Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell for Onondaga County Dept of Water Environment Protection
9. Project Implementation Schedule
The following presents the proposed implementation
schedule for the Harbor Brook CSO abatement
facilities.
|
Begin construction of FCFs
|
March 2007
|
|
Complete construction of FCFs
|
May 2008
|
|
Begin construction of Conveyances
|
January 2008
|
|
Begin construction of RTFs
|
January 2008
|
|
Complete construction of Conveyances
|
May 2010
|
|
Complete construction of RTFs
|
September 2010
|
|