Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell
for Onondaga County Dept of Water Environment Protection

9. Project Implementation Schedule

The following presents the proposed implementation schedule for the Harbor Brook CSO abatement facilities.
 
Begin construction of FCFs March 2007
Complete construction of FCFs May 2008
Begin construction of Conveyances January 2008
Begin construction of RTFs January 2008
Complete construction of Conveyances May 2010
Complete construction of RTFs September 2010