aquatic Resources Center in College
Grove Tennessee for identification.
On November 20, County staff retrieved the caged and
uncaged artificial substrate which had been anchored
in the Lake earlier this year. The samples were
shipped to a consultant hired to conduct a zebra
mussel density assessment to calculate lake-wide
mussel densities in the littoral zone.
Draft monitoring report forwarded to DEC
On November 1, 2002, the County forwarded a draft copy
of the Annual Report for 2001 for the County's Lake
Ambient Monitoring Program to DEC for their comment
and review. As a follow up, County staff met with DEC
staff regarding their review and comments on November
20, 2002. The final report is due to be submitted to
DEC in December.
|
|
Completion of the concrete slab for the HRFS phosphorus treatment tankage (Nov 5, 2002)
|
None to report
None to report
Contract with The Pike Company increased to
accommodate wage rate differential from general to
heavy highway on the Ammonia/Phosphorus Removal
Project. Change Order amount: $950,858.00. Executed
11/05/02.
No action items presented.
No action items to be presented.
No items scheduled.
State Bond Act funds
Payments received this month from State Bond Act funds:
-
Erie Boulevard Storage System: Request #17 for $7,197.16 received on 11/15/02 for aggregate total of $1,530,000.00.
-
Midland Ave Conveyances/RTF: Request #17 for $60,836.98 received on 11/22/02 for aggregate total of $2,449,801.53.
Total received to date in State Bond Act funds: $32,795,585.
Federal EPA funds
Payments received this month from Federal EPA Funds:
None to report.
Total received to date in Federal EPA Funds: $16,286,189.
Federal Army Corps of Engineers funds
Payments received this month from U.S. Army Corps of Engineers:
-
Sewer separation: Request #3 for $34,943.19 received on 11/26/02 for aggregate total of $698,863.74
-
Urban Best Management Practices (UBMP): Request #2 for $12,107.57 received on 11/26/02 for aggregate total of $22,098.23.
Total received to date from U.S. Army Corps of Engineers Funds: $720,961.97.
The following reimbursement payments were received from EFC during the month of November:
-
Ammonia/Phosphorus Removal: Request #3 for $514,113.39 on 11/1/02, Request #4 for $204,250.00 received on 11/18/02, and Request #5 for $4,298,717.32 received on 11/22/02 for aggregate total on second loan of $7,237,878.51. Total for both
loans:
$60,578,878.51.
-
Erie Boulevard Storage System: Request #15 for $14,239.83 received on 11/18/02 for aggregate total of $2,000,560.86.
-
Kirkpatrick Street Pump Station & F/M: Request #23 for $196,670.01 received on 11/18/02 for aggregate total of $10,371,471.62.
Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $95,974,494 (short term), $7,677,996 (long term).
None to report for December
-
Site acquisition for Midland Project Phase IIOctober 1, 2002Revision requested.
-
Submit Engineering Report for Clinton ProjectNovember 1, 2002Revision requested.
|