General improvements
|
|
Metropolitan Syracuse Wastewater Treatment Plant, June 2005
|
Several diverse projects were undertaken to enhance
the ability of the Metropolitan Syracuse Wastewater Treatment Plant to treat wastewater. They
included the following:
-
Insulation of the roofs of digesters #1 and #3
-
Replacement of three waste-gas burners
-
Ventilation improvements in the digester control house
-
Installation of new instrumentation
-
Replacement of a sluice gate
-
Installation of new piping and overflow weirs in the diversion structure.
All of these projects are complete. They are helping
to achieve better wastewater treatment at the Metropolitan Syracuse Wastewater Treatment Plant
and improved water quality in Onondaga Lake.
|