Midland: November 2004
|
|
Partially removing Centro's storage barn to permit installation of sheeting for construction
|
|
|
Creek bank seeded for erosion control
|
|
|
Installing steel sheeting in the ground in preparation for replacing the 48-inch Main Interceptor Sewer (MIS)
|
|
|
54-inch HDPE piping arrives. It will replace the 48-inch MIS.
|
|
|
Relocating the 8-inch fire protection water line
|
Photos by Joe Lorah
|