Monthly report February 2002
Aeration system upgrade
(ACJ Completion Date7/1/02CompleteJanuary 2000)
Retrofitting a total of eight tanks was completed well ahead of the required ACJ
completion milestone. The tanks are all fully operational with the new more energy
efficient and effective fine bubble diffuser aeration
system. Lower ammonia levels
reported in lake corresponding with installation of new system.
Ammonia removal/phosphorus removal combined project
(ACJ Completion date for Ammonia Full Scale11/3/03on schedule)
(ACJ Completion date for Phosphorus Removal Stage II4/1/05ahead of schedule)
Site Preparation work continues.
Excavation of soils from the main footprint of the new facility including all the deep
pits was completed this month. Sheeting and bracing were installed for the 72" force
main, the 84" outfall pipe and the secondary effluent
pump station. Excavation for the
outfall pipe exposed the 42" and 18" force mains on
the Metro site and the mains
needed to be braced and support.
Extraction of all the old timber piles which were uncovered in the excavation work
was completed this month also.
Dewatering continues.
Dewatering (under contract 2D) is currently underway for the secondary effluent
pump station. Efforts to lower the groundwater in this area are hindered due to
impervious subsoil conditions. Alternative dewatering methods are being pursued by the
contractor.
Pile Installation begins.
The pile driving contractor mobilized on February 4th with the installation of the first
crane. Pile driving formally began on February 12th. During February, the contractor has
set up a total of three pile driving crews; two using vibratory hammers and one using an
impact hammer. Pile conflicts were encountered with existing sheeting and bracing in
the by-pass pit and the UV pits. Coordination meetings between contractors, design
engineers, construction mangers and the county have been held to determine future
options.
Other Contracts.
Contracts for general construction, electrical, HVAC and Plumbing (Contracts 4A, B,
C, and D) were signed in January. All began attending weekly progress meetings on the
entire project during February.
Meetings held.
The following meetings were held this month:
-
Construction progress meeting held weekly on Thursdays at 10 a.m.
-
Coordination meetings with CDM/C&S, EEA and the County held on 2/9,2/19 and 2/25.
This is the largest and most costly single project in the Amended Consent Judgment
program and will have the greatest positive impacts on the water quality of Onondaga
Lake by removing more ammonia and phosphorus from the Metro effluent discharge.
Digester modifications / chemical storage / digester cleaning (Phase III improvements)
(ACJ completion date7/1/02Completeahead of schedule)
Close-out activities.
Project close out activities continuing.
Digital system improvements
(ACJ completion date7/1/02CompleteDecember 2001ahead of schedule)
New system in operation.
The new digital system is operational in all locations. Certificate of Substantial
completion was submitted to NYSDEC. The contractor's warranty will continue through
May 2002.
The County is continuing with training of staff to optimize the operators' use of the
system.
Odor control and residuals handling
(ACJ Completion date7/1/02CompleteDecember 2000ahead of schedule)
Project completed
This project which was designed to reduce odors at the headworks of Metro adjacent
to Hiawatha Boulevard is completed and in operation. Positive comments have been
received from the public on a noticeable reduction in odors as a result of this project.
Phosphorus removal pilot project
(ACJ milestone date for completion of pilot4/1/07well ahead of schedule)
Final Report in preparation.
The pilot was completed in December 2000. Currently work continues on evaluation
and analysis of data compiled during the pilot operation which tested a variety of
phosphorus removal technologies.
The County is more than 6 years earlier than is called for in the ACJ in carrying out
this pilot project.
Clinton conveyances and regional treatment facility
(ACJ datesCommence construction of conveyances and RTFMay 1, 2003 Completion of conveyances 5/1/07 and RTF 1/1/12)
Activities continue to finalize draft Facilities
Plan. Activities this month include:
-
Submitted a preliminary draft Facilities Plan to the County for review.
-
Completed supplemental archeological Phase 1A analysis for additional
alternative siteDickerson St. Continued development of Phase IB work scope
for the Dickerson St. Site.
-
Draft Facility Plan to be released in March. The report will be forwarded to the
State DEC and other ACJ parties and public participation activities will continue
to receive public review and comment.
Meetings
During the month, meetings were held with persons representing and serving as
consultants to the Rescue Mission concerning possible
sites on west side of
Onondaga Creek including use of Dickerson St. site.
The goal of this project is to address the abatement
of ten CSOs between Fayette and
Adams Streets to be served by a Clinton Area Facility located near downtown Syracuse
and the Armory Square area. The contract work currently underway includes preparation
of a Facility Plan, which will evaluate alternative technologies to address the overflows
and alternative sites for any treatment facility. The contract also covers preparation of an
Environmental Impact Assessment and conceptual design.
Erie Boulevard storage system upgrade
(ACJ Completion date7/1/02on schedule)
Construction continues
The following
activities were completed this month: gate chamber sites have been
prepared for delivery of above ground buildings, instrumentation panels and poles have
been erected, a new submersible pump/flush mix valve was installed in gate chamber #1,
gate chambers have been pressure washed, and weir construction has been completed
except in CSO 080C. Installation of ultrasonic transducer mounting brackets is ongoing.
Pre-cast buildings are expected to be brought to the sites in March for installation to
house control equipment above ground.
Meetings.
Two construction progress meetings were held this month as well as a separate
meetings with contractors on instrumentation and control systems.
The project involves upgrading an existing large diameter underground storm sewer
previously constructed to store combined sewage in storm situations. Following a storm
event, the combined flow would be released back to the sewer system for treatment at
Metro. The existing system has experienced operational problems with control gates and
is in need of upgrading to function effectively.
Franklin Street floatables control facility
(ACJ completion date5/1/00CompleteMay 2000)
Facility in operation.
This $4.7 m facility was completed by its ACJ milestone date of May 1, 2000 and is in
operation. This is the largest floatables facility currently planned by the County and
removes floatable debris from both the Burnet and Butternut trunk sewers to prevent their
discharge into Onondaga Creek. Quarterly reports on their operation are filed with DEC.
Harbor Brook floatables control facility
(ACJ completion date7/1/02on schedule)
DEC approval receivedbid package finalized.
In a letter dated February 27, 2002, DEC approved the engineering drawings and
contract specifications for this project and the County proceeded to finalize the bid
package. The bid was advertised on Friday, March 1st and the pre-Bid meeting is
scheduled for Monday, March 11. Bid opening is scheduled for Wednesday, March 20th.
This project was consists of a floating net-bag
collection system in the brook which
included 3 net bags to trap floatables before entering
Onondaga Lake. The project is
estimated to take 3 months to construct and is on an extremely tight time schedule with a
milestone completion date of July 1, 2002.
Harbor Brook CSO abatement project
(ACJ completion date7/1/02Revision to be requested due to change from in-water project )
Work continues to finalize Draft Facility Plan.
Meetings were held this month between design engineers and the County to review
and discuss County comments on a preliminary draft Facility Plan and finalize the draft
of the Plan.
The County plans to have the draft Harbor Brook CSO Abatement Facilities Plan
completed in March. The County will submit the report to the State DEC and other ACJ
parties and undertake further public participation activities to receive review and
comments on the draft plan.
The purpose of the design contract is to compile a Facilities Plan, Environmental
Impact Assessment and conceptual design for Harbor Brook CSO Abatement. The
project is intended to address the 19 CSOs, which enter Onondaga Lake via Harbor
Brook.
Hiawatha Blvd. regional treatment facility
(ACJ completion date7/1/02Complete July 2001ahead of schedule)
Construction completed and operational.
Construction of all major structures of this facility is complete. The facility was
operational by July 2001.
Kirkpatrick Street pump station upgrade
(ACJ completion date7/1/02on schedule)
Construction Activities.
This month, the contractor continued installation of the new force main and storm
sewer facilities on Van Rensselaer Street. The following work was also undertaken this
month: demolition of existing bar screen and concrete at pump station and installation of
equipment pads; installation of interior conduit, lighting and electrical equipment and
other miscellaneous demolition in the existing pump station as it is upgraded.
Issues this month concerned the dewatering and sheeting for the new wet well and
coordination with construction related to Ammonia/Phosphorus removal upgrade at
Metro.
Meetings.
Progress and coordination meetings for all contracts were held regularly throughout
the month.
Additional meetings were held concerning wet well construction between design
engineerEEA, CDM/C&S and the County and between construction managers and the
contractor. Contract modifications expected which would require an increase in the
current amount authorized for this project.
Maltbie Street floatables control facility
(ACJ completion date5/1/99Complete May 1999)
Facility Fully Operational.
This is the first floatables control facility completed under the Onondaga Lake ACJ
program. The County is collecting operational data on this facility, which will be helpful
in designing and operating other net bag operations that are part of the Lake Improvement
Project. Quarterly reports are filed with DEC.
Midland conveyances and regional treatment facility
(ACJ completion datePhase II RTF5/01/04 & Phase III Conveyance5/01/07)
County takes part in DEC facilitated meetings.
County representatives continue to take part in weekly meetings facilitated by the
DEC and involving representatives of the City, ASLF, the Onondaga Nation and other
groups interested in the Midland project. Alternative technologies, sites, and visions for
the area are under discussion.
In a letter to the State DEC dated February 12, 2002, the County Executive indicated that
he had instructed the County staff to investigate and consider other alternatives,
specifically storage, to the County's current proposed plan for the regional treatment
facility. The County also agreed as a result of the DEC negotiations to evaluate the
alternative of scattered storage facilities for CSOs
in the Midland Service area. In
addition, the County agreed to meet with a consultant
(Ensource) hired by the City to
review the County's plans and alternatives for the
Midland project. Information has been
provided and meetings held.
95% Design work completed.
Design engineers have completed the 95% design documents for Phase II of the
project which includes the RTF and 1000' of conveyance
to the facility. These
documents were submitted to the County for review on November 16, 2001 and
transmitted to the State DEC on December 3, 2001. The County does not intend to
finalize the documents to 100% until the County and City are able to reach agreement
and/or the Federal Court orders transfer of the needed City property to the County or
takes other action which resolve the issue.
Notice of Intent to Sue.
In a letter dated February 1, 2002, the County notified the Mayor of the City of
Syracuse, the State and USEPA, of its intent to sue pursuant to the Clean Water Act for
violation of the general prohibitions of the national pretreatment standards.
Newell St. pilot treatment facility
(ACJ completion date7/1/02pilot disinfection project completed)
Newell St. CSO investigated under Midland project.
Abatement of the Newell St. CSO is currently being evaluated under the Midland
Phase II and III design contracts with EEA.
Onondaga Creek floatables control facility
(ACJ completion date7/1/02on schedule)
Report to be filed on Pilot.
The County is reviewing a report submitted by the design engineer on the pilot
project including information of modifications made and results of seeding events.
Following its review, it will be submitted to the State DEC.
The system continued to experience buoyancy problems during high flow conditions.
The boom and basket were removed by the County on February 28 for possible
modifications and evaluation of alternatives is taking place.
To date, over 2½ tons of floatables were collected by the system.
Sewer separation
(ACJ completion date1/1/12on schedule)
CSO 024 Sewer Separation Construction completed
One of two previous combined lines in the Water St. area was relined and now
transports wastewater only. The other combined line is now used for stormwater only.
Close out paperwork to be completed. Connections were made and plumbing modified at
two commercial buildings in the area to insure sanitary flow went to the new sewer only
line. Completion of this work has eliminated one additional CSO on Onondaga Creek.
From the start of the lake improvement program, the County has reduced the number of
untreated CSOs from 66 to 57 which includes total closure of 4 overflow points by
sewer separation.
Design of additional 12 Sewer Separation areas.
Design documents are expected shortly for the additional twelve areas proposed for
sewer separation under the ACJ. The next areas slated for construction with the
assistance of funding from the US Army Corps of Engineers are CSO areas 053 and 054
on the South side of the City.
Siphon rehabilitation
(ACJ completion date7/1/02CompleteMay 1999)
Work completed May 28, 1999 ahead of schedule.
Teall Ave. floatables control facility
(ACJ completion date7/1/02on schedule)
Construction completed.
Construction was completed on this project in December 2001 and Teall Ave. re-
opened to traffic on December 12th. The facility is
operational. Remaining site work will
be completed in the Spring. Closeout paperwork is
proceeding. Operation and
maintenance manuals, as-built drawings and punch list items being finalized.
West Street sewer separation
(ACJ completion date7/1/02CompleteDecember 1999)
This was the first sewer separation project conducted under ACJ and eliminated 3
CSOs on Onondaga Creek by converting them to stormwater discharge only.
Year 2002 monitoring program submitted to DEC
In a transmittal dated February 28, 2002, the County submitted its Proposed Ambient
Monitoring Program for Onondaga Lake and its tributaries to the State DEC for their
review and approval. Modifications made to the 2002 program were based on
recommendations from the County's previous Phase I report and input from participants
in the Monitoring Program Design and the Biological work groups which met earlier this
year.
The new program will commence March 31, 2002.
Summary of sampling program
Tributary Sampling.
Bi-weekly tributary sampling events were conducted
2/12 and 2/26. Appropriate
notification was provided to DEC and ASLF prior to sampling dates. The event on 2/12
qualified as a high flow event. A minimum of five such high flow events are required to
be sampled each year. To date, two have been completed this year.
Lake Sampling.
Winter sampling at the South Deep station was
conducted 2/21. Appropriate notification
was provided to DEC and ASLF prior to sampling date.
River Sampling.
None to report.
Fisheries Sampling.
This month, staff began reviewing and analyzing the diaries submitted by participants in
the Year 2001 Angler Diary Program.
Activities underway to prepare for this year's program including changes to diary form.
Macrovertebrate sampling.
None to report.
Macrophytes sampling.
None to report.
Other activities
The fourth quarter Ambient Monitoring Program data was sent to DEC as required on
2/12/02.
Staff attended meeting with representatives of USGS, County Planning, Corps of
Engineers about the Lake Watershed GIS project.
Preparations made for Technical Lake Advisors meeting on March 3 and 4th.
County continues to work on Partnership activities with the Corps of Engineers.
County representatives serve on the Resource, Project and Outreach Committees
and the County Executive serves on the Executive
Committee. Committees meet
monthly.
In a transmittal dated February 12, 2002, the County submitted information to the
State DEC with copies to the ACJ parties giving an
update on the County's
activities on the CSO toxicity evaluation which is a
requirement of the ACJ. The
results of the toxicity testing planned and the County's proposed plan to address
any wastestream showing toxicity effects will be submitted in a report to the State
by April 1, 2002.
None to Report.
CDM/C&S.
Contract with CDM/C&S amended for 2002 program management for
Contract amendment amount: $384,786. Executed 2/1/02.
Pomeroy Appraisal Associates.
Contract with Pomeroy Appraisal Associates amended for real estate
appraisals on Midland Ave & Clinton Street projects.
Contract amendment amount: $11,300. Executed 2/25/02
Contract with C.O. Falter Construction Co. decreased for deletion of pipe
lining for the Sewer Separation ProjectCSO 024.
Change Order amount: ($59,302.00). Executed 2/27/02.
Approval of Intermunicipal Agreement with the City of Syracuse for the
Urban Best Management Practices program.
Authorizing a permanent easement to NiMo for installation and
maintenance of electric transmission facilities at the Kirkpatrick St. Pump
Station at a cost of $1.00.
Additional authorization for the Kirkpatrick St. Pump Station Upgrade and
Force Main.
Presentation of Clinton and Harbor Brook CSO Abatement Facility Plans
State Bond Act Funds
Payments received this month from State Bond Act Funds:
-
Erie Boulevard Storage SystemRequest #7 for $12,493.89 received 1/23/02 and
Request #8 for $9,590.81 received on 2/11/02 for
aggregate total of $335,284.63.
-
Kirkpatrick Street PS & Force MainRequest #7 for $46,996.81 received 2/11/02
for aggregate total of $1,673,692.90.
-
Midland Ave Conveyances & RTFRequest #9 for $231,000.95 received on
2/11/02 for aggregate total of $1,846,525.12.
-
Metro Digital UpgradeFinal Request of $156,331.70 received on 2/11/02 for
aggregate total of $1,563,317.76.
Total received to date in State Bond Act funds$24,396,555.
Federal USEPA funds
Payments received this month from Federal USEPA Funds:
None to report.
Total received to date in Federal USEPA Funds$1,435,863.
Federal Army Corps of Engineers funds
Payments received this month from US Army Corps of Engineers:
None to report.
Total received to date from US Army Corps of Engineers Funds$643,325.75.
Loans
The following reimbursement payments were received from EFC during the
month of February:
Franklin Street FCFRequest #16 for $15,276.91 on 2/7/02 for aggregate total of
$4,589,758.93.
Kirkpatrick St. Pump Station & F/MRequest #9 for $63,203.37 on 2/19/02 for
aggregate total of $2,511,430.88.
Teall Ave FCFRequest #6 for $40,190.98 on 2/19/02 for aggregate total of
$892,700.67.
Total reimbursement monies received to date through EFC Loans for the funded ACJ
projects: $46,714,154 (short term), $7,340,809 (long term).
-
Continuation of weekly DEC facilitated meeting with
City and others on the
Midland project.
-
Quarterly ACJ All-Parties Meeting set for March 14, 2002.
-
Site Acquisition for the Midland Project-Phase IIRevised to April 1, 2002revision to be requested.
-
Submit construction documents for the Midland Project Phase IIRevised to
June 28, 2002revision to be requested.
-
Submit construction documents for Onondaga Creek FCFJanuary 29, 2002revision approved to April 30, 2002.
-
Submit Engineering Report for Clinton ProjectJune 3, 2002trevision to be
requested.
|