Metro construction: July 2003

Ammonia removal facilities (BAF)

 
Setting precast concrete columns in the southeast BAF gallery   Swinging precast concrete beams to the southeast BAF gallery


 
Setting precast concrete planks over the southeast BAF gallery
Setting precast concrete planks over the southeast BAF gallery


 
 
Planking in place atop the southeast BAF gallery   Looking southeast at the roof over the BAF


 
Forming the North BAF drop boxes
Forming the North BAF drop boxes


 
Formed for the South BAF wedge wall
Formed for the South BAF wedge wall


 
Pouring concrete for the influent channel of the North BAF
Pouring concrete for the influent channel of the North BAF


 
Looking northwest at the BAF complex at the end of July 2003
Looking northwest at the BAF complex at the end of July 2003


 
 
Installing roof insulation at the BAF utility building   Power feeds into the BAF utility building

Phosphorus removal facilities (HRFS)

Working on the concrete slab for the HRFS maturation tank #4
Working on the concrete slab for the HRFS maturation tank #4


 
Concrete slab for the deck of the HRFS north gallery
Concrete slab for the deck of the HRFS north gallery


 
Building the concrete forms for the effluent channel of the HRFS
Building the concrete forms for the effluent channel of the HRFS


 
Installing scaffolding for the slab on deck of the HRFS North Gallery
Installing scaffolding for the slab on deck of the HRFS North Gallery


 
Pouring the north part of the HRFS influent channel
Pouring the north part of the HRFS influent channel


 
Pouring the upper lift of HRFS tank #1
Pouring the upper lift of HRFS tank #1


 
Decking over the HRFS influent channel
Decking over the HRFS influent channel


 
Installing reinforcing steel bars in the influent channel
Installing reinforcing steel bars in the influent channel


 
14-inch sludge line for the HRFS
14-inch sludge line for the HRFS


 
Looking northeast toward the HRFS complex
Looking northeast toward the HRFS complex

Ultraviolet disinfection

CMU work along the south wall of the UV facility
CMU work along the south wall of the UV facility

Secondary effluent pump station (SEPS)

 
Flying in one of the 500-hp pump at the SEPS   The last 500-hp pump is set in place


 
 
Construction of the south wall of the pump room   Temporary bypass piping for the SEPS

Additional projects

Using a plate tamper for backfilling the conduit crossings by the secondary clarifiers
Using a plate tamper for backfilling the conduit crossings by the secondary clarifiers


 
New switch gear added to the substation
New switch gear added to the substation


 
Excavation begins for the new operations building
Excavation begins for the new operations building


 
Forming the grade beams at the operations building
Forming the grade beams at the operations building


 


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection