|
|
Construction worker at the RTF
|
Midland overflow abatement project
See construction photos.
In its efforts to improve water quality in both Onondaga
Lake and Onondaga Creek, Onondaga County is building the Midland
Regional Treatment Facility (RTF) and 2 miles of
conveyance piping.
Between Newell and Tallman streets, twenty-one
overflow points discharge combined sewage to Onondaga Creek
fifty to sixty times per year. The overflows create
human health risks because they contain bacteria and
degrade water quality, and they are the source of
odors to the area.
Nine of these CSOs will be connected to the Midland
overflow abatement facilities now under construction.
The remaining twelve are being eliminated through
sewer separation projects.
Full information about the project is available in the facility plans:
Facility plan & Plan amendment
|
|
Adding the brick façade to the RTF
|
The specialty metals subcontractor worked on installing walkways and stairs in
the vortex separator room. The plumbing contractor continued to install roof
drains and leaders in the RTF. The HVAC contractor continued to install supply
and return water lines for the unit heaters in the RTF. The electrical
contractor continued to install switchgear and conduit in the RTF, lighting in
the underground storage tank, and conduit and panel
boxes in the underground
disinfection tank.
Total amount of concrete poured to date is 19,885 cubic yards of an
estimated 23,000 yards for the completed facility. Concrete work this month
included the chemical room floor, tank retaining
walls, and equipment pads.
For the exterior walls and the interior walls, 100% of the concrete masonry
units (CMU) have been installed. Work has begun on the
exterior brick.
Installation of storm drain piping around the site continued this month.
Installation of sections of 144-inch pipe was completed.
Geotechnical monitoring instrumentation reports continue to be compiled and
submitted to the County and consultants for review.
Work anticipated for May 2007 includes:
-
Continued backfilling of the 144-inch pipe.
-
Installation of roofing system.
-
Continued placement of exterior bricks.
-
Continued installation of switchgear and conduit and panel boxes where required.
-
Continued installation of supply and return lines, unit heaters, and HVAC ductwork in the RTF.
-
The plumbing contractor will continue installation of drains and roof leaders in the RTF.
For Midland Phase III this month, bids were advertised
on April 23 and will be opened June 6.
Onondaga County's will meet or exceed federal and state
water quality requirements to reduce CSOs and make
improvements to the area affected by construction. The
RTF project will significantly improve water quality
of Onondaga Creek and Onondaga Lake. It will reduce human health
risks associated with discharge of untreated sewage
into the Creek and Lake and eliminate odors caused by
discharging overflows.
|
|
Proposed Midland RTF, as seen from Blaine Street
|
Existing collector and trunk sewers in the Midland
service area can store 74% of the average annual wet
weather flow. The piping now under construction will
store another 18%. All of this stored flow will be
conveyed to the Metropolitan Syracuse Wastewater Treatment Plant (Metro) for treatment and
disposal. The remaining 8% (about 77 million gallons
annually) will be handled by the RTF.
This 8% of the total flow will be treated at the RTF
by swirl concentrators (vortex units), disinfected,
dechlorinated, and discharge to Onondaga Creek.
Besides the vortex units, the RTF will include a
pumping station, odor control and ventilation
equipment, electrical and control equipment, chemical
storage (liquid sodium hypochlorite and liquid sodium
bisulfite), and a small office. The aboveground
portion of the RTF will be 24,000 square feet and 24
feet high.
The RTF is
not
a sewage treatment plant. Sewage treatment plants
typically operate 24 hours per day everyday and
usually include a biological treatment process.The RTF
will operate
infrequently.
It will fully operate and discharge only when the 7.2
million gallons of storageincluded in the large
diameter conveyance pipes, underground storage tank,
and RTF influent wet wellis exceeded. Even then, a
treated discharge to Onondaga Creek will only occur when the
total 8.45 million gallonsincluding inherent storage
in the vortex units and disinfection tankis exceeded,
approximately nine times per year.
Onondaga County has been working to reduce combined sewer
overflows in the Midland area for several years:
1969
Ownership of Midland Avenue and Elmhurst combined
trunk sewers transferred from the City of Syracuse to
Onondaga County.
1978
Tallman Street and Bellevue Avenue trunk sewers
transferred from City to County.
Mid-1980s
Onondaga County undertook a series of best management
practices to improve the combined trunk sewer system
and significantly reduced the incidence and volume of
combined sewer overflows. Through the County's
efforts, a number of CSOs were closed, and the volume
of sewer overflows released to Onondaga Creek and Onondaga Lake
was reduced by 90%.
1991
Onondaga County began plans to address and abate remaining
CSOs with a 1991 facilities plan.
1996
Proposed municipal compliance plan (MCP) specified a
CSO abatement project at the Blaine-Oxford streets
site.
1998
The Amended Consent Judgment signed by the County, State, and Atlantic
States Legal Foundation includes a regional treatment
facility with vortex separation at the Blaine-Oxford
streets site for the Midland sewer area. Design and
construction of the project had required milestone
dates for the County to meet.
1998-2000
As part of the planning and environmental review for
the Midland project, Onondaga County re-evaluated potential
locations for the Midland facilities and the
technologies to be employed.
2000
Phase I: A 900-ft conveyance pipeline was installed to
bring the Tallman Street CSO to the RTF site.
Fall 2000
Construction documents for the Midland RTF and related
Phase II conveyances submitted to NYSDEC
Fall 2001
City of Syracuse Common Council voted to refuse to
sell necessary City-owned and -controlled land to the
County for the project.
Nov 2001-Aug 2002
Onondaga County, independently and in cooperation with a
mediation efforts of NYSDEC, identified and evaluated
further alternatives to the proposed RTF.
Aug 2002
Onondaga County adopted a modified project plan reducing the
number of vortex units from four to two and added 2.5
million gallons of underground storagethus increasing
the amount of CSO captured and reducing the amount to
be processed through the RTF and discharged to Onondaga
Creek after treatment.
Oct 2002
Onondaga County sponsors workshop on
disinfection of wastewater with chlorine to
demonstrate the effectiveness and benefits of this
technology. Speakers included USEPA, NYSDEC, and
Syracuse Research Corp.
Nov 2002
U.S. District Court rules that Onondaga County may condemn
property owned by the City that is needed for the Midland
project. Engineers begin preliminary design for the
County's preferred option.
Jan-Feb 2003
Revised and updated facilities
plan submitted to NYSDEC for the Midland Avenue
RTF and conveyances project. Onondaga County Legislature
authorized acquisition of property for construction,
operation, and maintenance of Phase II Midland Avenue
RTF and conveyances.
Mar 2003
Onondaga the County further modified its plan by locating
most of the RTF and the underground disinfection tank
on CENTRO property adjacent to the bus garage.
May-Jun 2003
Federal district court judge supports Onondaga County's
right to use eminent domain with just compensation to
acquire a City-owned property. City files appeal.
County proceeds to purchase needed private properties
and assists property owners in finding new homes and
provides compensation for moving.
Jun 2003
Amended facility plan and
revised engineering design report forwarded to NYSDEC
for review.
Nov 2003
NYSDEC approves updated facilities plan and engineering design report.
Feb 2004
Contract for building demolition put out for bid.
Bids advertised for construction of Phase II Midland
RTF and conveyances.
May 2004
Demolition contract awarded. Site demolition begins.
Aug 2004
Notices-to-proceed issued to general contractor and
electrical contractor. Demolition of structures on
the construction site completed. Under agreement with
the Syracuse Housing Authority, public housing
residents located in the Blaine-Oxford area are
assisted in finding new apartments. Relocations are to
be completed by November 15, 2004.
Sep 2004
Construction begins with site preparation work.
Perimeter fencing is installed, office trailers
arrive on site, and the former apartment building at
115 Oxford Street is demolished. In all, seven
structures are demolished, including five houses,
purchased from their owners, an abandoned garage, and
one apartment building.
Oct 2004
Oxford Street bridge is demolished. Work begins to
relocate utility lines before relocating Main
Interceptor Sewer which crosses the construction site.
County officials meet with area residents at a meeting
of SUN-Tallman Action Council. Questions are asked
and responded to regarding construction and the
proposed schedule of construction activities.
Test wells are installed for dewatering.
Mar 2005
One segment of MIS on the Midland construction site
replaced. Excavation begins for disinfection tank.
Jun 2005
Completed replacement of the 48-inch brick-and-concrete
MIS segment across the Midland construction
site with 54-inch high-density polyethylene plastic
pipe.
Jun 2006
Conveyance line to Bellevue Regulator crosses Onondaga
Creek.
Aug 2006
Onondaga County Legislature authorizes issuance of an
additional $49,890,420 in bonds to pay increased
cost of improvements for Midland facility. The
Legislature also authorizes $218,100 for
acquisition of real property for the construction,
operation, and maintenance of the Midland project.
|
|
Along the route of the 144-inch conveyenceunder construction, Nov 06
|
Sep 2006
Bellevue Avenue conveyance creek crossing is complete.
Jan 2007
Final design documents on Midland Phase III completed
and submitted to DEC for review and approval.
Apr 2007
Installation of the Phase II portion of the 144-inch
pipe is completed. The length of the pipeline is 1200
feet in this section. Midland Phase III is advertised
for bid.
Aug 2007
Expected start of construction for the Phase III
pipeline
January 2009
Expected completion of construction of the Phase III
pipeline.
|