Go to home page
Go to home page

Env Info Document

Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell
for Onondaga County Dept of Water Environment Protection

Executive summary

Harbor Brook combined sewer collection system

A total of 18 CSOs from the Harbor Brook watershed discharge into Harbor Brook.
Click to enlarge

The locations of all CSO outfalls and drainage areas are shown in Figure ES.1.

 
Click to enlarge

These areas are shown on an aerial photo in Figure ES.2.

For the purposes of developing abatement alternatives the drainage areas have been broken up into three general areas including the Upper, Middle and Lower Basins.

Sanitary sewage and storm water from these areas collect in a network of pipes that discharge into the Harbor Brook Interceptor Sewer (HBIS). Flows in excess of the capacity of the HBIS are relieved through Combined Sewer Overflows (CSOs), which discharge to Harbor Brook.

Impacts of CSO discharges

The discharge of untreated sewage through combined sewer overflows to Harbor Brook contributes to the discharge of floatables and conditions where the bacterial levels in Onondaga Lake exceed the coliform standards set in 6 NYCRR Part 703.4. However, computer modeling has been used to demonstrate that the disinfection of all CSOs is not required to achieve water quality standards for bacteria in those portions of Onondaga Lake designated as Class B.

CSOs also contribute to the release of floating solids in violation of 6 NYCRR Part 703.2. The term floating solids or floatables is used to describe those materials that float at or near the water surface, and can include neutrally buoyant materials that are carried along within the flow. All alternatives that were considered meet the water quality objectives and criteria established through the ACJ process.

Environmental information document

A separate Environmental Information Document (EID) has been developed for the Harbor Brook CSO Abatement Project. The EID includes the results of the Phase IA Literature Review and Archeological Sensitivity Assessment to be completed by Hartgen Archeological Associates, Inc. as a subconsultant to Brown and Caldwell on sites for CSO-related facilities which would be part of the overall Harbor Brook CSO abatement plan.

Public participation

During the compilation of this draft Facilities Plan, County staff and design engineers met with and gave presentations to various individuals and groups to provide information on the purpose and status of the Facility Plan and to obtain public input on potential issues and concerns. Individuals included interested county and city officials, area business people, local school and church officials and residents of the City's west side. In addition, public availability sessions were held and information distributed via direct mailings to area residents.

The County will continue its public participation activities to solicit and receive further input from the community. Public participation activities will include direct mailings to area residents, holding availability sessions in the neighborhoods near Harbor Brook, presentations to local groups and organizations, public information meetings and other activities.

Harbor Brook in-water system (HB IWS)

The original HB IWS concept included a storage structure at the mouth of Harbor Brook along with the associated Harbor Brook Floatables Control Facility (HB FCF), located just upstream. The HB IWS was to be constructed in two increments, the demonstration phase and the full-size, both of which would provide temporary containment of wet-weather discharges for subsequent treatment at Metro.

All of the potential sources for the contamination on the landside in the vicinity of the proposed IWS have not yet been identified. In light of evidence of the ongoing release of contamination occurring near the mouth of Harbor Brook, any plan to capture the brook flow in an IWS would also lead to capture of contaminated materials which would require appropriate disposal.

As a result of the impediments identified above, the HB IWS is not considered a viable CSO abatement approach for the Harbor Brook Basin. Alternatives to the HB IWS have been developed and presented in the following sections.

Siting analysis

Fifteen potential sites were identified for further evaluation of the abatement of CSOs discharging to Harbor Brook. Fourteen potential sites were identified along Harbor Brook for the location of Regional Treatment Facilities (RTFs) and one site was identified for treatment at Metro.

Floatables control facilities (FCFs) will be placed at the site of the CSOs. Where feasible, the FCFs will be located in existing roads. Where not feasible, the FCF will be locatged to minimize traffic and disruption during construction and maintenance. and home- or business-owner disruption during construction and maintenance.
Click to enlarge

The sites under consideration have been shown on a street map in Figure ES.3.

 
Click to enlarge

Fig ES.4, Aerial photo

The following criteria were developed for use in assessing the sites that have been identified:

  • Relation to residences and businesses
  • Opportunities for public facilities and community enhancement
  • Site availability and current usage
  • Engineering and operational considerations.

Based on site characteristics and the Decision Criteria listed above, two sites were selected for the siting of the RTFs. These are summarized below and shown in Figures ES.3 and ES.4.

  • Site #4 is a suitable site for construction of an RTF for the abatement of lower basin CSOs. This site is a relatively large, privately owned property and located in close proximity to CSOs 003 and 004. The site is also adjacent to Harbor Brook and the HBIS. The site is adjacent to commercial properties, easily accessible and is currently undeveloped.
  • Site #10 is located within a city block that is primarily vacant with some adjacent commercial and residential areas. This site is near the Brook and the HBIS and is in close proximity to CSO 014, which is the largest contributor of CSO in the upper basin. The site is primarily undeveloped and accessible from Grand Avenue, Seymour Street, Amy Street, Delaware Street and Geddes Street. As part of the recommended plan, this site could be used to build a new recreational or educational facility for nearby schools. The costs for recreational or educational facilities are not included in the project costs. These characteristics make this site a most suitable location for an Upper Basin RTF.

Technology evaluation

A number of technologies have been considered viable for the abatement of the Harbor Brook combined sewer overflows (CSO). Although sewer separation is not a technology but a CSO abatement option, it is included in this section.

The various technologies considered are grouped into floatables control and storage-treatment. More detailed evaluations of the technologies are described further in the body of the Facilities Plan.

Floatables control. A number of technologies were identified and evaluated for floatables control. Those that were considered include:

  • Net bags
  • Trash racks and bar screens
  • Weir-mounted screens.

Storage-treatment. A number of technologies were identified and evaluated for storage and treatment. Those that were considered include:

  • Vortex separators
  • Storage
  • Overflow retention facilities
  • Disinfection.

Development of treatment systems. The technologies identified above were assembled into treatment systems that are necessary to meet the requirements of the ACJ. These include:

  • Screening, where disinfection is not required
  • ORF with in-line storage and high-rate disinfection
  • Vortex separators and high-rate disinfection
  • Offline-upstream storage with vortex separators and high-rate disinfection
  • Off-line storage at the Metro tertiaries and treatment
  • Regional off-line storage
  • Sewer separation.

Scenario evaluation

Four main alternatives for Harbor Brook CSO abatement were identified as:

  • Sewer separation
  • Conveyance to Metro for storage and treatment
  • Regional treatment facilities (RTFs)
  • Floatables control facilities (FCFs)

These alternatives were further evaluated to develop a number of scenarios for the complete abatement of CSO discharging to Harbor Brook. Each scenario addresses the lower, middle and upper basins and was developed with the goal of meeting or exceeding the requirements of the ACJ.
Click to enlarge

An overview of these scenarios is included in Table ES.1.

Scenario 1—Sewer separation

Description. Based on the anticipated extent of disruption, duration of construction and the high project cost of separating large densely urban tributary areas, sewer separation was considered viable only for the Middle Basin of Harbor Brook (CSOs 005, 006, 006A, 007, 008, 009, 010, 011, and 013). The characteristics of the Middle Basin which make it more viable for sewer separation include: fewer number of streets and smaller volumes of CSO. Sewer separation of the entire Harbor Brook Basin was also presented for comparison purposes. However, sewer separation was dismissed based upon the above factors.

Conveyance to Metro for storage and treatment

Two scenarios were identified for conveyance of Harbor Brook CSOs to Metro for storage and treatment: namely, conveying CSOs 003 through 008, or full conveyance (CSOs 003 to 078). For both alternatives CSO 063 would receive an FCF.

Scenario 2—Full conveyance

Description: This alternative consists of a conveyance that would divert flow from each of the 18 Harbor Brook outfalls to Metro for storage-treatment. In order to meet the ACJ requirements, an additional storage facility would need to be provided to capture the 1-year recurrence interval volume. Flows in excess of the combined storage volume would be conveyed to a separate tank and receive high-rate disinfection prior to discharging to the Lake. As such, the Metro tertiaries and new disinfection facility would act as an Overflow Retention Facility (ORF). The Metro tertiaries would require retrofitting to be utilized for this purpose.

Scenario 3—Lower basin conveyance

Description: The CSOs located in the Lower Basin (CSOs 003 and 004) as well as a portion of the Middle Basin CSOs (005, 006, 006A, 007, and 008) would be conveyed to a pumping station and to the Metro tertiaries for storage and subsequent treatment. Wet-weather volumes greater than the 1-year recurrence interval volume would be discharged through the existing overflows and/or at the new pump station outfall.

Based upon costs, scenarios 2 and 3 were dismissed.

Scenarios 3 through 9—Regional treatment facilities

Based on the location of the major CSOs and the characteristics of suitable local sites, it was considered practical to construct two separate Regional Treatment Facilities (RTFs) in the Harbor Brook combined-sewer basin. The first, identified as the Upper Basin RTF, would address the Upper Basin CSOs and would be designed to address a portion of the Middle Basin. The second facility, the Lower Basin RTF, would provide CSO abatement for the Lower Basin and would be designed to address a portion of the Middle Basin as well.

Three technologies that were considered for storage-treatment in combination with disinfection were considered viable. These include an Overflow Retention Facility (ORF), a vortex facility, and a combination of vortex and off-line upstream storage. In addition, a regional storage facility without disinfection was included.

Scenarios 6 through 9—Floatables control facilities

Description: FCFs have been presented as viable alternatives for relatively smaller CSOs (CSO 005, 006A, 007, 009, 010, 011 and 013).

Since the Emerson Avenue overflow (CSO 063) does not discharge directly from the sewer to the Brook, an FCF would be sufficient treatment for this CSO. All of the scenarios except full separation include an Emerson Avenue FCF.

Replacement of HBIS

Two Middle Basin CSOs (006 and 008) would be eliminated by improvements to the regulator sewers as well as the Sacket Street and Richmond Avenue pumping stations.

A common project associated with each scenario regardless of the technologies considered is the replacement of the Upper and Middle Basin portions of the HBIS. The HBIS from Velasko Road north to Fayette Street is a 30-inch slab top sewer built in the early 1900s and is in poor condition. In addition, in the vicinity of Fowler High School, the HBIS appears to have a significant limitation that has reduced its capacity by more than 50 percent. As a result of these conditions, the HBIS should be replaced from Velasko Rd. north to Fayette Street. The Upper Basin RTF would include abandonment of the HBIS and utilization of a new conveyance pipeline to convey dry weather flow to the RTF location.

Summary of basin-specific options

Table ES.1 [above] summarizes the scenarios identified above. The table includes the approach used for each scenario and for each of the Lower, Middle and Upper Basins. The total project and present worth costs for each scenario are provided for comparison purposes. In addition, the average annual number of treated discharges as well as the annual average discharge volumes are shown in Table ES.1.

Table ES.2 presents the project costs, estimated annual O&M costs and present worth costs.
 
Table ES.2. Present worth analysis
Scenario Total est. project cost Est. annual O&M cost Present worth
Scenario 1 - Sewer separation $261,930,000 $53,000 $262,700,000
Scenario 2 - Convey and treat at Metro 111,390,000 450,000 117,730,000
Scenario 3 - Convey-treat at Metro, vortex, FCF 91,860,000 652,000 101,050,000
Scenario 4 - Vortex facilities, separation, FCF 62,830,000 609,000 71,410,000
Scenario 5 - Vortex facilities and FCF 58,460,000 607,000 67,020,000
Scenario 5a - Combo of Scenarios 5 and 6 55,230,000 678,000 64,790,000
Scenario 6 - Vortex facilities, FCFs, PS upgrades 53,410,000 731,000 63,710,000
Scenario 7 - ORFs, FCF, FCFs, PS upgrades 68,780,000 372,000 74,020,000
Scenario 8 - Vortex-offline and upstream storage facilites, FCFs, PS upgrades 60,760,000 552,000 68,540,000
Scenario 9 - ORF, regional storage, FCFs, PS upgrades 69,810,000 382,000 75,190,000
Notes: Based on ENRCCI = 7314 escalated to midpoint of construction worth cost bsed on 25-yr useful life and discount rate of 5.0%

CSO closures

CSO closure has been considered for each of the scenarios. For all scenarios, CSOs 004, 005, 006, 008, 015, and 016 would be permanently closed. Additionally, CSO closure would be included as part of any sewer separation. These closures are indicated on Figures ES.6 and ES.7.

Recommendation

Based on the information presented in this report and summarized in Table ES.1, the three more cost-effective scenarios of the ten evaluated are 5, 5a and 6. While Scenario 6 represents the lowest overall cost, Scenario 5a provides the best balance of low cost, reduced number of CSO facilities and fewer average annual treated discharges. Therefore, Scenario 5a is recommended as the preferred Scenario.

The locations of the proposed facilities for Scenarios 5a are shown in Figures ES.5 through ES.8.
Emerson FCF (photo)
Lower Basin RTF (photo)
Upper Basin RTF (photo)
Upper Basin conveyance (photo)


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection