Matt Mulcahy served as facilitator for the meeting and
began the meeting by welcoming those in attendance and
briefly stating the purpose of the meeting. Following
introductions of those present from the County, John
Clare gave a PowerPoint presentation of the proposed
Clinton Street CSO Abatement Project Facility Plan (Nov 2005) and Clinton CSO Abatement: Environmental Information Document (Nov 2005). Following the presentation, the
facilitator opened the meeting to questions and
comments from those in attendance.
The following is a summary of the questions and
comments raised by the public and the responses
provided. Additional information to the responses
given at the meeting
is printed in italics.
Similar or repeated questions have been consolidated.
Following the meeting, there was a public comment
period that closed on December 30, 2005. Any written
comments received are included in the Appendix, below.
1.
What level of treatment will the regional storage and
treatment facility provide to the combined sewage,
realizing it is not the same level of treatment as
Metro?
Response:
The ACJ requires the County to abate CSOs by
eliminating or capturing for treatment 85% of the CSO
volume on an average annual system wide basis, to
eliminate or minimize floatables from discharging into
Onondaga Creek and to provide sufficient facilities to
reduce bacterial concentrations to less than 200
cfu/100 mL within the service area for the 1-year
design storm. The Clinton facility plan is designed to
meet these ACJ requirements.
When the volume of the storm, requires the regional
treatment facility to fully operate and discharge
treated effluent, floatables will be removed and the
effluent will be treated with sodium hypochlorite to
kill bacteria and then dechlorinated with sodium
bisulfate before it is released into Onondaga Creek.
(Clare)
2.
What are the incremental costs for higher levels of
treatment?
Response:
The County does not have a listing of incremental
costs for "higher levels of treatment." The
alternatives evaluated by the County satisfy the
requirements of the Clean Water Act and the ACJ.
(Clare)
Out of the alternatives evaluated, the County has recommended the alternative that will meet these requirements in the most cost effective manner.
3.
Suggested that the County look into further reducing
costs. Asked if the County had looked into generating
energy from the water in the operation perhaps with
use of a low head turbine for instance. (K. Miranda)
Response:
These CSO facilities operate on average fifty to sixty
times per year during wet weather situations. The wet
weather events are normally of limited time duration.
For this reason, the County has not investigated
energy generation due to the fact that the energy
developed would be unpredictable, intermittent and of
very limited duration.
In addition, the RTF will be designed at water surface elevations high enough for discharge into the creek, but no higher than necessary to save energy costs associated with pumping. Therefore, the free fall will be
minimal and not sufficient for even low head turbines.
4.
County should look at this as an opportunity and think
outside the box. Need to look at long term planning
issues and see what other projects could be tied into
this project in a useful way. Speaker suggested as an
example of multi-use facilities, incorporating nuclear
waste storage for instance into the RTF. The County
should look at this project and see how it could
contribute to the City in other real beneficial ways.
Could be tied into the MOST in some ways for
educational programs. Was willing to give the County
the names of designers who could really help with this
kind of multi-use thinking. (E. Kamell)
Response:
The County has looked into tie-ins with other
beneficial projects like the creekwalk, parking
alternatives, etc. and has been actively pursuing
those possibilities since starting this facilities
planning process. The County would take designers'
names if she would like to pass them along to County
and/or further suggestions for multiple use
facilities. (Elander)
5.
Has anyone looked into the air pollution from these
facilities? Does the ACJ consider air pollution?
(Wolfson)
Response: Eidt:
The ACJ does not get into air pollution issues.
Those are design issues. Air pollution controls, if
necessary, would be put in the final design of the
facility that would then be reviewed by DEC.
6.
Concerned about release of chlorination by-products
into the environment and their impacts on human
health. Stated that a Health Risk Assessment must be
done. He asked where the Health Risk Assessment was
and who was going to do it? (Wolfson)
Response: Eidt:
Can't answer that question. The DEC Division of
Air would get involved if and when there is an
emission point determined during design.
Following the meeting, the County formally asked DEC for an opinion on the necessity for a health risk assessment.
See letter from County to DEC in Appendix.
In a subsequent discussion on the topic with DEC, the
County was informed that no such health risk assessment would be required for such a facility and DEC would be indicating that opinion in a letter of response (as not yet received) to be sent to the County.
7.
Review schedule for completion and operation of this
project.
Response:
Design of the conveyances is scheduled to be complete
by September 2006. Construction of the conveyances is
scheduled to commence by December 2006 and be
completed by August 2008.
Design of the Regional Treatment Facility is scheduled
to be complete by April 2007. Construction is
scheduled to commence by July 2007 and be completed by
July 2009. (Clare)
8
My property is directly affected by this project
because the conveyance line goes right through it.
Have you looked into other possible routes and
alternatives like use of the Erie Boulevard storage?
How will the County compensate me for disturbing my
property and making it no longer available for
development, therefore stifling growth in the Armory
Square area? What about changing the RTF's location to
the Dickerson site? (J. Butler)
Response:
Other routes have been looked into. Use of the Erie
Boulevard system for storage is not feasible because
there is no remaining capacity. (Clare)
At your convenience, the County will plan to meet with
you in the very near future to discuss your concerns
about your property. (Elander)
The Dickerson Site would have required the same
conveyance route through your (Butler) property. One
of the alternative routes that was looked at was
putting the pipe in Franklin Street; however, this
would have been much more disruptive to the whole of
Armory Square area. (Clare)
Diverting flow from CSO area 027 to the Erie Boulevard Storage Structure was investigated. The existing volumes of CSO inflow in addition to the non-CSO stormwater currently utilize almost all of the capacity of the Erie
Boulevard Storage Structure. Even if there were room for the flow from 027, it would not eliminate the conveyance pipe that is currently proposed through your property between Walton and W. Jefferson Streets. This pipe
will
be bringing flow from CSO 029 to the regional treatment facility.
At the proper time the County will order an appraisal to determine fair market value of the property. An offer from the County will then be made to purchase the property or acquire an easement. The use of eminent domain
(condemnation) will only be used as a last resort if it is determined that a negotiated purchase on reasonable terms cannot happen.
9.
Did you look into sewer separation for the Fayette St.
trunk sewer? (D. Hughes)
We'll take a look at that, if we haven't already and
respond in the responsiveness summary. ( Elander)
Further response: CSO 027 drainage basin contains 2,695 LF of combined sewers within residential areas and 28,520 LF of combined sewers in the non-residential areas.
(See Table 5-2 in the draft Clinton facilities plan.)
Using the sewer separation costs in the CDM/C&S memorandum contained in Appendix I of the facility plan, separating this one basin would cost an estimated $28.7 million.
Clearly, the choice to undertake sewer separation within CSO basin 027 would increase the total project costs without significantly lowering costs attributable to conveyances or the size of the regional treatment
facility. Therefore, the lack of any economic benefit would not justify the severe disruption and resulting economic impacts that such a sewer separation project would have on downtown Syracuse.
10.
Encouraged use of more storage like at the Midland RTF
thereby reducing the number of vortex units. Noted
Midland had at least half of total volume available
for storage. Use more sewer separation to get
stormwater out of the system and therefore reduce size
of plant. (A. Lane)
Response:
Various storage options were investigated for the
Clinton project.
One of the options looked into was similar to that
used for the Midland facility. It was recommended that
this type of application was not the most cost
effective approach to abating CSOs within the Clinton
area for the reasons stated in
Chapter 6 and Table 6-4
of the draft facilities plan. (Clare)
Also, when large volumes of stormwater are "taken out" of the system through extensive sewer separation, that stormwater volume (via a separate pipe) is discharged into Onondaga Creek without any level of floatables
control or treatment to reduce bacteria levels. These untreated stormwater volumes could be in excess of existing levels released to the creek because the existing combined sewer system currently captures large volumes
of
polluted stormwater and conveys it to Metro for treatment. This is even more significant in highly urbanized and impervious areas like the Clinton basin area.
11.
Had given 5 questions to J. Clare and had not received
a response. Asked for that response. Noted that all
estimates of CSO volumes had gone up since the Midland
negotiations were held with the State and the
Partnership for Onondaga Creek. Questioned why the
volume numbers calculated through modeling had changed
so much? She cited that the volume before negotiations
on Clinton had been estimated at 142 MG and now it was
225 MG. (A. Lane)
Response:
We will get back to you with the responses to your 5
questions. (Elander)
(See below for County response to A. Lane letter with
written questions.)
With regard to the Clinton and Erie Boulevard Storage System connection, prior to 2002, the Clinton model did not include portions of the CSO 080 drainage area in the upper reaches of the Fayette Trunk Sewer (which is
interconnected with the EBSS ). Dry weather flow and smaller storm events are directed down the Fayette Trunk Sewer and during larger storms combined sewage is discharged to the EBSS. These areas contribute additional
flow
to the Clinton RTF as well via the Fayette Trunk Sewer. New model figures reflect this additional flow.
12.
What is the process by which the County will purchase
the needed property in the "Trolley Lot" from the
City?
Response:
The County will attempt to purchase the property from
the City through a standard negotiated purchase. In
the past, the City has told the County that they
didn't want to sell the land to the County. If they
maintain that position, the County will pursue
acquisition of the land through the use of eminent
domain as was done on the Midland project. Currently,
both the City and the County are still waiting on the
U.S. Court of Appeals for the Second Circuit to issue a
decision on the use of eminent domain on the Midland
project that was requested when the City appealed a
lower court's decision to uphold the County's use of
eminent domain. (Elander)
13.
What about replacing parking that will be taken away
by use for the RTF?
Response:
The County has consistently stated our commitment to
replacing any parking we take from this area due to
our construction and the completed project. Many
alternatives have been offered that could assist in
expanding parking supply within the Armory Square area
as well as downtown in general.
Possible alternatives mentioned include adding on to
the Atrium garage and expanding its hours of operation
on nights and weekends, incorporating parking into the
Regional Treatment Facility, building a parking garage
on the lot across from the Hawthorne Suites as part of
a joint public/private economic development venture,
providing direct funding assistance to renovate the
Hotel Syracuse garage or assisting in funding the
construction of the Excellus garage. To date, the City
has refused to discuss any parking alternatives.
(Elander)
14.
Could the new parking spaces be put in a couple of
places, not just in one location?
Response:
Above ground surface parking could be arranged on a
couple of sites. This would be one additional
possibility to those listed above. However, there is a
shortage of unused open space within the downtown area
particularly near Armory Square and multiple sites
have not been identified.
Spaces available for building a parking garage are
also limited, and it's not cost effective to build two
or more parking garages of smaller size rather the one
larger facility. (Elander)
15.
What are the good points in favor of sewer separation,
and why do some people want that vs. a regional
treatment facility?
Response:
The advantages as well as the disadvantages of sewer
separation are included in
Table 5-1 of the facilities plan.
Generally, the advantages of sewer separation
are that all wastewater is sent to Metro for full
treatment, and sewer separation results in the lowest
operating and maintenance requirements. On the
negative side, sewer separation is the most expensive
and most disruptive CSO abatement alternative to
implement. Additionally, sewer separation results in
untreated urban stormwater discharging into the creek
and at some point in time, the regulations governing
these discharges may change and require treatment.
The County does not object to sewer separation. The County objects to sewer separation where it does not make economic or environmental sense. Within the Clinton CSO area, sewer separation would cost almost $100
million more than the proposed RTF and would result in the excavation of every street within the downtown Syracuse area as well as parts of the Syracuse University area over a period of years. After all the disruption
and
the expenditure of all the extra dollars, Onondaga Creek would still be subject to significant pollutants from the discharge of increased amounts of untreated stormwater.
16.
You referred to charcoal filter. What is that for?
(Wolfson)
Response:
The regional treatment facility will include a carbon
adsorption odor control system. Any air discharged
from the facility will pass through this system. The
system is a redundant design to assure continuous
operation during CSO events even while the system is
being maintained.
17.
Reiterated concerns about by-products of chlorination
that he says will not be eliminated by dechlorination
process.
Response:
(See Questions and response #6 above.)
18.
Wants to know distance from discharge pipe to Walton
St. near Armory Square? (Wolfson)
Response:
Can not provide distance figure at this time; will
get back to you in Responsiveness Summary with that
information. (Clare)
Additional Information: Distance from outfall pipe to Walton Street at the Walton Street bridge is approximately 450´. Distance to the intersection of Walton Street & S. Franklin Street is approximately 600´.
19. Representing Hanford Pharmaceutical Company
Would like to know construction schedule and how the
construction may impact their operation. He noted that
Tully St. will be disrupted and the Company uses that
as a driveway to their operation and entrance to their
parking lot. The conveyance pipe also will be
installed directly in front of the shipping and
receiving area for the Company.
Also cited concerns if any contaminants could be
released from the air pollution control or effluent
discharge pipes because the nature of Hanford's
business requires Clean Room facilities that have air
intakes to the outside air; therefore he's concerned
about potential for air pollution and dust during
construction and post construction and if there would
be any resultant impacts on the Company's operation.
Pleased about the good things happening in the area
and possible connections with this RTF like the
creekwalk. Interested in talking to County about
alternative route to Fabius St. that would be
helpful to Hanford in continuing their operation in
downtown Syracuse. (W. Buecheler)
Response:
We will arrange to sit and discuss those issues and
routes with you. RTF will be taking care of the
current situation where untreated combined sewage is
released from 11 discharge points within a small
distance between Oneida and Fayette St. into Onondaga
Creek. (Elander)
As addressed in the draft EID, the County has determined that this project will result in no significant adverse environmental impacts. Any potential impacts will be temporary and short term related to construction. To
address these potential impacts, the County will ensure that mitigation measures are implemented to reduce impacts as much as possible. These mitigation measures can include requiring the contractors to utilize dust
control
systems, making sure that construction vehicles have proper muffler systems, maintaining access for local traffic, requiring excavated areas to be covered to allow entry into driveways by the end of each work day and
restoring and improving areas following construction.
These temporary impacts due to construction will be offset not only by the County's mitigation measures, but by the overall environmental benefits brought about by this project in addressing the 11 CSOs that currently
discharge unto Onondaga Creek in this 4-6 block area. This project will reduce odors and health concerns to the area caused by these overflows as they exist now.
20.
I used to live across the street from a large
treatment plant in New York City; so, I don't believe
this facility here will be odorless. What do you have
to say on that? (J. Miranda)
Response:
This facility will be a fully enclosed operation with
odor control system and, therefore, odorless to the
outside. It is difficult to provide a specific
response on the NYC situation without knowing the
specifics of the facility being referred to in New
York City.
The NYC facility could have been a 24-7 full sewage treatment plant, not a CSO facility with odor control. Full wastewater treatment facilities that are not fully enclosed and operate on a 24/7 basis are not comparable
to CSO abatement facilities.
And there is one case the County is aware of that was a demonstration CSO facility in New York City known as the Corona Ave. Facility. It was not equipped with any odor control system. The Corona facility also received
non-CSO or dry weather sanitary flow in addition to flow resulting from combined sewer overflows. These factors would make the Corona Ave. facility prone to odor problems and complaints.
The Clinton facility will be totally enclosed, have an
odor control system and will only operate during times
of wet weather that produce combined sewer overflows.
21.
Indicates that he is pleased this meeting was held but
concerned that all questions weren't answered. The
County should get back to lady with 5 questions,
should look outside the box for possible energy/green
building alternatives, should incorporate other
beneficial uses if possible as mentioned by urban
planner, and answer Dr. Wolfson's concerns. (J.
Miranda)
Response:
We will get back to anyone who did not get the answer
to their question tonight either directly or through
the Responsiveness Summary to be compiled and we will
investigate some of the alternatives suggested.
We will meet with Mr. Butler about his property and
Mr. Buecheler from Hanford and look into the
information Dr. Wolfson has requested. The purpose of
tonight's meeting was to hear your concerns and
suggestions. It is advantageous to us to hear these
suggestions and we are writing them down and all will
be included in the Responsiveness Summary of this
meeting.
Regarding use of chlorine, wastewater treatment
facilities across the country and around the world are
using the process of chlorination-dechlorination as
the approved disinfection method to eliminate harmful
bacteria from the effluent. These are facilities that
operate 24-7. Use of chlorine is also approved by EPA
and DEC as an effective method to eliminate bacteria
in combined sewage as well. It will be an odor-free
operation and safe. (Elander)
22.
Owner of property on Dickerson Street site offers his
property for sale as an alternative site, pointing
out it is still available and might eliminate concerns
in Armory Square. (T. Ward)
Response:
We acknowledge your property is available. The Clinton
St. site is still the preferred site for this facility
as described and evaluated in
Section 5 of the Facilities Plan.
1.
How much does each conveyance cost?
Response:
The draft facilities plan provides an estimated
construction cost for all conveyances related to the
Clinton facility of $19 million. At the present time,
we do not have a breakdown for each conveyance
section.
2.
How much storage volume is in the plan?
Response:
The following storage is included in the Clinton Plan:
Conveyances - 0.64 MG
RTF - 3.06 MG
Total - 3.70 MG
The pipe volume of the underflow main to the MIS is
not calculated as part of the in-line storage because
the underflow pipe is only used after a CSO event to
convey stored flow to the MIS.
3. a.
Why is the model's effluent prediction so
off-base when you use the old hydrograph (uses Midland
as example)?
Response:
The following response was provided from the County's
modeling consultant, Dan Davis of Brown and Caldwell:
Any collection system modeling program representative
of a combined sewer system as large as the County's
will include improvements in model development as the
programs are developed. Two models were developed and
employed for the County CSO work and both were
necessary to meet the ACJ requirements. The first,
Model A, was used to size the conveyance pipelines,
regional treatment facilities (RTFs), and associated
equipment to accommodate peak flows. This model uses a
one-year design storm. The one-year design storm is a
single storm event with 2-hour duration and so
reflects the short-term impacts on the collection
system and the RTF. Model A was not modified since it
included the EBSS connection.
The long-term Model B uses many years of rainfall to
assess the longer-term impacts on the collection
system and receiving waters and to calculate the
percentage of capture in the RTF on a average annual
basis. Model B was used also to determine average
annual volumes of discharge, and was modified since it
did not include the EBSS connection. Model B was
modified as identified in a memo by Brown and Caldwell
dated June 2, 2003, but these modifications did not
change the design flows or facility sizing. While the
Model B modifications did result in significantly
changed average annual volumes at individual
facilities, the total system-wide annual CSO volume
discharged to the receiving waters was reduced by only
4%. Additionally, the Model B modifications resulted
in an increase in total system-wide capture of
approximately 1%.
The one-year design storm (Model A) will only include
the volume associated with a single event, while the
long-term simulation (Model B) will include the
volumes from all the overflow events in a typical or
average year (approximately 50). As an example, the
one-year storm will result in a total influent flow to
the Midland Facility of approximately 15 MG; however,
the average year will result in approximately 200 MG
of influent flow to the Midland Facility.
3. b.
Explain how adding the upstream EBSS connection
increased the Clinton CSO volume from 142 MG to 225
MG?
Response:
With regard to the Clinton and EBSS connection, prior
to 2002 the Clinton model did not include portions of
the CSO drainage area (080 designations) in the upper
reaches of the Fayette Trunk Sewer (which is
interconnected with the EBSS system). Dry-weather flow
and smaller storm events are directed down the Fayette
Trunk Sewer and during larger storms combined sewage
is discharged to the EBSS. These areas contribute
additional flow (83 MG) to the Clinton RTF via the
Fayette Trunk Sewer. Also see response to Question #11
in Responsiveness Summary (above)
4.
Why is the EBSS under-utilized? Since the Fayette
trunk has three upstream connections to the EBSS why
is it only storing 5 MG (2003) and 24 MG (2004)?
Response:
The Erie Boulevard Storage System receives both
stormwater-only flows and combined sewer overflows.
During wet weather events that do not trigger a CSO
event, the EBSS still receives large volumes of
stormwater. When a CSO event starts from any of the
overflow points, the gates within the EBSS system
close and begin storing the CSO flow as well as flow
from dedicated stormwater points upstream of the CSO
points. Upon completion of the CSO event, the stored
volumes are sent to the Main Interceptor Sewer for
treatment at Metro. The volumes cited in your question
are from the measurements taken by the County's
Department of Water Environment Protection at each of
the CSO overflow points. These volumes do not include
the stormwater flows that enter the EBSS from the
dedicated stormwater-only points located upstream. The
sources of the stormwater points are separated sewer
systems upstream of the EBSS that now contribute 100%
of their stormwater flows.
The County investigated the option of storing
additional CSO flows from the Fayette trunk sewer in
the EBSS. Based on total volumes of CSO and stormwater
in the EBSS, there is not adequate capacity to store
the additional CSO volume from the Fayette St. Trunk.
5.
The tiny district of Walton St. needs to be
separated. It has a pre-Civil War Pipe.
Response:
We do not agree that it would be preferable to
separate the sewers in this area. Sewer separation
here would require excavating the entire length of
Walton St. and reconstructing internal building
connections. Even though this area is small in size,
the street involved is the main arterial within the
Armory Square area. Therefore, excavating this street
would be extremely disruptive to residents and businesses
in the area and could have potentially major economic
impacts on businesses in the entire Armory Square
area.
It is also important to point out that current
condition or age of the City's sewer pipes are not a
factor in determining the cost-effectiveness of sewer
separation under the ACJ because in most cases, the
combined pipes are still in use; however, instead of
transporting combined flow, they carry stormwater
only.
Given the fact that the flows from Fayette St. cannot
go to the EBSS, the conveyance pipe from W. Fayette
St. to Walton will be required. Since this pipe will
need to pick up the area of CSO 030 behind the MOST,
it will pass right through the end of Walton St.
anyway. It would, therefore, not make sense to go
through with full disruption of Walton St. by sewer
separation when the conveyance pipe will need to go
by this area and would be far less disruptive to
Armory Square.
The Walton St. CSO 029 will be permanently closed
under the County's Clinton facility plan, and the
result will be, therefore, environmentally superior to
sewer separation of this basin which would still
necessitate untreated stormwater to be released into
Onondaga Creek at the former CSO discharge point.
6.
In the Facilities Plan, there will be no sewer
separation (in the Clinton Plan) even for CSO 037.
However, in the facilities plan, the separation of CSO
037 is described as "currently directed by the ACJ."
How is it possible to ignore any ACJ directions?
Response:
Chapter 6 of the Facilities Plan
contains a financial
analysis that finds it is more cost-effective to
capture the CSO flow from CSO 037 and direct it to the
Clinton RTF than to undertake sewer separation in that
basin area. As stated in the Facilities Plan, "this
assessment was considered appropriate due to the short
distance between the CSO 037 outfall and the proposed
Clinton St. RTF along with the anticipated complexity
and potential construction risks, difficulties and
impacts to local business operations associated with
separation of the combined sewers within the highly
urbanized CSO 037 drainage basin." Based on plan's
finding, it was recommended that flow from CSO 037 be
included into the Clinton RTF.
This recommendation to bring in CSO 037 into the RTF
was also discussed during meetings with the Clinton
Mitigation Advisory Committee with members
representing Armory Square and downtown businesses,
and they supported this option as less disruptive than
sewer separation for CSO 037.
This more cost-effective/less disruptive alternative
is in the Facilities Plan and is in full compliance
with ACJ requirements. The State DEC has the
responsibility to review and approve the facilities
plan for compliance with the ACJ and the Clean Water
Act.
7.
How do the conveyance pipes for the Trolley Lot site
that go through J. Butler's property affect
development plans for this property or value of the
property? Owner asks if he can build on top of the
pipes and what option does he have for input into the
design?
Response:
The conveyance pipe for the Clinton project would go
through the J. Butler property whether the RTF was
located on the Trolley lot site or the Dickerson St.
site.
The same Butler property has also been identified for
use by the City as a section of the Creekwalk project.
Placement of our conveyance pipe would not be in
conflict with proposed use of this land for the
creekwalk or for its future use, as it is now, for
surface parking.
Building on top of the pipe would depend on the
structure to be developed and its use. The County will
require a permanent easement along the pipe in order
to maintain legal access to the pipe for maintenance.
The County has indicated their willingness to meet
with Mr. Butler to discuss this issue in more detail.
Susan A. Miller, Jan 2006