Responses: Sept 14-15, 2005 public information meetings
Information from Harbor Brook public hearing:
Responses: Public hearing, Dec 6, 2005
Transcript: Public hearing, Dec 6, 2005
Responsiveness Summary For Harbor Brook CSO Abatement Facilities Plan
Questions and Responses from Public Informational Meetings held Sept. 14 and Sept. 15, 2005 & written comments received
Sept 14 meeting at Rosamond Gifford Zoo
Meeting
Moderator: Matt Mulcahey, UPN 6 News
Those present representing the County Dept of Water Environment Protection:
Dick Elander, Commissioner
Stephen Martin, Sewer Maintenance Engineer
Consultants John Clare (project manager)
and Dan Davis (Brown and Caldwell)
Among those also present were Sue Miller, OCWEP
County Legislators Ed Ryan, Brendan Whalen, and Jim Rhinehardt
Steve Eidt from NYSDEC
Vince Esposito from City DPW
Representatives of CDM/C&S: Bob
Albright, Bob Kukenberger
Representatives from EEA: Bruce Munn
About ten interested citizens including two
students from the Newhouse School of Journalism
doing a story for class.
Sept 15 meeting at Pensabene's Casa Grande Banquet Hall on State Fair Blvd.
Moderator: Matt Mulcahey, UPN 6 News
Those present representing the County Dept of
Water Environment Protection:
Stephen Martin, Sewer
Maintenance Engineer and consultants John Clare,
(project manager) and Dan Davis, Brown and Caldwell.
Among those also present were Sue Miller, OCWEP
County Legislator Ed Ryan Steve Eidt, NYSDEC
Vince Esposito from City DPW Representative of EEA:
Bruce Munn Representatives of CDM/C&S Bob Palladine and Mark
Gorthey About thirteen interested citizens.
Total present at each meeting about 24-26 people.
Following a brief welcome and introductions of those
County representatives in attendance, presentations on
the project were given by John Clare, Project Manager.
During and following the presentations, questions and
comments were received from the public.
The following is a composite of the questions asked at
both meetings and the responses given. Additional
information to the responses given at the meetings is
printed in italic.
1. What is the time frame for this project?
Design estimated to start in 2005 and conclude in
2007. Construction to begin 2007 and conclude in
2010.
2. How were these meetings publicized?
Direct mailing by the County to over 700 individuals
who reside or own property in the immediate area of
the projects plus churches, schools, businesses and
organizations in the area on the west side of the
city. Plus advertisements in the local Scotsmen Press
Pennysaver and the Syracuse Post Standard. News Story
in Post Standard. News Release faxed to all major
news outlets in area.
3. How big is the footprint of the building proposed for the regional treatment and storage facility. What will it look like? Is any landscaping planned?
The dimensions for the above-ground portion of the
building are estimated at 120 ft x 140 ft and 20 ft high. It
will be a brick and masonry building with no open
tanks. Landscaping will definitely be done as we have
at other project sites. The County has and will
continue to be guided by the principle to make the
appearance of each area where our projects are built
better than they were before our project. Landscaping
in and around the buildings constructed is a major
part of these improvements to enhance the areas.
4. The following possible mitigation measures and/or amenities were suggested by those present:
-
Consider helping to fund improvements to Frazier
Pool that is near the interceptor pipeline and brook
and is in major disrepair. Improvements to the pool
would be great for the neighborhood. (Bob Oberst)
-
Many of the constituents in Lower Basin area are
interested in having the sidewalks and tree plantings
finished along Genesee Street, a continuation of the
"automobile row" improvements including around the
corner in front of homes on State Fair Boulevard so
they could get some benefits as they may be directly
across the street from the new facility. I would like
to suggest this as a mitigation measure under this
project. (Ed Ryan)
-
Constituents in the Upper Basin area indicated the
need and interest in sidewalks being extended along
Grand Avenue along with curbs and landscaping. (Ryan)
-
Landscaping in front of the treatment facility and
shrubbery and trees along State Fair Boulevard in
front of the facility were suggested. (nearby
resident)
-
Additional suggestions for neighborhood improvements
that have been discussed at local TNT Area 2-Westside
meetings in recent years related to this project
include the installation of sidewalks along Grand Avenue
to Velasko Roadgreatly needed including along the
detention basin. Also TNT Area 2-Westside group was
interested in possible purchase by the County and
removal of the two houses and former Molly's Place bar
on the corner of Grand and Delaware for possible
playfields for Delaware School. Does City or State
own right-of-way along basin area on Grand Avenue? The
speaker noted that he realized that plowing of the
sidewalk might be a concern as to who would plow and
the proximity of the street. He suggested that the
new sidewalk should be back from the curb.(Bob Oberst)
-
I would like to suggest that the County consider
grooming the area behind the wall along Grand Ave and
Wilbur through which Harbor Brook flows. (Ed
McLaughlin)
The State owns the right-of-way along Grand Avenue near
the detention basin. Plowing and placement of such a
sidewalk would need to be investigated further. We
are familiar with the need for sidewalks in this area
and the current situation with walkers in the street.
Also we are familiar with the existing "automobile
row" improvements and can look into current and future
plans and what areas are not currently including in
those improvements.
County staff have been discussing possible mitigation measures and amenities for a number of year with the Westside TNT and local residents. We appreciate receiving these types of suggestions this
evening and will keep this list together for further research into the suggestions and evaluation of their relationship with the construction project and their costs. Any proposed mitigation plans
would require County Legislature approval for funding.
The County is committed to leaving areas better both in terms of an improved environment and in appearance than before we began our construction, and we have done this on other completed projects.
For example, during the County's West Street sewer separation project, the County funded restoration improvements in coordination with the "automobile row" improvements along Genesee Street near
Durston's and landscaping and restoration improvements carried out with construction of the Franklin Street floatables control facilities greatly enhanced that area that now serves as a "gateway" to
the city.
5. How long will construction take for installation of
the pipes, and what sizes will be installed? The County
should supply a specific timeframe to residents in the
area detailing how long disruption will be on their
streets. (Rich Puchalski)
It will take multiple months to install all of the
pipelines. We will provide a time estimate based on
previous projects. And we will supply residents with
specific timeframes for construction on their streets
as we get closer to the actual start of construction.
Based on our sewer separation projects to date we estimate about 2-5 days for installation of pipelines in front of individual house lots dependent on the length of their street frontage, utilities
impacted, and the size of pipe installed. Later on in each project, street restoration including final paving will disrupt streets for about 3 days on a block-by-block basis. The size of pipes
planned at this time include: Hartson St. (from Holden to Herriman) - 48" pipe Hoefler St. (from Harbor Brook to Hartson) - 18" pipe Lydell St. (from Harbor Brook to Hartson) - 18" pipe
Herriman St. (from Hartson to Grand Ave.) - 54" pipe Park Ave. (from Sackett to W. Genesee) - 48" pipe State Fair Blvd. (from W. Genesee St. to Harbor Brook) - 48" pipe
Residents will be notified on specifics for their streets as construction gets closer. This project is just at the design phase right now.
6. How often and what will the treatment facilities discharge into the brook?
The majority of times the facilities will simply store
all of the combined sewage and stormwater and then
following the rainfall, the flow will go to the
Metropolitan Treatment Plant for treatment via the
Harbor Brook interceptor sewer line. It is estimated
that the facilities will exceed their storage capacity
and actually discharge treatment effluent to the brook
about 20-30 times per year. Currently the combined
sewer overflows along Harbor Brook discharge untreated
into the brook about 50-60 times per year for a total
volume of 139 million gallons per year. 47% of this
current 139 million gallons of overflow, including the more concentrated
"first flush" of combined sewage that comes at the
front end of storms, will be captured by the two
treatment and storage facilities and sent to Metro for
treatment. Another 52% will be treated at the
regional treatment facilities and discharged after
treatment into the brook. About 1% will be treated
and discharged to the brook through the proposed five
floatables control facilities.
7. Concerns were indicated about possible smells, the looks of the facilities and other options that wouldn't have to use chemicalslike complete storage. Concerns raised about impacts of chlorine used in
disinfection.
During the facilities planning process, the County
researched various technologies including complete
storage and assessed the associated costs,
construction impacts, and environmental impacts. Based
on that thorough and multi-year process, the County
has recommended the alternative described in the
facilities plan that includes two regional treatment
and storage facilities. Both facilities will be
entirely enclosed, and odor control systems will be installed.
As mentioned earlier, for the majority of times
combined flow is received in the treatment facility,
it will simply be stored until the storms pass. If
flow exceeds the storage capacity of the facility, the
effluent will have floatables removed and then be
disinfected by using chlorine similar to household
disinfectants and chlorine bleach to kill bacteria in
the sewage. Following chlorination and before
discharge to the Brook, the effluent will be treated
to remove the chlorine. This
chlorination-dechlorination process is standard
practice for abating combined sewer overflows
throughout the country and is approved by the NYS
Department of Environmental Conservation and the U.S.
Environmental Protection Agency. The major concern
about the impacts of combined sewer overflows on the
tributary streams and Onondaga Lake are floatables and
bacteria. These facilities are intended to treat
those two issues and, therefore, minimize their negative
impacts on the tributaries and the lake.
8. Can the County improve the catch basins that back up stormwater into the streets now during heavy rains? (Louise Pascuzzi)
Yes, this will be one of the benefits of this project.
With the installation of new sewer lines to handle
the current excess flow, this should help alleviate
current back ups in streets. Vince Esposito from City
of Syracuse DPW also noted that a spring of water
comes down into the Upper Basin area and from time to
time that cause additional plugging in the catch
basins at DePalma Avenue. He recommended that residents
call the City Line at 448-2489 if they see a back up
there, and the city DPW will come out and open up the
line.
9. Concerns were raised about noise during construction and what the hours of construction would be? They mentioned that current Midland construction starts at 7:00 a.m. and made the suggestion that
construction hours start at 8:00 a.m. instead on Harbor Brook. (Pascuzzi and Puchalski)
Noise is an issue during construction, and the County
does limit the hours of construction by designating
work hours in contract requirements. The Midland
contract work hours are 7:00 a.m. to 6:00 p.m. Hours
may be extended by agreement with County to meet
construction completion schedules. Hours of
construction need to balance and consider optimum use
of daylight hours, completion schedule needs, and
consideration of local residents.
10. What is the status of the wetlands project proposed for a CSO in the retention basin? (Puchalski)
This project is a proposed project by staff of the
SUNY College of Environmental Science and Forestry and
Atlantic States Legal Foundation. It is not a County
project.
The County is aware of the project and has been in
communication with representatives of SUNY-ESF and
Atlantic States Legal Foundation over a number of
years on the project. It is intended to be a pilot
project on the use of wetlands for treatment of
combined sewer overflows and could be located in the
County's retention basin.
Steve Eidt from DEC reported that currently ASLF and
ESF are attempting to finalize funding from EPA and
other sources for the design and implementation of the
project. Prof. Richard Smarden is the lead on this
project, and County representatives said additional
information on the project's status should be obtained
from Prof. Smarden.
11. How many vortex separators are planned for the regional treatment and storage facility to be located at Amy and Grand?
Two.
12. Will Amy Street stay open?
The County does not intend to permanently close Amy
Street. During construction, the county may need some
short time periods of closure to through traffic while
allowing local traffic only.
It should be noted that this is a very low trafficked street.
13. How much money is available for use through the County for neighborhood improvements?
We do not know how much money the County will have
available for such mitigation measures, but we are
continuing to look for suggestions and that is one of
the purposes of tonight's meeting. Ultimately the
decision on funding for mitigation/amenities will be
made by the County Legislature following a proposal
from WEP and the County Executive.
14. What is the projected cost of the Harbor Brook CSO Abatement Project, and where will funding come from?
The project is currently estimated at $55 million.
The County will attempt to get as much federal and
state aid as possible for the project; but none is in
place right now. Low interest loans from the State
will also assist in financing the project. At this
time, the project costs will mainly be covered by
Consolidated Sewer District users. The County intends
to cover costs for this and other projects with
controlled and gradual increases in the sewer user
charges.
15. Did you look into sewer separation for any of the smaller basins? (Aggie Lane)
Yes, and this alternative is covered in facilities
plan. None were found to be cost effective.
16. Indicated concerns about the functionality of floatables control facilities.(A. Lane)
Under the Harbor Brook recommended facilities plan,
the County is proposing the installation of five
floatables control units similar to the mechanical
screen unit used in the Teall Brook project. This
unit has been working very well since its installation
in December 2001. The Harbor Brook FCF projects will
not use net bags as used at Franklin project and the
interim in-stream project operating currently near the
mouth of Harbor Brook.
17. Indicated concerns about sounds/noises emanating from the facility on State Fair after it is constructed and operational? (nearby neighbors on State Fair)
Facility should be very quiet as all of the operation
will be enclosed in a building. The loudest noise in
the building will be from the ventilation system and
pumps which will have noise controls to dampen sounds.
The facility will only operate during wet weather
events. This is not a sewage treatment plant that
operates on a 24/7 basis for 365 days per year.
During an average year, it is projected that the
facilities will only operate about 50-60 times per
year.
18. Will this project eliminate the "popping" manhole on State Fair Boulevard near this site and basement flooding that sometimes occurs?
Yes. By diverting water in the combined sewers for
capture and treatment at the treatment and storage
facility, this will reduce the backups in the system
and the manhole should not "pop."
19. Homeowner along Waite Avenue concerned about what construction impacts will be in his area. (Frank Esposito)
During dry weather, the interceptor sewer behind the
houses on Waite Avenue transports the wastewater flow to
the Metropolitan Treatment Plant on Hiawatha
Boulevard. The new pipe to be constructed will accept
combined sewer and stormwater flow and transport it to
the new overflow control facility on State Fair.
Under the revised conveyance route, the new conveyance line will be installed in Park Avenue and State Fair Boulevard, not behind houses on Waite or on Eureka.
20. Suggestion received to put the facility further north on State Fair Boulevard nearer to the Napa Parts Store end of the property which has more industrial buildings rather than nearer to the
southern end of that section of State Fair Boulevard where there were some homes. (area resident)
J. Clare indicated he uncertain why the facility was
shown at the southern end of the property and would
check into the matter. Final determination of
specifically where on the property the facility would
go will be made after the archeological and
geotechnical investigations of the property are
completed.
The possibility of locating the facility further north on the site will be looked into by the County. Since the meeting, the archeological and soil testing were scheduled and in response to this
question, the tests will cover both the northern and southern section of this vacant property on State Fair Boulevard.
21. Legislator Ed Ryan pointed out that the County
Department of Water Environment Protection was out
front on this Harbor Brook project for quite some time
now. He noted the County responded to the lack of
practice ballfields for area schools in the Upper
Basin.The County built two fields in the detention
basin at the corner of Velasko and Onondaga that are
worth ¼-million dollars and are now available for
local school use. He pointed out that this was
evidence of their stated intention to make areas
better than when they started.
One letter was received with written comments. That
letter dated October 17, 2005 was submitted by Richard
Puchalski, Executive Director of Syracuse United
Neighbors and is summarized below with
responses:
Summary of position:
-
County should consider alternatives like storage.
Response: County did consider alternatives including
storage (See Questions # 7 & 15 and responses)
-
County should landscape the 20' high facility.
Response: The County is committed to landscaping the
facility. (See Question # 3 and response )
-
SUN objects to any plan to take private property
for the Upper Basin facility and pipe.
Response: As stated at the September 14th informational
meeting, the County's plans for the Upper Basin
facility and pipe do not include any plans at this
time for taking private property containing occupied
homes for this project. All property identified for
purchase for this project is currently vacant land.
Additional Comments:
-
Information on the proposed wetland project should
be part of this facility plan. SUN "has been on
record supporting this wetland project. Originally
the plan was proposed by Atlantic States and now we
have been told it is a SUNY-ESF project. We expect to
be informed."
Response: The County has been aware of the proposed
wetlands project for a number of years starting when
it was first brought to our attention by
representatives from Atlantic States and SUNY-ESF and
was proposed to be located behind the "wall" in the
State property along the brook near Grand Avenue. The
County suggested a new possible location for the
wetlands pilot project in the County-owned detention
basin that included two CSOs that discharged into the
brook. Other meetings were held and discussions
continued on the proposal, and the County has supported
the pilot project in written documentation as
requested by SUNY-ESF as they applied for grant
monies. The proposal is not part of the County's
Facility Plan and it is not a county project.
However, the County has and continues to support a
pilot program, and if funding is received and design
completed, the County could work with the sponsors to
enable the pilot project to be carried out on CSO 018
in the detention basin.
-
SUN wants to be informed of the timetable and length
of time work will be done on the streets impacted in
the Skunk City area, and SUN offers to host a community
meeting before actual construction in that area
begins.
Response: Residents will be kept informed along all of
the streets that will be impacted by installation of
new pipes in the streets as part of this project. A
schedule for work and length of time that work will
take to complete along each stretch of street will be
provided. We appreciate SUN's offer to host a
community meeting prior to construction beginning in
the area on the project. We can add that based on
sewer separation work accomplished in the past few
years, it is estimated to take about 2-5 days to
complete installation of 20-35 feet of new pipe
dependent on pipe size and necessary utility
relocations. (See Question #5 and response)
-
Noise, dust and traffic should be limited during
construction. Flyers should be distributed to
neighbors re when the project will impact access to
their homes and supply them with a number to call with
questions or complaints. Request 24-hour notice when
access to home will be limited. Do not allow
construction vehicles to emit noise until after 8 a.m.
Response: The County will do our best through contract
requirements with construction contractors to limit
the noise, dust and traffic impacts during
construction of the facilities and installation of the
conveyance pipes. Contact name and number will be
supplied residents and 24-hour notice supplied to
homes where access will be limited or power
temporarily affected. In addition, the County will
work with the City School District on school bus
access needs for children in the area.
-
Since streets area being torn up.property owners
should be informed in writing if they have lead water
service to their homes and offered the portion to pay
to convert these pipes to non-lead. Lead water lines
from curb to main line must be replaced at City
expense.
Response: As part of the City-County Intermunicipal
Agreement on this project, the County will replace all
lead water lines found from the curb to the mainas
we have on all other Lake Improvement Projects in the
city streets.
-
SUN is requesting the following neighborhood
improvements as part of this project on streets
impacted by construction: new sidewalks, tree
plantings along the right-of-way, and building streets
with curbs on the unimproved streets where the new
pipe would be installed.
Response: These requests will be compiled with the
other requests for mitigation and amenitiescost
estimates compiled and then a proposed plan presented
to the County Executive and the County Legislature for
their consideration. Thank you for your suggestions.
|