Go to home page
Go to home page
54-inch stainless steel header piping for the BAF cells is lowered into place.
54-inch stainless steel header piping for the BAF cells is lowered into place.

Monthly report — September 2002

Equipment arriving
 

Highlights of the month

Process equipment arriving for ammonia/phosphorus removal facilities   Process equipment from US Filter/Krüger has begun arriving on site on a regular basis. Large diameter valves and other equipment have been delivered and turned over to the general contractor for installation. Placement of steel and concrete for the facilities continues and moving at an accelerated rate to attempt to recover some of time lost due to schedule delays encountered during site preparation. Approximately 11,000 cubic yards of concrete had been placed by the end of September of a total of 27,000 cubic yards expected for the whole project.
 

Technical lake advisors meet for two days   The Onondaga Lake Technical Advisory Committee met September 11 and 12 at the Onondaga Lake Yacht Club. In addition to the scientists, representatives of the State DEC, USEPA, USGS, Atlantic State Legal Foundation, Congressman Walsh's office and County Water Environment Protection Department staff were present and took part in the presentations and discussions. The meetings focused on the results of the County's Ambient Monitoring program to date and suggestions and considerations for future monitoring and modeling efforts.
 

Post-bid meeting held on Brighton sewer separation   Review was completed on the bids received on this project and a post-bid meeting was held with low bidder, C.O. Falter on September 30th. Project is scheduled to begin construction in November with a pre-construction meeting scheduled for October 17, 2002. A public availability session is scheduled for Tuesday, October 22 at Elmwood School. Arrangements for the public meeting and coordination efforts with NiMo and others were made during the month.
 

Kirkpatrick wet weather pumps started   This month, the construction of the new wet well was completed and installation of the wet weather pumps with start up of the pumps completed on September 5, 2002. Start up of the new dry weather pumps is scheduled for October.
 

OLP Outreach Committee and EPA representative tour Metro and CSO facilities   Tours of the construction at the new Ammonia/Phosphorus removal facilities currently under construction and CSO projects were given in September for a representative from EPA on an inspection tour on September 10 and members of the Onondaga Lake Partnership's Outreach Committee on September 18.

Projects under construction

Ammonia/phosphorus removal project (Metro)

East wall of BAF cells number 2 and number 4 for ammonia removal
East wall of BAF cells number 2 and number 4 for ammonia removal

(ACJ Completion date for Ammonia Full Scale—11/3/03—schedule concerns)
(ACJ Completion date for phosphorus Removal Stage II—4/1/05—on schedule)

Construction continues at accelerated pace.

Placement of steel and concrete is moving at an accelerated rate in the ammonia removal and UV portions of the facilities. An acceleration schedule was developed and implemented to attempt to recover some of the time lost earlier in the construction during site preparation contracts. In September, work in the secondary effluent pump station was initiated with installation of a portion of the base slab. Work in the existing plant galleries is progressing to allow tie-in with the new facilities when required. Yard piping was initiated this month with completion of steam and gas lines in the entrance area of the plant. Work is underway on the UV disinfection structure on concrete base slabs and walls.

The existing boilers were removed from the Low Lift Pump Station and this month three new boilers were set in the low lift pump station. Work continues on installation of the boiler connections and exhaust system. Boiler start up is scheduled for October 15, 2002.

Electrical work continues

Installing conduits in the electrical room
Installing conduits in the electrical room

Installation of below slab conduits continued this month at the BAF (ammonia removal) complex. Work was also started on the main electrical substation this month.

Dewatering continues

Dewatering (under contract 2D) is continuing and the system has lowered groundwater below the excavation of all areas needed. It is anticipated that full scale dewatering and treatment will be discontinued by the end of 2002. Dewatering and groundwater treatment for miscellaneous trench excavations will be conducted on an as needed basis.

Process equipment arriving

As mentioned in monthly highlights, process equipment from US Filter/Krüger is arriving regularly on site and turned over to general contractor for future installation.

Meetings held

The following meetings were held this month:

  • Construction progress meeting were held weekly on Thursdays at 10 a.m.
  • Weekly meetings held between construction manager (CDM/C&S), design engineer and the County.
  • Modification review meetings held weekly.
  • Scheduling meetings held weekly with all prime contractors.

This is the largest and most costly single project in the Amended Consent Judgment program and will have the greatest positive impacts on the water quality of Onondaga Lake by removing more ammonia and phosphorus from the Metro effluent discharge.

Kirkpatrick Street Pump Station upgrade (CSO)

(ACJ completion date—7/1/02—milestone revision requested)

Milestone revision requested

Construction at the Kirkpatrick Street Pump Station
Construction at the Kirkpatrick Street Pump Station

Because the project has expanded in scope since it was originally conceived in the ACJ and unforeseen hydrogeologic conditions have impacted the construction schedule, the County has requested that the milestone be extended to November 1, 2002 by which time the County anticipates the project would be fully operational. Decision on revision request still pending.

Construction activities

Construction activities related to the pump station upgrade continued this month.

The following activities were conducted this month: completed construction of the new wet well and installation of the wet weather pumps, started up wet weather pumps on September 5th, installation of site fence, completed masonry, completed training for bar screens, installed new wet well hoist rail and began installation of new dry weather pumps.

Electrical and mechanical activities

Wiring was completed on wet weather pumps, installed bar screen level transducers, demolition of electrical equipment of existing pumps, installation lighting for new wet well and installation miscellaneous ductwork and thermostat control conduit.

Activities planned for October include: installation and start up of new dry weather pumps.

Brighton Avenue sewer separation project (CSO)

Houses in the 053/054 sewer separation area
Houses in the 053/054 sewer separation area

After review of the bids previously received on this project in July, changes in the documents were made and the project was re-bid during the month of August. The pre-bid meeting on the revised bid was held on August 15 and bids were opened on August 23, 2002. Two bids were received and were reviewed during September. On September 30 a post-bid meeting was held with apparent low bidder, C.O. Falter. A Notice of intent to award was sent on October 9th for the $2.1 million project.

Construction is scheduled to start on this project in November and is estimated to be completed in 6-9 months, weather dependent. The project involves the streets of Bishop, Marguerite, Hunt and a portion of W. Brighton Avenue on the City's south side. New sewer lines will be installed and existing combined lines will be converted to stormwater use only. Lead water service lines encountered will be replaced by the County, and the existing gas main will be replaced by Niagara Mohawk. Much coordination will be necessary between the County's contractor, NiMo, City Water and other utilities.

A pre-construction meeting is scheduled for October 17th and a public availability session is set for Tuesday October 22.

Projects completed

Aeration system upgrade (Metro)

(ACJ Completion Date—7/1/02—Complete—January 2000)

Retrofitting a total of eight tanks was completed well ahead of the required ACJ completion milestone. The tanks are all fully operational with the new more energy efficient and effective fine-bubble diffuser aeration system. Lower ammonia levels reported in lake corresponding with operation of new system.

Digester mods/chemical storage (Metro)

(ACJ completion date—7/1/02—Complete—ahead of schedule)

Digital system improvements (Metro)

(ACJ completion date—7/1/02—Complete—December 2001—ahead of schedule)

New system in operation. The new digital system is operational in all locations. Certificate of Substantial completion was submitted to NYSDEC. The contractor's warranty continued through May 31, 2002.

Odor control and residuals handling (Metro)

(ACJ Completion date—7/1/02—Complete—December 2000—ahead of schedule)

Project completed. This project, which was designed to reduce odors at the headworks of Metro adjacent to Hiawatha Boulevard, is completed and in operation. Positive comments have been received from the public on a noticeable reduction in odors as a result of this project.

Phosphorus removal pilot project (Metro) (ACJ milestone date for completion of pilot—4/1/07 - well ahead of schedule)

Final report in preparation. The pilot was completed in December 2000. Currently work continues on evaluation and analysis of data compiled during the pilot operation which tested a variety of phosphorus removal technologies. The County is more than 6 years earlier than is called for in the ACJ in carrying out this pilot project.

ACJ interim projects

Status of ACJ Interim Projects
with completion dates of July 1, 2002*
Evaluation of Siphon Crossings
Evaluated and rehabilitated
Complete May 1999
Hiawatha Regional Treatment Facility
Part A 30-inch CSO interceptor
Part B Regional Treatment and Storage Facility
Part C Underflow Force Main and Outfall pipeline
Complete July 2001
Newell Regional Treatment Facility
Disinfection Tested and Report filed
Complete July 2001
Teall Brook Floatables Control Facility Complete Dec 2001
Evaluation of CSO Toxicity
Evaluated and report approved
Complete May 2002
Erie Boulevard Storage System Upgrade Complete June 2002
Onondaga Creek Floatables Control Facility
Skimmer boat in operation summer ’02 under contract. Long-term control will include purchase of boat by County.
Complete June 2002
Harbor Brook Floatables Control Facility Complete July 2002
Harbor Brook In-Water System**
Project changed, Facility Plan drafted
   
Kirkpatrick Street Pump Station Upgrade**
Construction delays
   
 *As described in Appendix B pp. 10-12 of the ACJ—listed chronologically by date completed
**Milestone revision requested

Erie Boulevard storage system upgrade (CSO)

(ACJ Completion date—7/1/02—Complete June 2002 - Milestone met)

Construction completed, system operational. System is fully operational. Project closeout activities underway.
Gate 1 of Erie Boulevard storage system improvements near Niagara Mohawk Building
Gate 1 of Erie Boulevard storage system improvements near Niagara Mohawk Building

The project involved upgrading an existing large diameter underground storm sewer previously constructed to store combined sewage in storm situations. Following a storm event, the combined flow is released back to the sewer system for treatment at Metro. The existing system had experienced operational problems with control gates and was in need of upgrading to function effectively. The project is now complete and has successfully operated in storm events.

Franklin Street floatables control facility (CSO)

(ACJ completion date—5/1/00—Complete—May 2000)

Facility in operation. This $4.7 m facility was completed by its ACJ milestone date of May 1, 2000 and is in operation. This is the largest floatables facility currently planned by the County and removes floatable debris from both the Burnet and Butternut trunk sewers to prevent their discharge into Onondaga Creek. Quarterly reports on their operation are filed with DEC.

Harbor Brook floatables control facility (CSO)

(ACJ completion date—7/1/02—Complete—July 2002)

Construction complete. Construction was completed and system is operational with three net bags in place. County personnel have begun maintaining facility. 15-month performance period has started. Punch list being worked on.

This project consists of a floating net-bag collection system in the brook which includes 3 net bags to trap floatables before they enter Onondaga Lake.

Hiawatha Boulevard regional treatment facility (CSO)

(ACJ completion date—7/1/02—Complete July 2001 - ahead of schedule)

Construction completed and operational. Construction of all major structures of this facility is complete. The facility was operational by July 2001.

Maltbie Street floatables control facility (CSO)

(ACJ completion date—5/1/99—Complete May 1999)

Facility fully operational. This is the first floatables control facility completed under the Onondaga Lake ACJ program. Quarterly operation and maintenance reports are filed with DEC.

Newell Street pilot treatment facility

(ACJ completion date—7/1/02—pilot disinfection project completed)

Newell Street CSO investigated under Midland project. Abatement of the Newell Street CSO is currently being evaluated under the Midland Phase II and III design contracts with EEA.

Onondaga Creek floatables control facility

(ACJ completion date—7/1/02 -Complete—June 2002)

Trash skimmer vessel in operation in harbor. The County obtained the services of a private company, CNY Aquatic Harvesting, to collect, remove and dispose of floatable debris from the Inner Harbor beginning on June 7. Coordinated operation with officials from the Lakefront Development Corporation to coincide with the scheduled events in the Harbor. The response of officials and the public to the operation of the boat and its ability to pick up the floatable debris and improve the aesthetics of the harbor has been extremely positive.

DEC reviewing skimmer vessel usage. In a letter dated May 22, 2002 to DEC as per their request, the County provided a detailed summary of the pilot project, alternative solutions that were evaluated, and information on the County's recommendation to use a skimmer boat in conjunction with a boom in the Inner Harbor to provide effective floatables containment and collection. The letter concluded with a formal request for approval from State DEC on the use of the boat with or without booms as meeting the intent of the ACJ requirement for control of CSO-derived floatables in the harbor and Lake. The letter also contained a list of additional benefits of selective placement and use of booms in the harbor area. The information provided in the letter and the report filed April 26th are currently under review by DEC.

County looking into skimmer boat purchase for future years. Work has begun on collecting information for necessary authorizations and development of bid specifications for purchase of a skimmer boat by the County.

Siphon rehabilitation

(ACJ completion date—7/1/02—Complete—May 1999—Milestone met)

Work completed May 28, 1999 well ahead of schedule.

Teall Avenue floatables control facility

(ACJ completion date—7/1/02—Complete—Milestone met)

Construction completed. Construction was completed on this project in December 2001 and the facility is operational. Project consists of an underground floatables capture facility consisting of an automatic screening device which directs floatables and screenings to underflow sewer channel.

Water Street CSO 024 sewer separation

Completed

Former combined lines revised. One of two previous combined lines in the Water Street area was relined and now transports wastewater only. The other combined line is now used for stormwater only.

Completion of this work has eliminated one additional CSO on Onondaga Creek. From the start of the lake improvement program, the County has reduced the number of untreated CSOs from 66 to 57 which includes total closure of 4 overflow points by sewer separation.
Appearance of West Street after sewer separation project
Appearance of West Street after sewer separation project

West Street sewer separation

(ACJ completion date—7/1/02—Complete- December 1999—Milestone met)

This was the first sewer separation project conducted under ACJ and eliminated 3 CSOs on Onondaga Creek by converting them to stormwater discharge only.

Projects under design

Midland conveyances and RTF (CSO)

(ACJ completion date—Phase II RTF—5/01/04 & Phase III Conveyance—5/01/07)

County compiles further information. County design engineers were tasked and spent further time on development of further information on various options. Side-by-side layouts and cross-sections for four of the options under discussion by the involved groups were finalized. Information was also compiled concerning anticipated chlorinated discharges for various operations.

Planning for a workshop on disinfection took place this month. The workshop will be sponsored by the County on October 15th for officials and interested citizens and groups to share the latest information on disinfection. No resolution or agreement achieved to date on facility.

Design work on hold. Design engineers completed the 95% design documents for Phase II of the project which includes the RTF and 1000 ft of conveyance to the facility and plans which were transmitted to the State DEC on December 3, 2001. The County will not finalize the documents to 100% until the County and City are able to reach agreement and/or the Federal Court orders transfer of the needed City property to the County or takes other action which resolve the issue.

Additional sewer separation

Design of additional 10 sewer separation areas being finalized (CSO), design documents due Design documents are being finalized following internal review for the additional 10 areas in the City of Syracuse proposed for sewer separation under the ACJ. Funding for this design effort is through the US Army Corps of Engineers. Design documents for the Brighton Avenue and the Water streets projects were completed under this contract and finalized earlier so that projects could be moved along for construction.

Projects in facility planning stage

Clinton conveyances and regional treatment facility

(ACJ dates—Commence construction of conveyances and RTF—May 1, 2003, Completion of conveyances 5/1/07 and RTF 1/1/12)

Activities. One meeting was held this month with the Mitigation Advisory Committee on September 5th. Environmental review activities continued on areas common to preferred sites and traffic engineering consultation work continued to be compiled. In addition, nine soil borings were completed on a couple of the preferential sites for the Clinton facility. A noise dissipation analysis with completed in response to a request for the Mitigation Advisory Committee.

The goal of the Clinton project is to address the abatement of ten CSOs between Fayette and Adams Streets to be served by a Clinton Area Facility located near downtown Syracuse. The Facilities Plan evaluates alternative technologies to address the overflows and alternative sites for a storage/treatment facility. The current contract with EEA also covers preparation of an Environmental Impact Assessment and conceptual design. A draft facility plan is available.

Harbor Brook CSO abatement project

(ACJ completion date - 7/1/02 - Revision requested)

Milestone revision requested. In a letter dated June 5, 2002 to DEC, the County provided a summary of the history and status of this project with a milestone revision request. The letter requested that all the ACJ parties agree to a stipulated modification of the ACJ that removed the in-water demonstration project from the ACJ and established a new minor milestone date of July 1, 2003 for submittal to DEC of a final Facility Plan. This letter was follow up to the County's presentation on the project given at the ACJ All-parties meeting held on May 23.

At All-Parties meeting held on July 26, this project and the need for a milestone revision was discussed. The draft Facilities Plan issued in March 2002 by the County indicates that the County cannot proceed with implementation of the in-water system due to the extent and type of contamination present in the area and the fact that the contamination is on-going. As the County has indicated previously to the ACJ parties at previous all-parties' meetings, the County feels these concerns make the project not technically feasible at this time; therefore a milestone revision is necessary.

The draft facility plan, which was released in March 2002 outlines and evaluates alternative technologies including the in-water system for abating and treating the 18 CSOs which release into Harbor Brook and identifies potential sites for CSO abatement facilities. The County will proceed with public participation activities with interested residents and organizations in the Harbor Brook area and could finalize the Facility Plan with a recommended alternative over the next year.

Ambient monitoring program

Tributary sampling

Sampling in Onondaga Creek
Sampling in Onondaga Creek

Bi-weekly tributary sampling events were conducted September 10 and 24. Appropriate notification was provided to DEC and ASLF prior to sampling dates.

Lake sampling

Summer season sampling continued this month with sampling in the South Deep area on September 4 and 17 and special weekly sampling on September 4, 12, 17, and 25. Appropriate notification was provided to DEC and ASLF prior to sampling dates. In addition, a special field survey was conducted at several sites in the lake in response to a fish kill observed by County monitoring technicians in the north end of the lake.

River sampling

A monthly and supplemental sampling of the river was completed on September 19.

Fisheries sampling

During September, juvenile seining events were conducted on September 11, 12, 13 and 16. This completes 6 of the required 8 such sampling events. Electrofishing events were conducted from September 23-25. This completed 2 of the required 2 such sampling efforts.

Macrovertebrate sampling

During September, 32 of the 40 tributary screen samples were sorted.

Zebra mussel sampling

During this month, the County's consultants, Beak Consultants, Inc., initiated the Lake Zebra mussel density assessment as per their contract. The project will calculate zebra mussel densities lake wide based on the results of the habitat selection task of the monitoring program which was conducted on June 25-26 this year.

Storm event monitoring

Near shore sampling was conducted following two storms in September. One storm was on Sunday, September 22 with a rainfall intensity of 0.41 inch/hr. The other event was on Friday, September 27, 2002.

Mass mailing on AMP informational materials. The following informational materials were mailed out to officials and interested publics and others this month: Fishing in Onondaga Lake, Measuring Progress in Onondaga Lake, and the Onondaga County Fact Sheet. Copies of the new 13-minute video on the AMP program were also mailed out to those requesting a copy.

Additional activities and accomplishments

Urban best management practices

Program gears up for Leaf campaign. Plans for a public educational campaign to encourage the use of paper leaf bags to decrease the amount of leaves getting into the sewer system were developed this month. Bags were designed and ordered with shipping expected in October. Ads and flyers developed and contacts with appropriate agencies including City DPW made.

Contracts

New contracts

Contract with Brower Kriz & Stynchcomb for professional services relating to construction contractor claims on Ammonia/Phosphorus. Contract amount: $50,000. Executed 9/6/02.

Contract with Moffa & Associates for further research and development of bid specifications for skimmer boat for Onondaga Creek FCF. Contract amount: $49,637. Executed 9/11/02.

Amendments to existing contracts

Contract with MPR Technologies amended for additional computer support. Contract amendment amount: $10,000. Executed 9/3/02.

Contract with EEA amended for completion of draft facilities plan and environmental work for the Clinton Street Conveyances & RTF project. Contract amendment amount: $175,458. Executed 9/19/02.

Contract with John Clare amended to include additional project management services on Clinton Street Conveyances and Sewer Separation projects. Contract amendment amount: $8,800. Executed 9/25/02.

Change orders

Contract with The Pike Company increased to accommodate the revised contract schedule and Value Engineering of the SIP Decking relating to the Ammonia/Phosphorus Removal Project. Change Order amount: $2,468,385.00. Executed 9/4/02.

Contract with C.O. Falter Construction Corp. increased for removal and disposal of excess debris, access road modifications and installation of a steel bar screen for the Harbor Brook FCF Project. Change Order amount: $30,269.21. Executed 9/11/02.

Contract with C.O. Falter Construction Corp. increased for installation of soldier piles, probe drilling and curb removal for the Kirkpatrick Street Pump Station /Force Main Project. Change Order amount: $105,695.75. Executed 9/12/02.

Contract with Ridley Electric increased for installation of additional conduits and re-routing of service conduits for the Erie Boulevard Storage System Project. Change Order amount: $10,359.47. Executed 9/16/02.

Legislative action

Action items of the County Legislature in the month of September: No action items presented.

Actions items of the County Legislature in the month of October: No action items to be presented.

Upcoming for October Committees: Appropriating $5,500,000 of serial bond proceeds authorized 9/7/99 to provide funds for design and other related expenses of the Clinton Street Conveyances & RTF project.

Funding

Grants

State Bond Act funds

Payments received this month from State Bond Act funds:
Erie Boulevard Storage System: Request #16 for $49,971.34 and Request #17 for $7,606.01 received on 9/27/02 for aggregate total of $1,522,802.84.
Midland Ave Conveyances/RTF: Request #15 for $22,544.34 and Request #16 for $27,268.26 received on 9/27/02 for aggregate total of $2,388,964.55.
Total received to date in State Bond Act funds: $31,159,833.

Federal EPA funds

Payments received this month from Federal EPA funds:
Ammonia/Phosphorus Removal: Request #5 for $4,159,990, Request #6 for $2,927,323 received on 9/18/02 and Request #7 for $2,432,344 received on 9/30/02 for aggregate total of $14,850,325.
Total received to date in Federal EPA funds: $16,286,189.

Federal Army Corps of Engineers funds

Payments received this month from U.S. Army Corps of Engineers:
Urban Best Management Practices (UBMP): Request #1 for $9,990.66 received on 9/19/02 for aggregate total of $663,875.55.
Total received to date from U.S. Army Corps of Engineers funds: $673,866.21.

Loans

The following reimbursement payments were received from EFC during the month of September:
Ammonia/Phosphorus Removal: Request #29 for $932,202.54 on 9/9/02 and Request #30 for $3,455,105.88 received on 9/4/02 for aggregate total of $51,384,986.77.
Total reimbursement monies received to date through EFC Loans for the funded ACJ projects: $85,563,015 (short term), $7,677,996 (long term).

Upcoming

Meetings

Quarterly All-parties meeting: November 7, 2002

Milestones

  • Completion of Interim Projects: July 1, 2002
  • Site Acquisition for the Midland Project-Phase II: Revised from April 1, 2002 to October 1, 2002.
  • Submit Engineering Report for Clinton Project: revised to November 1, 2002.


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection