Clinton Street area CSO abatement
Onondaga County is working to abate combined sewer overflows
(CSOs).
CSOs create human health risks because they add
bacteria, floating trash, organic material, heavy
solids, and grit to city streams and Onondaga Lake. Material
from CSOs collects on vegetation along and in streams.
It looks bad and smells bad, and it can also transmit
disease to humans who may come in contract with the
water. Material from CSOs also depletes the dissolved
oxygen in the water that is necessary for aquatic
life.
By implementing this project, Onondaga County will meet or exceed federal and state water
quality
requirements,
reduce human health risks associated with the discharge of
untreated sewage to Onondaga Creek and Onondaga Lake, and eliminate
odors caused by discharging overflows.
The County will also make improvements to the area
affected by construction of the abatement work.
The following documents describe this project in detail:
Facility Plan
Environmental Information Document
Public hearing transcript Responses
The goal of the Clinton project is to abate eleven CSOs
between Fayette and Oneida streets near downtown
Syracuse.
Transportation engineers will develop ways to
maintain, as much as possible, the flow of traffic and
the supply of parking spaces both during and after
construction of the facilities. The Environmental Information Document examines
this and other potential environmental effects of the
project.
|
|
Geotechnical installations (Sep 2007)
|
-
Construction began at the end of July 2007 and is continuing.
-
Installation of manholes, sheeting, and sewer lines continues.
-
Installed about 60 linear feet of the 72-inch pipe
-
Formed and poured walls for two manholes
-
Completed a section of microtunneling along Tully
Street.
Work anticipated for July includes:
-
Continue installation of manholes, sheeting, and sewer conveyance
pipelines
-
Continuation of microtunneling operation on west side
of Onondaga Creek and under the Creek to the Trolley lot
-
Continue site restoration activities
-
Installation of "green" porous pavement for path on east side of MOST.
|
|
Clinton CSO area, noting CSO 030
|
Mobilization continues on project the site.
Exploratory borings were completed to help develop the
dewatering plan.
Contract 2A covers pipe installation under the
railroad near RTF to the rear of the MOST and will
take in one CSO (030).
Upcoming work:
-
Finish exploratory borings
-
Install two dewatering test wells
-
Begin installation of geotechnical monitoring instruments
-
Install construction fencing, and place signage for road detours.
The County notified bidders on April 25, 2008 that all
bids on the Clinton RTF project were rejected. Working
with the ACJ parties and others, the County will
pursue implementation of alternatives technologies to
address the Clinton CSOs. These technologies will include green
infrastructure projects.
Onondaga County held a public information meeting (Nov 2005)
and a public hearing (Feb 2006) on the Clinton CSO
abatement project. The following documents are the
public record of those meetings:
Responsiveness summary: Public info meeting, Nov 29, 2005
Transcript of public hearing, Feb 22, 2006
Responsiveness summary: Public hearing, Feb 22, 2006
|