Go to home page
Go to home page

Env Info Document

Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell
for Onondaga County Dept of Water Environment Protection

7. Scenarios

7.1 Purpose

The conclusions made in the siting analysis, technology evaluation, sewer separation and alternatives analysis sections have been used to develop seven scenarios for the complete abatement of the CSOs discharging to Harbor Brook. Each scenario addresses the lower, middle and upper basins and was developed with the goal of meeting or exceeding the requirements of the ACJ. These scenarios include combinations of Regional Treatment Facilities (RTFs), disinfection, sewer separation, conveyance to Metro, and Floatables Control Facilities (FCFs). Replacement of portions of the HBIS is a commons project for each Scenario.
Click to enlarge

Table 7.1 shows overview of scenarios with frequency of overflows, average annual discharges, estimated project and present worth costs.

 

 

Table 7.2 presents the project costs, estimated annual O&M costs and present worth costs.
 
Table 7.2. Present worth analysis
Scenario Total est. project cost Est. annual O&M cost Present worth
Scenario 1 - Sewer separation $261,930,000 $53,000 $262,700,000
Scenario 2 - Convey and treat at Metro 111,390,000 450,000 117,730,000
Scenario 3 - Convey-treat at Metro, vortex, FCF 91,860,000 652,000 101,050,000
Scenario 4 - Vortex facilities, separation, FCF 62,830,000 609,000 71,410,000
Scenario 5 - Vortex facilities and FCF 58,460,000 607,000 67,020,000
Scenario 5a - Combo of Scenarios 5 and 6 55,230,000 678,000 64,790,000
Scenario 6 - Vortex facilities, FCFs, PS upgrades 53,410,000 731,000 63,710,000
Scenario 7 - ORFs, FCF, FCFs, PS upgrades 68,780,000 372,000 74,020,000
Scenario 8 - Vortex-offline and upstream storage facilites, FCFs, PS upgrades 60,760,000 552,000 68,540,000
Scenario 9 - ORF, regional storage, FCFs, PS upgrades 69,810,000 382,000 75,190,000
Notes: Based on ENRCCI = 7314 escalated to midpoint of construction worth cost bsed on 25-yr useful life and discount rate of 5.0%

A more detailed summary of the costs is included in Appendix F.
Click here for Appendix F. Construction cost summary for abatement scenarios.

7.1.1 Scenario 1—Full sewer separation

This scenario represents the separation of all of the combined sewers in the Harbor Brook drainage basin. Sewer separation is considered an effective approach to CSO abatement. However, there are several major disadvantages to this scenario. If untreated stormwater is discharged, it may have a negative impact on the water quality of Harbor Brook and Onondaga Lake.

Ownership of the separated sewers will be transferred to the City of Syracuse following the completion of construction. As a result, the City would be responsible for maintaining these new sewers and the treatment of stormwater under future more stringent regulations.

Since new sewers would be constructed on almost every street in the sewer service area, the disruption to the community would be the most extensive of any scenario considered. The cost of complete sewer separation is also estimated to be significantly greater than the cost of any of the other scenarios. The estimated project cost for this scenario is $262 million and includes the cost of the HBIS replacement for $2.34 million. This cost, however does not include treatment of the stormwater that will likely be enforced in the future under current environmental regulations.

7.1.2 Scenario 2—Full conveyance to Metro

This scenario includes the conveyance of all Harbor Brook CSOs to Metro for storage and subsequent treatment. The major advantage of this alternative is that a greater portion of CSO would be captured and receive treatment at Metro. Although this scenario is considered effective at improving the water quality of both Harbor Brook and Onondaga Lake, there are two significant disadvantages to this scenario. First, there will be considerable disruption of the community along the HBIS corridor. Second, the project cost of this scenario is estimated to be higher than the costs of several other scenarios considered. The estimated project cost for this scenario is $111 million.

7.1.3 Scenario 3—Regional treatment facilities / conveyance to Metro

Under this scenario, CSOs 014 through 078 from the upper basin would be conveyed to the upper basin RTF along with CSOs 009 through 013 from the middle basin. This facility would need to accommodate 175 cfs in order to meet the ACJ requirements, based on bacteria modeling results.

For the middle basin, CSO 005 through 008 would be conveyed to Metro along with CSOs 003 and 004 from the lower basin. CSO 063 will be directed to the Emerson FCF.

This scenario will meet the water quality requirements of the ACJ. Its advantages are that it utilizes available capacity at Metro, has a lower project cost compared to full conveyance, and minimizes the addition of new treatment facilities. The estimated project cost for this scenario is $91.9 million.

7.1.4 Scenario 4—Regional treatment facilities / sewer separation

Under this scenario, the upper basin CSOs 009 through 078 would be addressed with the upper basin RTF. Modeling has shown that this facility would need to accommodate a peak flow of 175 cfs.

The middle basin CSOs 005 through 008 would receive targeted sewer separation.

This scenario also includes the Emerson FCF for 063. An RTF would consolidate CSOs 003 and 004. This facility is termed the Lower Basin RTF.

This scenario offers a reasonable balance of minimizing community disruption while meeting the minimum water quality requirements of the ACJ, not only in Onondaga Lake but also in Harbor Brook. The estimated project cost is $63.6 million.

7.1.5 Scenario 5—Regional treatment facilities

Under this scenario, the Upper Basin RTF would take flow from CSO 014 through 078 as well as CSOs 009 through 013 from the middle basin. Modeling results show that the Upper Basin RTF would need to accommodate a peak flow rate of 175 cfs to meet ACJ requirements.

The remaining middle basin CSOs (005-008) would be consolidated and conveyed to the Lower Basin RTF along with CSOs 003 and 004. The Lower Basin RTF would need to accommodate a peak flow rate of 205 cfs. CSO 063 would receive floatables control as an FCF.

This scenario has a relatively low cost, will meet or exceed the water quality criteria of the ACJ and will provide treatment of stormwater in the form of CSO, that will likely be enforced in the future through current regulations. The estimated project cost for this scenario is $58.5 million.

7.1.6 Scenario 5a—Regional treatment facilities / floatables control facilities

Under this scenario, the upper basin CSOs 014 through 078 would be addressed with the upper basin RTF. Modeling has shown that this facility would need to accommodate a peak flow of 155 cfs. Middle basin CSOs 009 through 013 would receive floatables control as FCFs. Table 7.3 shows the average annual treated volume and frequency of discharge for the FCFs associated with this scenario.
 
Table 7.3. Average annual treated discharge frequency and volume at the FCFs
Lower Basin
063 4.5 22

Middle Basin
005* 0.2 26
006* Pump station upgrade -
006A 0.4 22
007 0.4 50
008* Pump station upgrade -
009 <0.1 1
010 <0.1 11
011 0.2 31
013 <0.1 25
*Note: Planned CSO closure

CSOs 005 through 008 would be consolidated and conveyed to the Lower Basin RTF along with CSOs 003 and 004. The Lower Basin RTF would need to accommodate a peak flow rate of 205 cfs. CSO 063 would receive floatables control as an FCF.

The estimated project cost for this scenario is $55.2 million.

7.1.7 Scenario 6—Regional treatment facilities / floatables control facilities

The Upper Basin RTF would address the overflow from CSOs 014 through 078. Modeling results have shown that the Upper Basin RTF would need to accommodate a peak flow rate of 155 cfs.

A combination of FCFs and pumping station upgrades for the middle basin could be considered for CSO areas 005 through 013. Pumping station and regulator improvements would eliminate CSOs 006 and 008. For planning purposes, the remaining scenarios will include this combination.

For the Lower Basin an RTF would address the flow from CSOs 003 and 004. The Lower Basin RTF would need to accommodate a peak rate of 190 cfs to meet ACJ requirements. CSO 063 would be treated by an FCF. Table 7.3 shows the average annual treated volume and frequency of discharge for the FCFs associated with scenarios 6, 7, 8, and 9

The estimated project cost for this scenario is to $53.4 million.

7.1.8 Scenario 7—Regional treatment facilities / floatables control facilities

This scenario is similar to scenario 7 above; however, the Upper and Lower basin RTFs would include the use of ORFs followed by disinfection in place of the HRT facility. The Lower Basin ORF would be sized for a storage volume of 3.7 MG. The Upper Basin ORF would be sized for a storage volume of 3.4 MG. The Middle Basin and CSO 063 would be as described in Scenario 6.

The estimated project cost for this scenario is to $68.8 million.

7.1.9 Scenario 8—Regional treatment facilities / floatables control facilities

This scenario is similar to scenario 7 above; however, the Upper and Lower basin RTFs would include the use of offline-upstream storage followed by half-sized vortex and disinfection facilities. The Lower Basin facility would include 1.2 MG of offline storage with an HRT sized for 95 cfs. The Upper Basin ORF would include 0.9 MG of upstream storage with an HRT sized for 78 cfs. The Middle Basin and CSO 063 would be as described in Scenario 7.

The estimated project cost for this scenario is to $60.8 million.

7.1.10 Scenario 9—Regional treatment facilities / ORF / floatables control facilities

This scenario is similar to scenario 7 above; however, the Upper and Lower Basin RTFs would include the use of an ORF and regional storage, respectively. The Upper Basin RTF would require an ORF since capacity would not be available in the HBIS to dewater a regional storage facility within a 48-hour period. The Lower Basin facility would include 5.4 MG of storage. The Upper Basin ORF would include 3.4 MG of storage.

The Middle Basin and CSO 063 would be as described in Scenario 7.

The estimated project cost for this scenario is to $69.8 million.

7.2 CSO closure

CSO closure has been considered for each of the scenarios described above. For all scenarios, CSOs 004, 005, 006, 008, 015, and 016 would be permanently closed. Additionally, CSO closure would be included as part of any sewer separation.

7.3 Recommended CSO abatement approach

Based on the information presented in this report and summarized in Table 7.1, the three more cost-effective scenarios of the ten evaluated are 5, 5a and 6. The breakout of construction costs, O&M costs, and present worth are shown in Appendix F. While Scenario 6 represents the lowest overall cost, Scenario 5a provides the best balance of low cost, reduced number of CSO facilities, and fewer average annual treated discharges.

Therefore, Scenario 5a is recommended as the preferred Scenario.


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection