1925
|
City constructs primary sewage treatment plant
|
|
1954
|
County takes over City sewage treatment plant
|
|
1959
|
County upgrades and expands sewage treatment plant
|
|
1970
|
County completes construction of Kirkpatrick Street Pump Station
|
|
1971
|
County repairs main interceptor sewer (MIS) and Harbor Brook interceptor sewer (HBIS), and trunk sewers on Oneida Street, Marcellus Street, Evans Street
|
|
1971
|
City Common Council clarifies ownership and maintenance responsibility for the Main Interceptor Sewer
|
|
1972
|
County repairs MIS and HBIS, and trunk sewers on Midland Avenue, Maltbie Street, Newell Street
|
|
1973
|
County repairs MIS and HBIS, and trunk sewers on Hiawatha Boulevard, South Avenue, Gifford Street, Midland Avenue, South Avenue & Onondaga Street, Harriman Street,
|
|
1974
|
County repairs MIS and HBIS, and trunk sewers on Tallman Street, Onondaga Avenue, State Fair Boulevard, Hoefler Street,
|
|
1975
|
County repairs MIS and HBIS, and trunk sewers on Elmhurst Street, West Fayette Street, Tallman Street, Ballantyne Road, Richmond Avenue
|
|
1976
|
County repairs MIS and HBIS, and trunk sewers on West Jefferson Street, Colvin Street, Rescue Mission
|
|
1977
|
County HBIS repairs
|
|
1978
|
County MIS/trunk sewer repairs Elmhurst
|
|
1979
|
County MIS/trunk sewer repairs Harrison Street, Tallman Street
|
|
1979
|
County upgrades and expands sewage treatment plant
|
|
1979
|
County produces first comprehensive combined sewer overflow facilities plan
|
|
1979
|
City transfers certain combined trunk sewers
|
|
1982
|
City transfers certain combined trunk sewers
|
|
1985
|
County completes $10 million ($18 million in 2006 dollars) best management practices physical improvements to trunk sewers and CSO regulating structures, eliminating forty CSOs and reducing volume of CSO by 90% (started 1980)
|
|
1987
|
Atlantic States Legal Foundation sues County over alleged Clean Water Act violations
|
|
1991
|
County completes CSO comprehensive facilities plan
|
|
1993
|
County upgrades sewage treatment plant
|
|
1996
|
County completes draft Municipal Compliance Plan and draft environmental impact statement
|
|
1997
|
County upgrades sewage treatment plant
|
|
1998
|
Start of ACJ
|
|
Source: Onondaga County website, accessed Nov 28, 2007.
|