Go to home page
Go to home page
Fitting up the last piece of the 84-inch outfall pipe (Oct 10, 2002)
Fitting up the last piece of the 84-inch outfall pipe (Oct 10, 2002)

Monthly report — October 2002

Accelerated construction
 

Highlights of the month

Placement of steel and concrete moves at accelerated rate on new facilities.   Placement of steel and concrete for the facilities is moving at an accelerated rate on the ammonia removal and ultraviolet disinfection facilities. In October, the contractor started work on the phosphorus removal facilities as well with placement of slab on grade and forming of the concrete tank walls. Approximately 13,000 cubic yards of concrete has been place by the end of October of 27,000 cubic yards expected for the whole project. Process piping for the Ammonia removal facilities is being installed and work on the secondary effluent pump station continued with installation of the remainder of the base slabs and placement of the concrete wet well walls.
 

Pre-construction and public availability meetings held on Brighton sewer separation.   A pre-construction meeting on this contract with C.O. Falter for sewer separation in the area of Brighton, Marguerite, Hunt and Bishop avenues was held on October 17, 2002. In addition a public availability-open house session was held Tuesday, October 22 at Elmwood School. Representatives of the County, the contractor, Niagara Mohawk, the design consultant, project construction managers and the City DPW were present to provide information to interested residents and respond to questions on the scope and schedule of construction. A detailed letter was sent out to over 100 residents and property owners in the area to be impacted by the sewer separation project prior to the meeting.
 

Kirkpatrick project completed and operational.   The new wet weather pumps were operational since September 8, 2002. During September and October, the wet weather pumps were utilized for 100% of both dry weather and wet weather flow. As of October 31, 2002, the replacement pumps and screens for the pump station have been operating as well. As reported in a letter to DEC dated November 8, 2002, the project was complete and fully operational prior to November 1, 2002 (the requested new major milestone date). Punch list and other evaluation activities continue.
Mayor Driscoll and County Executive Pirro describe benefits of the Leaf Bag Program, Oct 31
Mayor Driscoll and County Executive Pirro describe benefits of the Leaf Bag Program, Oct 31


 

Kick-off of fall leaf public education campaign.   A press conference was held on Thursday, October 31 by the County Executive and the Mayor to kick off a new program to help the lake and keep leaves out of the sewers and treatment process facilities—Bag ’Em! Held at the Eastwood Senior Center, the press conference noted that paper leaf bags were available free to City residents to bag their leaves. 10,000 bags were purchased through a Lake Partnership grant from the U.S. Army Corps of Engineers and the bags were placed in libraries throughout the City as well as youth and senior centers. The Urban Best Management Practices campaign has proven extremely popular with distribution sites calling for refills almost immediately.

Projects under construction

Ammonia / Phosphorus Removal Project (Metro)

Final preparations underway to pour concrete for a gallery in the phosphorus removal facility, Oct 10, 2002
Final preparations underway to pour concrete for a gallery in the phosphorus removal facility, Oct 10, 2002

(ACJ Completion date for Ammonia Full Scale—11/3/03—schedule concerns)
(ACJ Completion date for Phosphorus Removal Stage II—4/1/05—on schedule)

Construction continues at accelerated pace

Placement of steel and concrete is moving at an accelerated rate in the ammonia removal and UV portions of the facilities. An acceleration schedule was developed and implemented to attempt to recover some of the time lost earlier in the construction during site preparation contracts.

In October, the contractor began work on the phosphorus removal facilities as well with placement of concrete slab on grade and forming of concrete tank walls. Work to tie-in the existing plant galleries with the new facilities is also progressing as is yard piping. This month, construction of the steam piping to the new steam vault progressed and work on the concrete walls for the UV disinfection facility also was underway.

Electrical work continues

New steam and condensate lines, Oct 17, 2002
New steam and condensate lines, Oct 17, 2002

Installation of below slab conduits continued this month at the BAF (Ammonia removal ) complex. Work was also continued on the main electrical substation.

Dewatering continues

Dewatering (under contract 2D) is continuing and the system has lowered ground water below the excavation of all areas needed. It is anticipated that full scale dewatering and treatment will be discontinued by the end of 2002. Dewatering and ground water treatment for miscellaneous trench excavations will be conducted on an as needed basis.

Process equipment continues arriving

Process equipment from US Filter/Krüger continues arriving regularly on site and is turned over to general contractor for future installation.

HVAC work

Three new boilers have been set in the low lift pump station boiler room. The contractor continues to install the boiler connections and exhaust system.

Meetings held

The following meetings were held this month:

  • Construction progress meeting were held weekly on Thursdays at 10 a.m.
  • Weekly meetings held between construction manager (CDM/C&S), design engineer and the County.
  • Modification review meetings held weekly.
  • Scheduling meetings held weekly with all prime contractors.
  • Special meetings were held this month on October 17th, with the general contractor (Pike) and union representatives concerning EEO and M/WBE issues.

This is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive impacts on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Kirkpatrick Street Pump Station upgrade (CSO)

(ACJ completion date—7/1/02—requested milestone revision met 11/1/02)

Final touches: planting and paving at Kirkpatrick Pump Station, Oct 29, 2002
Final touches: planting and paving at Kirkpatrick Pump Station, Oct 29, 2002

Facility fully operational. As of October 31, 2002, the dry weather replacement pumps and screens were operating. During September and October, the new wet weather pumps were operational since September 8 and were utilized for 100% of both dry and wet weather flow.

A number of additional related activities were completed during the month of October including: completion of wiring and start up of pumps, completion of installation of transducer for existing wet well, relocation of existing water service, completion of yard piping, relocation of existing floor drain laterals, stucco application, roofing, landscaping and site paving on facility.

Milestone revision requested

New equipment at Kirkpatrick
New equipment at Kirkpatrick

Because the project has expanded in scope since it was originally conceived in the ACJ and unforeseen hydrogeologic conditions impacted the construction schedule, the County requested that the milestone be extended from July 1, 2002 to November 1, 2002 by which time the County anticipated the project would be fully operational. Decision on revision request still pending. A letter was forwarded to DEC on November 8, 2002, informing DEC that the facility was complete and fully operational by the November 1, 2002 date.

Brighton Avenue sewer separation project (CSO)

A Notice of Intent to Award was sent to C.O. Falter on October 9th for the $2.1 million sewer separation project which will install new separate sanitary sewers on portions of Brighton Avenue and Hunt, Marguerite and Bishop avenues on the City's south side.

A pre-construction meeting was held October 17th and a public availability session was held at Elmwood School on Tuesday October 22 as well as notices mailed out to over 100 residents and property owners from both the County and NiMo.

Niagara Mohawk began installation of a new gas main in the area during October. Work up to and including a portion of Brighton Avenue must be completed before the County's contractor can begin work on the sewers. Contacts with Niagara Mohawk were made throughout the month and coordination meetings held as needed.

County construction is scheduled to start on this project in November dependent on weather and NiMo's progress. The entire project is estimated to be completed in 6-9 months, weather dependent. New sewer lines will be installed and existing combined lines will be converted to storm water use only. Lead water service lines encountered will be replaced by the County. Much coordination will be necessary between the County's contractor, NiMo, City Water, and other utilities.

Projects completed

Aeration system upgrade (Metro)

(ACJ Completion Date—7/1/02—Complete—January 2000)

Retrofitting a total of eight tanks was completed well ahead of the required ACJ completion milestone. The tanks are all fully operational with the new more energy efficient and effective fine-bubble diffuser aeration system. Lower ammonia levels reported in lake corresponding with operation of new system.

Digester mods/chemical storage (Metro)

(ACJ completion date—7/1/02—Complete—ahead of schedule)

Digital system improvements (Metro)

(ACJ completion date—7/1/02—Complete—December 2001—ahead of schedule)

New system in operation. The new digital system is operational in all locations. Certificate of Substantial completion was submitted to NYSDEC. The contractor's warranty continued through May 31, 2002.

Odor control and residuals handling (Metro)

(ACJ Completion date—7/1/02—Complete—December 2000—ahead of schedule)

Project completed. This project, which was designed to reduce odors at the headworks of Metro adjacent to Hiawatha Boulevard, is completed and in operation. Positive comments have been received from the public on a noticeable reduction in odors as a result of this project.

Phosphorus removal pilot project (Metro) (ACJ milestone date for completion of pilot—4/1/07 - well ahead of schedule)

Final report in preparation. The pilot was completed in December 2000. Currently work continues on evaluation and analysis of data compiled during the pilot operation which tested a variety of phosphorus removal technologies. The County is more than 6 years earlier than is called for in the ACJ in carrying out this pilot project.

ACJ interim projects

Status of ACJ Interim Projects
with completion dates of July 1, 2002*
Evaluation of Siphon Crossings
Evaluated and rehabilitated
Complete May 1999
Hiawatha Regional Treatment Facility
Part A 30-inch CSO interceptor
Part B Regional Treatment and Storage Facility
Part C Underflow Force Main and Outfall pipeline
Complete July 2001
Newell Regional Treatment Facility
Disinfection Tested and Report filed
Complete July 2001
Teall Brook Floatables Control Facility Complete Dec 2001
Evaluation of CSO Toxicity
Evaluated and report approved
Complete May 2002
Erie Boulevard Storage System Upgrade Complete June 2002
Onondaga Creek Floatables Control Facility
Skimmer boat in operation summer ’02 under contract. Long-term control will include purchase of boat by County.
Complete June 2002
Harbor Brook Floatables Control Facility Complete July 2002
Harbor Brook In-Water System**
Project changed, Facility Plan drafted
   
Kirkpatrick Street Pump Station Upgrade**
Construction delays
   
 *As described in Appendix B pp. 10-12 of the ACJ—listed chronologically by date completed
**Milestone revision requested

Erie Boulevard storage system upgrade (CSO)

(ACJ Completion date—7/1/02—Complete June 2002 - Milestone met)

Construction completed, system operational. System is fully operational. Project closeout activities underway.
Gate 1 of Erie Boulevard storage system improvements near Niagara Mohawk Building
Gate 1 of Erie Boulevard storage system improvements near Niagara Mohawk Building

The project involved upgrading an existing large diameter underground storm sewer previously constructed to store combined sewage in storm situations. Following a storm event, the combined flow is released back to the sewer system for treatment at Metro. The existing system had experienced operational problems with control gates and was in need of upgrading to function effectively. The project is now complete and has successfully operated in storm events.

Franklin Street floatables control facility (CSO)

(ACJ completion date—5/1/00—Complete—May 2000)

Facility in operation. This $4.7 m facility was completed by its ACJ milestone date of May 1, 2000 and is in operation. This is the largest floatables facility currently planned by the County and removes floatable debris from both the Burnet and Butternut trunk sewers to prevent their discharge into Onondaga Creek. Quarterly reports on their operation are filed with DEC.

Harbor Brook floatables control facility (CSO)

(ACJ completion date—7/1/02—Complete—July 2002)

Construction complete. Construction was completed and system is operational with three net bags in place. County personnel have begun maintaining facility. 15-month performance period has started. Punch list being worked on.

This project consists of a floating net-bag collection system in the brook which includes 3 net bags to trap floatables before they enter Onondaga Lake.

Hiawatha Boulevard regional treatment facility (CSO)

(ACJ completion date—7/1/02—Complete July 2001 - ahead of schedule)

Construction completed and operational. Construction of all major structures of this facility is complete. The facility was operational by July 2001.

Maltbie Street floatables control facility (CSO)

(ACJ completion date—5/1/99—Complete May 1999)

Facility fully operational. This is the first floatables control facility completed under the Onondaga Lake ACJ program. Quarterly operation and maintenance reports are filed with DEC.

Newell Street pilot treatment facility

(ACJ completion date—7/1/02—pilot disinfection project completed)

Newell Street CSO investigated under Midland project. Abatement of the Newell Street CSO is currently being evaluated under the Midland Phase II and III design contracts with EEA.

Onondaga Creek floatables control facility

(ACJ completion date—7/1/02 -Complete—June 2002)

Trash skimmer vessel in operation in harbor. The County obtained the services of a private company, CNY Aquatic Harvesting, to collect, remove and dispose of floatable debris from the Inner Harbor beginning on June 7. Coordinated operation with officials from the Lakefront Development Corporation to coincide with the scheduled events in the Harbor. The response of officials and the public to the operation of the boat and its ability to pick up the floatable debris and improve the aesthetics of the harbor has been extremely positive.

DEC reviewing skimmer vessel usage. In a letter dated May 22, 2002 to DEC as per their request, the County provided a detailed summary of the pilot project, alternative solutions that were evaluated, and information on the County's recommendation to use a skimmer boat in conjunction with a boom in the Inner Harbor to provide effective floatables containment and collection. The letter concluded with a formal request for approval from State DEC on the use of the boat with or without booms as meeting the intent of the ACJ requirement for control of CSO-derived floatables in the harbor and Lake. The letter also contained a list of additional benefits of selective placement and use of booms in the harbor area. The information provided in the letter and the report filed April 26th are currently under review by DEC.

County looking into skimmer boat purchase for future years. Work has begun on collecting information for necessary authorizations and development of bid specifications for purchase of a skimmer boat by the County.

Siphon rehabilitation

(ACJ completion date—7/1/02—Complete—May 1999—Milestone met)

Work completed May 28, 1999 well ahead of schedule.

Teall Avenue floatables control facility

(ACJ completion date—7/1/02—Complete—Milestone met)

Construction completed. Construction was completed on this project in December 2001 and the facility is operational. Project consists of an underground floatables capture facility consisting of an automatic screening device which directs floatables and screenings to underflow sewer channel.

Water Street CSO 024 sewer separation

Completed

Former combined lines revised. One of two previous combined lines in the Water Street area was relined and now transports wastewater only. The other combined line is now used for stormwater only.

Completion of this work has eliminated one additional CSO on Onondaga Creek. From the start of the lake improvement program, the County has reduced the number of untreated CSOs from 66 to 57 which includes total closure of 4 overflow points by sewer separation.
Appearance of West Street after sewer separation project
Appearance of West Street after sewer separation project

West Street sewer separation

(ACJ completion date—7/1/02—Complete- December 1999—Milestone met)

This was the first sewer separation project conducted under ACJ and eliminated 3 CSOs on Onondaga Creek by converting them to stormwater discharge only.

Projects under design

Midland Conveyances and Regional Treatment Facility (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07)

Workshop on disinfection held. Working with its design engineers and consultants, the County sponsored a workshop on disinfection on October 15, 2002. City, County and State officials and interested citizens and groups were invited to take part and share the latest information on disinfection. Presentations were given by EPA, DEC, Syracuse Research, Moffa/Brown Caldwell and representatives of other municipalities. About 20 people attended.

Design work on hold. Design engineers completed the 95% design documents for Phase II of the project which includes the RTF and 1000´ of conveyance to the facility and plans which were transmitted to the State DEC on December 3, 2001. The County will not finalize the documents to 100% until the County and City are able to reach agreement and/or the Federal Court orders transfer of the needed City property to the County or takes other action which resolve the issue.

No resolution or agreement achieved to date on facility.

Other work activities this month

Design engineer prepared and delivered to the County supplemental copies of the geotechnical reports and Data on the Phase II portion of the Midland project.

Design of additional ten sewer separation areas being finalized (CSO)

Design documents due. Design documents are being finalized following internal review for the additional ten areas in the City of Syracuse proposed for sewer separation under the ACJ. Funding for this design effort is through the U.S. Army Corps of Engineers. Design documents for the Brighton Avenue and the Water Street projects were completed under this contract and finalized earlier so that projects could be moved along for construction.

Projects in facility planning stage

Clinton conveyances and regional treatment facility

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003
Completion of conveyances 5/1/07 and RTF 1/1/12)

Environmental review activities for facility plan and environmental information document continued on areas common to preferred sites and traffic engineering consultation work continued to be compiled. In addition, the remaining subsurface borings were scheduled for the three preferential sites.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams Streets to be served by a Clinton Area Facility located near downtown Syracuse. The Facilities Plan evaluates alternative technologies to address the overflows and alternative sites for a storage-treatment facility. The current contract with EEA also covers preparation of an Environmental Impact Assessment and conceptual design.

Harbor Brook CSO abatement project

(ACJ completion date - 7/1/02 - Revision requested)

Milestone revision requested. In a letter dated June 5, 2002 to DEC, the County provided a summary of the history and status of this project with a milestone revision request. The letter requested that all the ACJ parties agree to a stipulated modification of the ACJ that removed the in-water demonstration project from the ACJ and established a new minor milestone date of July 1, 2003 for submittal to DEC of a final Facility Plan. This letter was follow up to the County's presentation on the project given at the ACJ All-parties meeting held on May 23.

At All-Parties meeting held on July 26, this project and the need for a milestone revision was discussed. The draft Facilities Plan issued in March 2002 by the County indicates that the County cannot proceed with implementation of the in-water system due to the extent and type of contamination present in the area and the fact that the contamination is on-going. As the County has indicated previously to the ACJ parties at previous all-parties' meetings, the County feels these concerns make the project not technically feasible at this time; therefore a milestone revision is necessary.

The draft facility plan, which was released in March 2002 outlines and evaluates alternative technologies including the in-water system for abating and treating the 18 CSOs which release into Harbor Brook and identifies potential sites for CSO abatement facilities. The County will proceed with public participation activities with interested residents and organizations in the Harbor Brook area and could finalize the Facility Plan with a recommended alternative over the next year.

Ambient monitoring program

Tributary sampling

Scientist samples water from a tributary of Onondaga Lake (file photo)
Scientist samples water from a tributary of Onondaga Lake (file photo)

Bi-weekly tributary sampling events were conducted October 8 and 17th. The event on the 17th qualified as a high flow event. With this event, the County has completed its required five high flow tributary sampling events for the year. Appropriate notification was provided to DEC and ASLF prior to sampling dates.

Lake sampling

Sampling in the South Deep area was conducted on October 2, 15, 24 and 29. These dates covered fall turnover sampling. Appropriate notification was provided to DEC and ASLF prior to sampling dates.

River sampling

None to report.

Fisheries sampling

During October, juvenile seining events were conducted on October 7, 9 and 10. This completes 7 of the required 8 such sampling events. Gill netting was conducted October 1, 3 and 4. During the month, staff began sorting the larval fish samples previously obtained.

Macrovertebrate sampling

During October, staff completed sorting the forty tributary screen samples. On October 14th, the samples were shipped to Aquatic Resources Center in College Grove Tennessee for identification.

Zebra mussel sampling

None to report this month.

Gage station agreement

Initiated a contract with the U.S. Department of the Interior for the cooperative funding for the operation and maintenance of eleven gaging stations and one lake gage station. County contribution is up to $72,290.

Additional activities and accomplishments

BAG ’EM! Leaf campaign started as part of Urban Best Management Practices

County Executive Pirro initiates the effort to keep leaves out of sewers and treatment plants, Oct 31, 2002
County Executive Pirro initiates the effort to keep leaves out of sewers and treatment plants, Oct 31, 2002

The public educational campaign to encourage the use of paper leaf bags to decrease the amount of leaves getting into the sewer system was kicked off this month with a press conference on October 31st with the County Executive and the Mayor participating. The entire program involves the purchase and distribution of over 10,000 bags which were received in October. Distribution sites were identified and included all branch libraries in the City and youth and senior centers. Ads and flyers developed and published and contacts with appropriate agencies including City DPW made.

The response of the public has been enthusiastic and bags stuffed with leaves are appearing throughout the City on curbs and being taken for composting by City DPW. Information on the campaign was also posted on the County and Lake Improvement web sites.

In addition to the newly purchased bags, the County made stickers for placement on formerly "Grass Only" bags that the City had leftover from a previous effort. We recycled the bags for use with the leaf campaign to respond to the overwhelming demand for more bags.

Contracts

New contracts

C.O. Falter Construction Corp. Contract with C.O. Falter Construction Corp. for general construction on Sewer Separation—CSOs 053 and 054. Contract amount: $2,167,851. Executed 10/22/02.

Amendments to existing contracts

CDM/C&S. Contract with CDM/C&S for project management services. Contract amendment amount: $90,000. Executed 10/10/02.

Change orders

No change orders executed this month.

Legislative action

Action items of the County legislature in the month of October: No action taken.

Action items for the October legislative committee: No items presented.

Upcoming for November committees: No action items to be presented.

Funding

Grants

State Bond Act funds

Driving casings under force mains Sept 30, 2002
Driving casings under force mains Sept 30, 2002

Payments received this month from State Bond Act Funds:

  • Harbor Brook FCF—Request #6 for $9,075.20, request #7 for $8,100.17 and request #8 for $150,805.07 for an aggregate total of $345,780.00 on 10/1/02.
  • Kirkpatrick Street Pump Station- Request #17 for $1,056,848.58 and request #18 for $310,232.76 for an aggregate total of $6,752,071.14 on 10/1/02.
  • Onondaga Creek FCF—request #7 for $8,720.37 for an aggregate total of $343,407.21 on 10/1/02.
  • Teall Brook FCF—request #11 for $23,937.33 for an aggregate total of $934,783.27 on 10/1/02.
  • Total received to date in State Bond Act funds—$32,727,551.

Federal EPA funds

Payments received this month from Federal EPA Funds: None to Report. Total received to date in Federal EPA Funds—$16,286,189.

Federal Army Corps of Engineers Funds

Payments received this month from U.S. Army Corps of Engineers: None to report. Total received to date from U.S. Army Corps of Engineers Funds—$663,876.

Loans

The following reimbursement payments were received from EFC during the month of October:

  • Ammonia/Phosphorus Removal—Request #31 for $789,995.46 and request #32 for $1,166,017.71 for aggregate total of $53,341,000 on 10/11/02 (This is the total amount of this first loan.)
  • Ammonia/Phosphorus Removal—request #1 for $1,579,538.16 and request #2 for $641,259.64 for aggregate total on this second loan of $2,220,797.80. Total for both loans: $55,561,797.80.
  • Kirkpatrick Street Pump Station—request #21 for $527,467.04 and request #22 fro $429,754.70 for aggregate total of $10,174,801.61 on 10/28/02.
  • Erie Boulevard—Request #13 for $30,401.35 and request #14 for $19,053.27 for aggregate total of $1,986,321.03 on 10/28/02.
  • Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $90,746,503 (short term), $7,677,996 (long term).

Upcoming

Meetings

Quarterly All-parties meeting—November 7, 2002

Milestones

  • Completion of interim projects—July 1, 2002
  • Site acquisition for the Midland Project-Phase II—revised from April 1, 2002 to October 1, 2002. (revision requested)
  • Submit engineering report for Clinton project—revised to November 1, 2002.(revision requested)


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection