Progress report January 2002
Aeration system upgrade
(ACJ Completion Date7/1/02CompleteJanuary 2000)
Retrofitting a total of eight tanks was completed well ahead of the required ACJ
completion milestone. The tanks are all fully operational with the new more energy
efficient and effective fine bubble diffuser aeration
system. Lower ammonia levels
reported in lake corresponding with installation of new system.
Ammonia removal / phosphorus removal combined project
(ACJ Completion date for Ammonia Full Scale11/3/03on schedule)
(ACJ Completion date for Phosphorus Removal Stage II4/1/05ahead of schedule)
Construction progress continues.
Site preparation
work continues. About 90% of the soil in the area has now been
excavated and transported to Seneca Meadows and High Acres landfills for disposal. In
December, Seneca Meadows landfill stopped accepting the soil without amendments
added. For about 3 weeks, soils were amended with sand causing significant delays in
the work and cost increases.
Options were evaluated and new arrangements were made
for disposal without amendments. Overall, the situation resulted in an approximate 6
week schedule delay.
Additionally, massive underground structures including both concrete and timber
piles were uncovered in the excavation work which required special efforts in removal
and may have also impacted the overall schedule.
Steel sheeting was installed this month for the new secondary effluent pump station.
Dewatering (under contract 2D) is continuing and the system has lowered
groundwater levels below the bottom of the excavation for the facilities.
Pile driving (contract 3) will begin when sufficient area has been prepared. During
January, the contractor continued to receive delivery of steel H piles and provide health
and safety training and certified welding training for
employees. Pile driving is slated to
begin in February.
Pile Test, Contract 2C, is complete.
Contracts for general construction, electrical, HVAC and Plumbing (Contracts 4A, B,
C, and D) were signed this month. The pre-construction meetings for these contracts
were held on January 31, 2002.
Meetings held.
The following meetings were held this month:
-
Construction progress meeting held weekly
-
Coordination meetings with CDM/C&S, EEA and the County held on 1/7, 1/14,
1/23 and 1/28.
This is the largest and most costly single project in the Amended Consent Judgment
program and will have the greatest positive impacts on the water quality of Onondaga
Lake by removing more ammonia and phosphorus from the Metro effluent discharge.
Digester modifications/chemical storage/digester cleaning (phase iii improvements)
(ACJ completion date7/1/02Completeahead of schedule)
Close-out activities.
Project close out activities continuing.
Digital system improvements
(ACJ completion date7/1/02CompleteDecember 2001ahead of schedule)
New system in operation.
The new digital system is operational in all locations. Certificate of Substantial
completion was submitted to NYSDEC. The contractor's warranty will continue through
May 2002.
The County is continuing with training of staff to optimize the operators' use of the
system.
Odor control and residuals handling
(ACJ Completion date7/1/02CompleteDecember 2000ahead of schedule)
Project completed.
This project which was designed to reduce odors at the headworks of Metro adjacent
to Hiawatha Boulevard is completed and in operation. Positive comments have been
received from the public on a noticeable reduction in odors as a result of this project.
Phosphorus removal pilot project
(ACJ milestone date for completion of pilot4/1/07well ahead of schedule)
Final report in preparation.
The pilot was completed in December 2000. Currently work continues on evaluation
and analysis of data compiled during the pilot operation which tested a variety of
phosphorus removal technologies.
The County is more than 6 years earlier than is called for in the ACJ in carrying out
this pilot project
Clinton conveyances and regional treatment facility
(ACJ datesCommence construction of conveyances and RTFMay 1, 2003 Completion of conveyances 5/1/07 and RTF 1/1/12)
Activities continue to finalize draft Facilities Plan.
Activities this month include:
-
Continued preparation of draft Facilities Plan.
-
Coordinated and scheduled supplemental archeological Phase 1A analysis and
Phase 1B work scope for additional alternative site.
Meetings.
Meeting held with representatives of the Rescue Mission concerning possible
sites on west side of Onondaga Creek.
The goal of this project is to address the abatement
of ten CSOs between Fayette and
Adams Streets to be served by a Clinton Area Facility located near downtown Syracuse
and the Armory Square area. The contract work currently underway includes preparation
of a Facility Plan, which will evaluate alternative technologies to address the overflows
and alternative sites for any treatment facility. The contract also covers preparation of an
Environmental Impact Assessment and conceptual design.
Erie Boulevard storage system upgrade
(ACJ Completion date7/1/02on schedule)
Construction activities.
Site preparation work including installation of electrical conduit was completed at all
four of the Gate Chamber sites for this project this
month. Instrumentation panels have
been fabricated and are currently in storage. All gates have been inspected and found in
generally good condition, however some repairs will be recommended. Pre-cast buildings
will be brought to the sites to house control equipment above ground.
Construction of weirs is ongoing at the CSO manholes.
Meetings.
Two construction progress meetings were held this month as well as a separate
meeting with contractors on instrumentation and control systems.
The project involves upgrading an existing large diameter underground storm sewer
previously constructed to store combined sewage in storm situations. Following a storm
event, the combined flow would be released back to the sewer system for treatment at
Metro. The existing system has experienced operational problems with control gates and
is in need of upgrading to function effectively.
Franklin Street floatables control facility
(ACJ completion date5/1/00CompleteMay 2000)
Facility in operation.
This $4.7 m facility was completed by its ACJ milestone date of May 1, 2000 and is in
operation. This is the largest floatables facility currently planned by the County and
removes floatable debris from both the Burnet and Butternut trunk sewers to prevent their
discharge into Onondaga Creek. Quarterly reports on their operation are filed with DEC.
Harbor Brook floatables control facility
(ACJ completion date7/1/02on schedule)
Response to comments sent to DEC.
The County finalized a response to comments from DEC and forwarded them to DEC
for approval on January 25, 2002. Currently waiting for DEC approval of construction
documents so project can be bid.
Harbor Brook CSO abatement project
(ACJ completion date7/1/02Revision to be requested due to change from in-water project )
Facilities planning continues.
Design engineers continue to finalize the draft of the Harbor Brook CSO Facilities
Plan. Alternative technologies, alternative sites and potential combinations of alternatives
are under consideration and evaluation.
Draft Facility Plan to be available for public review and comment early in 2002.
Meetings have been held with neighborhood groups over the previous year to keep them
up to date on the process being followed and the plan's development.
The purpose of the design contract is to compile a Facilities Plan, Environmental
Impact Assessment and conceptual design for Harbor Brook CSO Abatement. The
project is intended to address the 19 CSOs, which enter Onondaga Lake via Harbor
Brook.
Hiawatha Blvd. regional treatment facility
(ACJ completion date7/1/02Complete July 2001ahead of schedule)
Construction completed and operational.
Construction of all major structures of this facility is complete. The facility was
operational by July 2001.
Kirkpatrick Street pump station upgrade
(ACJ completion date7/1/02on schedule)
Construction activities.
This month, the contractor completed installation of the new force main on
Kirkpatrick St. and continued installation of the new force main and storm sewer
facilities on Van Rensselaer Street. Archeological monitoring was conducted in
conjunction with this work. Also installation continued this month on the force main
yard piping, equipment pads, architectural/roofing work on pump station and installation
of interior conduit, lighting and electrical equipment at the pump station.
The Kirkpatrick St. bridge was re-opened to traffic this month.
Meetings.
Progress and coordination meetings for all contracts were held regularly throughout
the month.
Additional meetings were held concerning wet well construction between design
engineerEEA, CDM/C&S and the County to review construction management
protocols.
Maltbie Street floatables control facility
(ACJ completion date5/1/99Complete May 1999)
Facility Fully Operational.
This is the first floatables control facility completed under the Onondaga Lake ACJ
program. The County is collecting operational data on this facility, which will be helpful
in designing and operating other net bag operations that are part of the Lake Improvement
Project. Quarterly reports are filed with DEC.
Midland conveyances and regional treatment facility
(ACJ completion datePhase II RTF5/01/04 & Phase III Conveyance5/01/07)
County takes part in DEC facilitated meetings.
County representatives continue to take part in weekly meetings facilitated by the
DEC and involving representatives of the City, ASLF, the Onondaga Nation and other
groups interested in the Midland project. Alternative technologies, sites, and visions for
the area are under discussion.
95% design work completed.
Design engineers have completed the 95% design documents for Phase II of the
project which includes the RTF and 1000' of conveyance
to the facility. These
documents were submitted to the County for review on November 16, 2001 and
transmitted to the State DEC on December 3, 2001. The County does not intend to
finalize the documents to 100% until the County and City are able to reach agreement
and/or the Federal Court orders transfer of the needed City property to the County or
takes other action which resolve the issue.
Other alternatives proposed by members of the public and other groups continue to be
investigated through engineering and cost analyses by the County and their design
consultants.
Newell St. pilot treatment facility
(ACJ completion date7/1/02pilot disinfection project completed)
Newell St. CSO investigated under Midland project.
Abatement of the Newell St. CSO is currently being evaluated under the Midland
Phase II and III design contracts with EEA.
Onondaga Creek floatables control facility
(ACJ completion date7/1/02on schedule)
Report drafted on status of boom modifications and seeding events.
The design consultant, Parsons, compiled a report as requested by the County,
including information of modifications made and results of seeding events held and
submitted the information to the County for review. The system continues to experience
buoyancy problems during storm events and further modifications and alternatives are
being assessed. To date, over 2 ½ tons of floatables have been collected.
Sewer separation
(ACJ completion date1/1/12on schedule)
CSO 024 sewer separation construction completed.
One of two previous combined lines in the Water St. area was relined and now
transports wastewater only. The other combined line is now used for stormwater only.
Close out paperwork to be completed. Connections were made and plumbing modified at
two commercial buildings in the area to insure sanitary flow went to the new sewer only
line. Completion of this work has eliminated one additional CSO on Onondaga Creek.
From the start of the lake improvement program, the County has reduced the number of
untreated CSOs from 66 to 57 which includes total closure of 4 overflow points by
sewer separation.
Design of additional 12 sewer separation areas.
Following a review meeting in September, the design engineers (OB&G) are
reviewing and incorporating comments received from the
County, its construction
managers and the Corps of Engineers. Final design documents expected shortly.
Siphon rehabilitation
(ACJ completion date7/1/02CompleteMay 1999)
Work completed May 28, 1999 ahead of schedule.
Teall Ave. floatables control facility
(ACJ completion date7/1/02on schedule)
Construction completed.
Construction was completed on this project in December 2001 and Teall Ave. re-
opened to traffic on December 12th. The facility is
operational. Remaining site work will
be completed in the Spring. Closeout paperwork is
proceeding. Operation and
maintenance manuals, as-built drawings and punch list items being finalized.
West Street sewer separation
(ACJ completion date7/1/02CompleteDecember 1999)
This was the first sewer separation project conducted under ACJ and eliminated 3
CSOs on Onondaga Creek by converting them to stormwater discharge only.
Summary of sampling program
Tributary sampling.
Bi-weekly tributary sampling events conducted January 3, 15 and 29. Appropriate
notification was provided to DEC and ASLF prior to sampling dates.
Lake Sampling.
The South Deep was sampled on January 23. Appropriate notification was provided to
DEC and ASLF prior to sampling date.
River Sampling.
None to report.
Fisheries sampling.
Scale samples mounted.
Macrovertebrate sampling.
None to report.
Macrophytes sampling.
None to report.
Other activities & meetings
River modeling group meets.
Meetings were held of the River Model workgroup on
January 16 and of the
Monitoring Program Design Work group on January 17
with representatives of USEPA,
the Corps of Engineers and the Lake Technical Advisory Committee also in attendance at
both meetings.
County continues to work on Partnership activities with the Corps of Engineers.
County representatives serve on the Resource, Project and Outreach Committees
and the County Executive serves on the Executive
Committee. Committees meet
monthly.
Ammonia/Phosphorus Removal.
Contract with The Pike Company for general construction.
Contract amount: $36,983,800. Executed 1/10/02.
Contract with Edward Joy for HVAC work.
Contract amount: $2,840,000. Executed 1/18/02.
Contract with Burns Brothers for plumbing and fire protection.
Contract amount: $982,000. Executed 1/25/02.
Contract with Ridley Electric for electrical work.
Contract amount: $6,060,730. Executed 1/25/02.
None to Report.
Contract with James & Son to cover installation of a handicap ramp at the
field office for Ammonia/Phosphorus Removal project.
Change Order amount: $1,388.00. Executed 1/10/02.
Contract with Resun Leasing to cover additional materials and signs at the
field office for Ammonia/Phosphorus Removal project.
Change Order amount: $5,282.00 Executed 1/11/02.
Contract with C.O. Falter Construction Co. for additional parking and traffic
signs on the Site Preparation contract for the Ammonia/Phosphorus Removal
project.
Change Order amount: $14,314.00. Executed 1/15/02.
Contract with Ridley Electric for additional outlets, cables and connections at
the field office for Ammonia/Phosphorus Removal project.
Change Order amount: $16,595.00. Executed 1/29/02.
No action items.
Approval of an Intermunicipal Agreement with the City of Syracuse for the
Urban Best Management Practices program (BMP).
State Bond Act funds
Payments received this month from State Bond Act Funds:
-
Teall Ave. FCFRequest #5 for $246,813.95 received 1/28/02 for aggregate total of
$595,895.26.
-
Harbor Brook FCFRequest #3 for $44,849.17 received 1/28/02 for aggregate total
of $155,650.70.
Total received to date in State Bond Act funds$23,940,500.
Federal USEPA funds
Payments received this month from Federal USEPA Funds:
None to report.
Total received to date in Federal USEPA Funds$1,435,863.
Federal Army Corps of Engineers funds
Payments received this month from US Army Corps of Engineers:
Sewer SeparationRequest #1 for $643,325.75 on 1/10/02 for aggregate total of
$643,325.75.
Total received to date from US Army Corps of Engineers Funds$643,325.75.
Loans
The following reimbursement payments were received from EFC during the
month of January:
Ammonia/Phosphorus Removal
Request #12 for $338,513.82 on 1/4/02, Request
#13 for $5,515,390.38 on 1/18/02, and Request #14 for $100,163.85 on 1/31/02 for
aggregate total of $20,935,396.20.
Erie Boulevard Storage System
Request #1 for $100,049.74 on 1/18/02 and
Request #2 for $334,462.29 on 1/25/02 for aggregate total of $434,512.03.
Franklin Street FCF
Request #14 for $9,973.20 on 1/4/02 and Request #15 for
$21,077.23 on 1/18/02 for aggregate total of $4,574,482.02.
Kirkpatrick St. Pump Station & F/M
Request #6 for $61,433.74 on 1/4/02,
Request #7 for $374,420.47 on 1/18/02 and Request #8 for $592,852.97 on 1/25/02
for aggregate total of $2,448,227.51.
Teall Ave FCF
Request #4 for $322,632.62 on 1/4/02 and Request #5 for
$211,967.17 on 1/18/02 for aggregate total of $852,509.69.
Total reimbursement monies received to date through EFC Loans for the funded ACJ
projects: $46,595,483 (short term), $7,340,809 (long term).
-
Continuation of weekly DEC facilitated meeting with
City and others on the
Midland project.
-
Quarterly ACJ All-Parties Meeting set for March 14, 2002.
-
Site Acquisition for the Midland Project-Phase IIRevised to April 1, 2002.
-
Submit construction documents for the Midland Project Phase IIRevised to
June 28, 2002.
-
Submit construction documents for Onondaga Creek FCFJanuary 29, 2002revision requested to April 30, 2002.
-
Submit Engineering Report for Clinton ProjectJune 3, 2002.
|