Go to home page
Go to home page

Env Info Document

Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell
for Onondaga County Dept of Water Environment Protection

4. Siting Analysis

4.1 Site characteristics

Fifteen potential sites have been identified for further evaluation for the abatement of CSOs discharging to Harbor Brook. Fourteen potential sites have been identified along Harbor Brook for the location of Regional Treatment Facilities (RTFs) or Floatables Control Facilities (FCFs), and one site has been identified for treatment at Metro.

The sites under consideration have been shown on a street map in Figure 4.1.
These sites have been grouped by basin (Upper, Middle, Lower) and are shown as follows:
Figures 4.2, Lower basin map
Figures 4.3, Middle basin map
Figures 4.4, Upper basin map

Floatables Control Facilities (FCFs) will be placed at the site of the CSOs. Where feasible, the FCFs will be located in existing roads. Where not feasible, the FCF will be located to minimize traffic and disruption during construction and maintenance. These sites are also shown in Figures 4.5, 4.6, 4.7, and 4.8 with base aerial photographs:
Fig 4.5, Aerial photo
Figures 4.6, Lower basin photo
Figures 4.7, Middle basin photo
Figures 4.8, Upper basin photo

4.2 Decision criteria

The following criteria have been developed for use in assessing the sites that have been identified:
 

Relation to Residences and Businesses   This criterion considers the number of residences and businesses potentially impacted by new construction on the site. The distance between the site and nearby residences and businesses was taken into consideration.
 

Opportunities for Public Facilities and Community Enhancement   Considers the opportunities of the site to provide open space, recreational facilities, public parking, public education and other possible positive amenities.
 

Site Availability and Current Usage   Lists the owner of the property, the potential for property acquisition (if available) and the current use of the property, including potential resident displacement.
 

Engineering and Operational Considerations   This criterion considers compliance with the ACJ, the proximity to Metro, subsurface characteristics, proximity to the Brook, distance from a major CSO, capacity of the HBIS, floodplain issues, site topography, existing utilities in the area, existing structures on the site, potential for contamination from past usages, accessibility of the site, and opportunities to close or consolidate CSOs.

A summary of the information currently available on these sites is provided in Tables 4.1, 4.2 and 4.3.
Table 4.1 describes the sites that could be used in the Lower Basin.
Table 4.1 (continued)
Table 4.2 describes sites in the Middle Basin.
Table 4.3 shows sites in the Upper Basin.

4.3 Conclusions

Based on the decision criteria and the site characteristics listed above, the following conclusions have been made:

  • Site #1 is remote from the CSOs and is only considered suitable for receiving pumped flow from all CSOs or just the lower basin.
    Click here for Appendix D. Pump to Metro alternative evaluation.
  • Site #2 appears to be a fill site for an unknown mix of material. The site will require an extensive conveyance system to transport the CSOs to the site. As such, it will not be considered further unless other more preferable sites are eliminated during the environmental review process.
  • Site #3 is too small to accommodate an RTF required to treat CSOs 003 and 004 and will not be considered further.
  • Site #5 is less desirable than others due to previous contamination and its location on the opposite side of the road from a large contributing CSO.
  • Site #6 is remote from major CSOs. The conveyance of flows from CSOs 003 and 004 would increase project costs. Additionally, access to the site is limited due to the presence of residences immediately adjacent to property, which also increases potential disruption and impacts during construction. As such this site will not be considered further at this time.
  • Site #s 7, 8 and 9 are small and located near smaller CSOs. These sites are considered only suitable for the installation of FCFs.
  • Site #12 is bisected by an existing water transmission main. This site is less desirable than others because of concerns regarding the disturbance of this line, which is one of the major connections to the City water distribution system. In addition, the site is on the opposite side of the Brook from the CSOs thereby increasing the costs to convey the CSOs to the site.
  • Site #13 is remote from major CSOs. The conveyance of flows from CSOs downstream of 016 would require pumping, thus increasing project costs. As such, this site is less desirable than other sites under consideration.
  • Site #14 is part of a flood control facility, as such, it is less desirable than other sites and will not be considered further.
  • Site #15 is suitable for the installation of a FCF.

Of the fifteen sites evaluated, three are considered to be the best suited for an RTF, namely: #s 4, 10, and 11.
 

Site #4   is a suitable site for construction of an RTF for the abatement of lower basin CSOs. This site is a relatively large, privately owned property and located near CSOs 003 and 004. The site is also adjacent to Harbor Brook and the HBIS. The site is adjacent to commercial properties, easily accessible and is currently undeveloped.
 

Site #10   is located within a city block that is primarily vacant with some adjacent commercial and limited residential areas. This site is near the Brook and the HBIS and is near CSO 014, which is the largest contributor of CSO in the upper basin. The site is primarily undeveloped and accessible from Grand Avenue, Seymour Street, Amy Street, Delaware Street and Geddes Street. This site could be used to build a new recreational or educational facility for nearby schools. These characteristics make this site a most suitable location for an Upper Basin RTF
 

Site #11   is also a suitable location for an Upper Basin RTF. The site is located directly across Grand Avenue from existing residences; the existing stone wall on the site could be refurbished and some of the mature trees could be maintained to provide a buffer. The balance of the site and the land immediately adjacent to it is undeveloped. Harbor Brook and the HBIS run along the northerly limit of the site. This site is easily accessible from Delaware Street and Grand Avenue. This site could be used to build a new recreational or educational facility for nearby schools. This site is within the 100-year flood plain of Harbor Brook and would require additional construction to protect the proposed facilities. Also, construction at this site would reduce an existing green space.
 

Site #5   is also a suitable site due to its relatively large size and commercial setting. The site is privately owned. The site is located near the Brook and the HBIS. The site is easily accessible and undeveloped.


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection