|
Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell for Onondaga County Dept of Water Environment Protection
8. Recommended Plan
As identified in Section 7.2 the recommended/preferred CSO abatement approach for the
Harbor Brook service area is Scenario 5a and includes vortex separators followed by
disinfection at both the Upper and Lower Basins. The Middle Basin CSOs 005 through
008 would be conveyed to the Lower Basin RTF and CSOs 009 through 013 would
include FCFs. CSO 063 would also include an FCF. In addition, portions of the HBIS in
the Middle Basin would be abandoned and a new interceptor constructed.
Site #4 and #10 were selected as the preferred sites
for the proposed RTFs based on an evaluation of
criteria identified in Section 4. Site #10 was
considered more favorable over #11 due to Site #11's
location in the 100-year flood plain, as well as that
it would be reducing an existing green space.
The plan [Scenario 5a] is summarized below and is shown in Figures
8.1 through 8.8 for Lower, Middle and Upper Basin
facilities. The figures depict the proposed facilities
on separate basemaps of city streets and aerial
photos.
Emerson FCF (map)
Lower Basin RTF (map)
Upper Basin RTF (map)
Upper Basin conveyance (map)
Emerson FCF (photo)
Lower Basin RTF (photo)
Upper Basin RTF (photo)
Upper Basin conveyance (photo)
Upper and lower RTFs:
-
CSO conveyance pipelines to collect and transport captured CSO, up to the 1-year
design storm, to the vortex separator treatment systems for the Upper and Lower
Basins (estimated volume of storage the conveyances will provide is 0.40 MG;
0.12 MG for the Upper RTF, 0.28 MG for the Lower RTF)
-
Influent stilling well/grit sump (estimated storage provided is 0.30 MG)
-
Coarse screening/manually cleaned trash racks
-
Influent pumping
-
Vortex solids separators to provide storage for smaller storms events and
floatables and settleable solids removal for larger storm events (estimated storage
provided is 0.17 MG)
-
Vortex solids separator underflow conveyance to the HBIS during a storm event
-
High-rate disinfection by chlorination/dechlorination for bacterial reduction prior
to discharge to Harbor Brook (estimated storage provided is 0.97 MG)
-
Dewatering of the vortex separators and disinfection
tank stored flows to the HBIS following a storm event
-
Odor control facilities
-
CSO 063 would be an FCF using weir-mounted mechanical
screens.
For planning purposes, the vortex separator treatment
systems were considered to include USEPA swirl
concentrator treatment units. High-rate disinfection
following the vortex separators, previously documented
by USEPA demonstration projects to achieve up to three
log bacterial reductions with a 5-minute contact time
in conjunction with high intensity mixing, will be
used as the basis for achieving the required bacterial
reduction pursuant to the ACJ. Dechlorination using a
1-minute contact time will also be included to reduce
potential toxicity issues that may be associated with
chlorinated discharges. The total in-line storage provided is estimated
to be 1.8 MG.
Middle Basin CSOs:
-
CSOs 005 through 008 would be conveyed to the Lower
Basin RTF
-
FCFs using weir-mounted mechanical screens for CSOs
009 through 013
-
Floatables collected at each FCF would be temporarily
stored and/or directed to the HBIS for treatment at
Metro following each storm event
-
Two CSOs (006 and 008) would be eliminated through
upgrades to existing pumping stations (Sackett St. and
Richmond Avenue) and regulator sewer improvements.
The recommended plan was also evaluated to determine
which CSOs might be permanently closed (eliminated).
Based on modeling results, CSOs 004, 005, 006, 008,
015, and 016 would be permanently closed.
The total estimated project cost for the
recommended plan is $55,200,000.
|