July 2004 progress

Ammonia and phosphorus treatment

Roofs of the Chemical, BAF, and HRFS buildings, looking northwest
Roofs of the Chemical, BAF, and HRFS buildings, looking northwest

PVC piping being installed for the neat polymer and mixing-aging polymer tanks
PVC piping being installed for the neat polymer and mixing-aging polymer tanks

Lamella tubes installed in the HRFS settling tanks to increase clarification capacity
Lamella tubes installed in the HRFS settling tanks to increase clarification capacity

Ferric chloride tanks and equipment tanks
Ferric chloride tanks and equipment tanks

Operation and control

 
SCADA room with cable tray installed under flooring—for control of processes   Installing floor supports in the control room

Stairs leading to the mechanical room in the Operations Center
Stairs leading to the mechanical room in the Operations Center

Site work

Southeast corner of the construction area, now graded to the sub-base elevation
Southeast corner of the construction area, now graded to the sub-base elevation

Initial construction of roads and parking lot, looking northeast from the UV building
Initial construction of roads and parking lot, looking northeast from the UV building

Installing filter fabric for new roads on the southwest corner of the BAF
Installing filter fabric for new roads on the southwest corner of the BAF


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection