|
Harbor Brook Environmental Information Document (Aug 2005)
by Brown and Caldwell and EcoLogic for Onondaga County Dept of Water Environment Protection
4. Alternatives considered
Nine scenarios are summarized in Table 4-1.
They consider a combination of technologies and
approaches for the abatement of CSOs in the Harbor
Brook project area were evaluated for this project.
The final Facilities Plan recommends Scenario 5a as
the preferred alternative for achieving required
improvements. Summaries of the technologies evaluated
are included in Section 4.3 of this EID. Complete
descriptions of the scenarios and technologies
considered are included in the final Facilities Plan
(Brown and Caldwell 2004).
Under the recommended scenario (5a), approximately 50
storm events will result in the release of treated
CSOs to Harbor Brook in an average year. The total
annual average volume of the treated discharge would
be approximately 75 million gallons.
Fifteen potential sites, as described below, were
originally evaluated as part of the CSO abatement
project in Harbor Brook. Of these, four sites (#4, 5,
10, and 11) were recommended for further evaluation by
project engineers. The final Facilities Plan
recommends two of these, sites 4 and 10, for
construction of the proposed RTFs.
The following criteria were used to screen the 17
candidate sites:
Relation to residences and businesses:
This criterion considers the number of residences and
businesses potentially affected by construction
activities. The distance between each candidate site
and nearby residences and businesses was taken into
consideration.
Opportunities for public facilities and community enhancement:
Each site was evaluated for opportunities to provide
open space, recreational facilities, public parking,
public education, and other positive community
amenities.
Site Availability and Current Usage:
This criterion examined current use, current
ownership, and the potential for property acquisition.
Whether current residents might be displaced by the
project was also considered.
Engineering and operational considerations:
This criterion considers compliance with the ACJ,
proximity to Metro, subsurface characteristics,
proximity to the Brook, distance from a major CSO,
capacity of the Harbor Brook Interceptor Sewer (HBIS),
flood plain issues, site topography, existing
utilities in the area, existing structures on the
site, potential for contamination from past uses,
accessibility, and opportunities to close or
consolidate CSOs.
Based on these screening criteria, the following
project engineering team from Brown and Caldwell was
able to rank the potential sites and eliminate several
from consideration. Major findings of the screening
are summarized below:
-
Site #1 is remote from the CSOs and is only
considered suitable for receiving pumped flow from the
lower basin.
-
Site #2 appears to be a fill site for an unknown
mix of material. The site will require an extensive
conveyance system to transport the CSO to the site. As
such, it will not be considered further unless other
more preferable sites are eliminated during the
environmental review process.
-
Site #3 is too small to accommodate the RTF
required to treat CSO 003 and was not considered
further.
-
Site #4 is a suitable site for construction of an
RTF for the abatement of lower basin CSOs. This site
is a relatively large, privately owned property, and
located in close proximity to CSs 003 and 004. The
site is also adjacent to Harbor Brook and the HBIS.
The site is adjacent to commercial properties. The
site is easily accessible and is currently
undeveloped.
-
Site #5 is a suitable site due to its relatively
large size and commercial setting. The site is
privately owned and located in close proximity to the
Brook and the HBIS. The site is undeveloped and easily
accessible. However, Site #5 is less desirable than
others due to previous contamination and its location
on the opposite side of the road from a large
contributing CSO.
-
Site #6 is remote from major CSOs. The conveyance
of flows from CSOs 003 and 004 would increase project
costs. Additionally, access to the site is limited due
to the presence of residences immediately adjacent to
property, which also increases potential disruption
and impacts during construction. As such, this site
will not be considered further at this time.
-
Sites #7, #8 and #9 are small and are located
near smaller CSOs. These sites are considered only
suitable for the installation of FCFs.
-
Site #10 is located within a city block that is
primarily vacant, with some adjacent commercial and
limited residential areas. This site is near the Brook
and the HBIS, and is in close proximity to CSO 014,
which is the largest contributor of CSO in the upper
basin. The site is primarily undeveloped and
accessible from Grand Avenue, Seymour Street, Amy
Street, Delaware Street and Geddes Street. This site
could be used to build a new recreational or
educational facility for nearby schools. These
characteristics make this site a highly suitable
location for an Upper Basin RTF.
-
Site #11 is also a suitable location for an Upper
Basin RTF. Although the site is located directly
across from existing residences on Grand Avenue, the
existing stone wall on the site could be refurbished
and some of the mature trees could be maintained to
provide a buffer. The balance of the site and the land
immediately adjacent to it is undeveloped. Harbor
Brook and the HBIS run along the northerly limit of
the site, and a main potable water supply line for
City of Syracuse runs adjacent to the southerly limit
of the site. This site is easily accessible from
Delaware Street and Grand Avenue. It could be used to
build a new recreational or educational facility for
nearby schools. However, this site is within the
100-year flood plain of Harbor Brook and would require
additional construction to protect the proposed
facilities. Also, construction at this site would
reduce an existing green space.
-
Site #12 is bisected by an existing water
transmission main. This site is less desirable than
others because of concerns regarding the disturbance
of this line, which is one of the major connections to
the City water distribution system. In addition, the
site is on the opposite side of the Brook from the
CSOs, thereby increasing the costs to convey the CSO
to the site.
-
Site #13 is remote from major CSOs. The
conveyance of flows from CSOs downstream of 016 would
require pumping, thus increasing project costs. As
such, this site is less desirable than other sites
under consideration.
-
Site #14 is part of a flood control facility; as
such, it is less desirable than other sites and will
not be considered further.
-
Site #15 is suitable for the installation of a FCF.
4.3. Alternative technology
The Facilities Plan (Brown and Caldwell 2004) includes an extensive review and assessment of available technologies for the abatement of CSOs. These technologies are categorized as follows:
-
Floatables control
Net bags
Trash racks and bar screens
Weir-mounted screens
Brush screens
Rotary drums and sieves
-
Storage/treatment
Micro screens
Continuous deflective separation
Vortex separators
Ballasted flocculation
Wetlands treatment
Storage
Overflow retention facilities
-
Disinfection
In addition, different treatment approaches were evaluated, such as:
-
Sewer separation
-
Regional conveyance to Metro
-
Regional conveyance, and in-line storage and treatment
The Facilities Plan (Brown and Caldwell 2004) includes
a detailed description of each technology or approach,
including basis for design, perceived advantages and
disadvantages, construction sequencing and project
scheduling, permitting requirements, and estimated
costs.
Without a CSO abatement project, Harbor Brook will
continue contributing to conditions where:
-
Bacterial levels in Onondaga Lake exceed the coliform standards set in 6 NYCRR Part 703.4
-
Release of floating solids is in violation of 6 NYCRR Part 703.2.
Onondaga County is required, under the ACJ, to
"design, construct, maintain, and modify and/or
supplement, as necessary, a CSO control and upgrade
program in accordance with NYSDEC CSO guidance". The
"no action" alternative would be in violation of the
requirements of the ACJ. Without CSO remedial actions
in Harbor Brook, Onondaga County will not come into
compliance with provisions of the State's
Environmental Conservation Law or the federal Clean
Water Act.
|