Highlights in April 2003

Aerial view of construction site for Secondary Effluent Pump Station, Apr 6
Aerial view of construction site for Secondary Effluent Pump Station, Apr 6

Aerial view of construction for new Metro treatment processes: ammonia removal (bottom), phosphorus removal (middle), and UV disinfection (top). Hiawatha Blvd. is at top. Apr 6
Aerial view of construction for new Metro treatment processes: ammonia removal (bottom), phosphorus removal (middle), and UV disinfection (top). Hiawatha Blvd. is at top. Apr 6

 
  Conduits installed in cross gallery, Apr 18

 
Motor control units for the BAF blowers, Apr 18   Mechanical work in the south BAF, Apr 18

Concrete block work for the Secondary Effluent Pump Station, Apr 18
Concrete block work for the Secondary Effluent Pump Station, Apr 18

Workers form the walls for the South Gallery BAF, Apr 18
Workers form the walls for the South Gallery BAF, Apr 18

 
Penetrations into the cell for the stoplogs, Apr 18   Metro's electrical substation with added switch gear, Apr 24

Influent wall of the HRFS gallery (phosphorus removal), Apr 24
Influent wall of the HRFS gallery (phosphorus removal), Apr 24

Pouring concrete for tank #3 of the HRFS facilities, Apr 24
Pouring concrete for tank #3 of the HRFS facilities, Apr 24

Concrete poured for the upper walls of the HRFS tank #3, Apr 24
Concrete poured for the upper walls of the HRFS tank #3, Apr 24


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection