|
Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell for Onondaga County Dept of Water Environment Protection
1. Basis for CSO Abatement
Onondaga County entered into an Amended Consent Judgment (ACJ) on January
20, 1998. Under Section 14 of the ACJ, entitled
[Combined Sewer Overflow] CSO Control and Upgrade
Compliance Schedule, it states:
The County shall design, construct, maintain and
modify and/or supplement, as necessary, a CSO control
and upgrade program in accordance with [NYS Department
of Environmental Conservation] DEC CSO guidance, as
set forth in [Technical and Operations Guidance
Series] TOGS 1.6.3 (CSO Control Strategy), which
implements the presumptive approach in [US
Environmental Protection Agency] EPA's CSO control
policy, as set forth in 59 F.R. 18688 (April 18,
1994). The County's program shall achieve the
following:
A. elimination or the capture for treatment of no less
than 85% by volume of the combined sewage collected in
the combined sewer system during precipitation events
on a system-wide annual average basis
B. elimination or minimization of floating
substances in Onondaga Lake attributed to the County's
CSOs
C. achievement of water quality standards for
bacteria for all portions of Onondaga Lake that are
classified as Class B pursuant to 6 NYCRR Part 895.
The Harbor Brook In-Water System (HB IWS) is listed in
the ACJ as an Interim CSO Project. The ACJ references
the HB IWS as follows:
The CSO abatement proposed on Harbor Brook will use an
in-lake technology called the EquiFlow system. The
intent of this project is to be a demonstration
project to determine the technical applicability of
its use in this location. The maximum term of the
initial project is 15 years. This system will provide
an opportunity to demonstrate abatement of CSO, urban
stormwater, and non-point pollution through a
combination of floatable solids entrapment, in-water
storage, pumpback, and treatment at Metro
[Metropolitan Syracuse Wastewater Treatment Plant].
The in-water system will also include the construction
of a floatable solids netting device to remove CSO and
stormwater floatables from Harbor Brook before they
reach the Equiflow system. (ACJ Appendix B, p. 10)
The Harbor Brook floatables netting device will be
located in the downstream reach of the brook between
Hiawatha Boulevard and the outlet to Onondaga Lake. By
placing the facility as close to the lake as possible,
floatables capture will be most effective for the
entire brook. The purpose of this facility is to
capture most of the floatable material that is
discharged to the lake from Harbor Brook. A secondary
purpose of this facility is to capture floatables in
the brook before they enter the proposed Equiflow?
facility. (ACJ Appendix B, p. 12)
Complete construction and begin operation of each and
every CSO Interim Project by July 1, 2002. (ACJ
Appendix B, p. 13)
If the [HB IWS] project is not deemed technically
acceptable, the County will proceed with the design
and construction of the Delaware and State Fair RTFs
[regional treatment facilities] at a schedule to be
proposed by the County to DEC. (ACJ Appendix B, p. 10)
The County, with input as provided by the City of
Syracuse, will review infrastructure needs,
maintenance considerations, and potential
opportunities for sewer separation before the start of
the following activity for the identified projects:
a. Design of the Midland Avenue Conveyances Project
b. Design of the Clinton Conveyances Project
c. Design of each of the RTF facilities within the Harbor Brook drainage
area, should RTFs be necessary. (ACJ Appendix B, p. 9)
The regional facility may be designed to store and/or
treat CSO. Regional facilities will be referred to as
Regional Treatment Facilities (RTF) or Floatables
Control Facilities (FCF).
The purpose of the Harbor Brook CSO Facilities Plan is
to evaluate the HB IWS in comparison to other
alternatives for abatement of CSOs in the Harbor Brook
basin, including regional facilities and sewer
separation based upon engineering and operational
considerations, environmental and community impacts,
and cost effectiveness.
In-water treatment of the County's CSOs was first
proposed in an August 1983 report entitled, In-Water
Combined Sewer Overflow Abatement Study, as an
alternative to constructing a number of the regional
treatment facilities that were recommended in the 1979
CSO Facilities Plan. At that time, two in-water
treatment facilities were considered, one for Onondaga
Creek and one for Harbor Brook. During development of
the draft Municipal Compliance Plan in the early to
mid-1990s the Onondaga Creek facility was dropped from
consideration leaving only the Harbor Brook in-water
facility included in the ACJ.
Harbor Brook is one of the primary tributaries to
Onondaga Lake, and has three water quality
designations, as listed in 6 NYCRR Part 895.4: Class C
from the source waters to the City of Syracuse line
(i.e. the vicinity of Velasko road and CSO 078); Class
B from the City line to the covered section (i.e. the
vicinity of Delaware Street and CSO 014); and Class C
through the covered section to Onondaga Lake. These
areas are shown in Figure 1.1.
|
|
Figure 1.1. Harbor Brook watershed
|
These Classes are defined in 6 NYCRR Part 701, as follows:
-
"§701.7 Class B fresh surface waters. The best
usages of Class B waters are primary and secondary
contact recreation and fishing. These waters shall be
suitable for fish propagation and survival.
-
"§701.8 Class C fresh surface waters. The best
usage for Class C waters is fishing. These waters
shall be suitable for fish propagation and survival.
The water quality shall be suitable for primary and
secondary contact recreation, although other factors
may limit the use for these purposes.
The Harbor Brook watershed has a surface area of 8,234
acres. The land use in the southern, or upper, section
of the watershed consists predominately of suburban
and residential areas and agricultural lands that
have different hydrologic responses than the northern,
or lower, urbanized section. The urbanized areas of
the Harbor Brook basin are located within the farthest
downstream reaches of the watershed and are closest to
Onondaga Lake. The 1,221-acre combined sewered area
within the urbanized portion of the Harbor Brook
basin, as shown on Figure 1.1, constitutes
approximately 20% of the combined sewer area tributary
to Metro.
The reach of Harbor Brook that flows through the urban
portion was channelized during the 1930s as part of
the U.S. Army Corps of Engineers (USACOE) city-wide
flood control program from Velasko Road to the Lake.
In 1980 Onondaga County constructed a flood detention
basin between Velasko Road and DePalma Avenue, which
was improved in 1999.
South of the detention basin, Harbor Brook is
characterized as an open, trapezoidal section from
DePalma Ave. to Delaware Street; a section from
Delaware St. to State Fair Blvd., which with the
exception of a short reach near Fowler High School is
covered; and another open, trapezoidal section from
State Fair Boulevard to Onondaga Lake.
For the purposes of this facilities plan, the
urbanized (combined sewer-service) portion of the
watershed will be broken up into three general areas
with the following designations:
Upper Basin, which begins near Velasko Road
Middle Basin, which is the predominantly covered section
Lower Basin, which is the northernmost open section that ends at the Lake.
The Onondaga County Harbor Brook Drainage District is
administered by the Onondaga County Department of
Water Environment Protection (OCDWEP), which is
responsible for the operation of the Velasko Road
Detention Basin. This detention basin was constructed
in 1980, and includes a dam and flow-regulating device
located at the end of DePalma Ave. The detention basin
was expanded near the east end so that it would retain
stream flows up to and including the 25-year design
storm. The basin expansion, channel and culvert
improvements were completed in 1999. The
flow-regulating structure was modified to increase the
maximum basin discharge to 480 cfs (the previous
discharge rate was 300 cfs).
A total of 18 CSOs from the Harbor Brook watershed
discharge into the Brook from 18 combined sewer
drainage areas. The characteristics of each CSO have
been summarized in Table 1.1.
Table 1.1 Lower Basin |
|
CSO
|
Location
|
Basin area (acre)
|
Overflow location
|
Peak rate (cfs)*
|
Volume (MG)
|
|
063
|
Emerson Ave., SW
|
122
|
West side
|
57
|
0.55
|
|
003
|
Hiawatha Blvd.
|
112
|
West side
|
95
|
1.15
|
|
064
|
State Fair Blvd.
|
350
|
West side
|
131
|
2.10
|
|
Total volume: 3.8 MG
|
| Middle Basin |
|
CSO
|
Location
|
Basin area (acre)
|
Overflow location
|
Peak rate (cfs)*
|
Volume (MG)
|
|
005
|
W. Genesee at Sackett
|
13
|
East side
|
12
|
0.19
|
|
006
|
Park Ave. at Sackett (west)
|
10
|
West side
|
7
|
0.05
|
|
006A
|
Park Ave. at Sackett (east)
|
7
|
East side
|
5
|
0.07
|
|
007
|
Richmond Ave. at Liberty
|
24
|
East side
|
2
|
0.02
|
|
008
|
Lakeview Ave. at Liberty
|
6
|
East side
|
2
|
0.01
|
|
009
|
W. Fayette (west)
|
28
|
West side
|
9
|
0.04
|
|
010
|
W. Fayette (east)
|
16
|
East side
|
12
|
0.08
|
|
011
|
Gifford St. at Fowler H.S.
|
20
|
East side
|
12
|
0.14
|
|
013
|
Seymour St.
|
12
|
West side
|
5
|
0.03
|
|
Total volume: 0.6 MG
|
| Upper Basin |
|
CSO
|
Location
|
Basin area (acre)
|
Overflow location
|
Peak rate (cfs)*
|
Volume (MG)
|
|
014
|
Delaware St.
|
196
|
East side
|
110
|
1.08
|
|
015
|
Herriman at Grand Ave.
|
40
|
East side
|
21
|
0.32
|
|
016
|
Lydell St.
|
9
|
East side
|
11
|
0.08
|
|
017
|
Hoeffler St.
|
25
|
East side
|
23
|
0.25
|
|
018
|
Rowland St.
|
145
|
East side
|
28
|
1.20
|
|
078
|
Bellevue Ave. at Velasko Rd.
|
86
|
East side
|
48
|
0.50
|
*Based on 1-yr, 2-hr duration, 15-minute rainfall interval storm Total volume: 3.4 MGTotal for Harbor Brook Basin: 7.8 MG
|
The locations of all CSO outfalls and drainage areas are shown in Figure 1.2.
These areas are shown on an aerial photo in Figure 1.3.
Sanitary sewage and storm water from these areas
collects in a network of pipes that discharge into the
Harbor Brook Interceptor Sewer (HBIS). The HBIS starts
near Velasko Road as a 15-inch pipe located on the
south side of the Brook, which it generally parallels
as it flows north toward the lake.
See Figure 1.4.
The HBIS gradually increases in size and capacity
until it becomes a 50-inch diameter pipe that
terminates at the Harbor Brook Pumping Station, which
is located along Hiawatha Blvd. adjacent to the Metro
headworks. The Harbor Brook Pumping Station is
equipped with three Archimedes screw pumps (two duty
and one standby) that discharge to the Main
Interceptor Sewer (MIS), which flows to the New
Screenings and Grit (NSG) side of the Metro headworks.
The maximum capacity of this pumping station is 30 MGD
with two pumps running. Flows in excess of the
capacity of the HBIS are relieved through Combined
Sewer Overflows (CSOs), which discharge to Harbor
Brook.
The regulator manholes (also known as diversion or
overflow manholes) and sewer pipes were typically
constructed at the same time as the HBIS, circa 1920.
The regulator and interceptor sewers are typically
sized to accommodate the anticipated dry-weather flow
and a small component of wet-weather flow from a
drainage area. Wet-weather conditions can cause flow
in the combined sewer to increase above the capacity
of the pump station, regulator and/or interceptor
sewers. During such conditions, the combined sewage
backs up and is stored in the system until the level
of the combined sewage reaches the crest of the
overflow weir. The excess flow passes over the weir to
the combined sewer overflow pipes that discharge to
the Brook.
The oldest portions of the HBIS are those from Hoeffler Street north to Fayette Street. In this stretch the HBIS
is a 30-inch slab top sewer that is in poor condition.
In addition, in the vicinity of Fowler High School the
HBIS appears to have a significant defect that has
reduced its capacity by more than 50 percent.
Another known area of concern is associated with CSO
018. The overflow chamber has high flows during
springtime conditions and may be causing dry-weather
overflows during these periods. During the late spring
of 2004, it was observed that significant flow was
being discharged to the combined sewers at the
Glenwood Avenue drainage boundary from the Bellevue
Golf Course. While there was no dry-weather overflow
occurring at the time, the flow was very close to
overflowing at the overflow chamber. This flow appears
to be drainage from the golf course's pond. Additional
investigation will be necessary during spring time
conditions to evaluate the potential for dry-weather
overflows.
Hydraulic modeling has shown that the existing
conveyance capacity (the sum of regulator-interceptor
flows and overflows) of the Harbor Brook combined
sewer system is generally limited to flow rates
resulting from events less than, or equal to, the
5-year recurrence interval storm. Wet-weather flow
that cannot enter the combined sewer system is either
stored at street level or passes along the surface
until it can either enter the system, or it reaches
Harbor Brook.
The Storm Water Management Model (SWMM) has been used
to develop the flows and volumes used throughout this
report. The model development, calibration and
projections are documented in a report entitled
Harbor Brook SWMM Modeling Report and is included in
Appendix A.
Click here for Appendix A. Harbor Brook SWMM Modeling Report.
Note:
Please add the following to p. 19 of Appendix A:
The average annual volumes developed with the long-term simulation used a historical
rain record from 1963 to 1993. The average annual volume represents the volume
generated by the model, divided by 30 years.
With the exception of CSOs 063 and 018, all of the
overflows discharge directly to Harbor Brook.
Overflows from CSO 018 flow through a short,
grass-lined swale located in the detention basin
before discharging to Harbor Brook. Overflows from CSO
063 currently flow through a retention basin created
by the flow restriction of a culvert under the rail
lines just east of Erie Blvd. Just downstream of the
rail lines flow passes through a natural wetland
before passing under the Ontrack rail line and then
discharges to Harbor Brook.
The discharge of untreated sewage through combined
sewer overflows to Harbor Brook contributes to
conditions where the bacterial levels in Onondaga Lake
exceed the coliform standards set in 6 NYCRR Part
703.4. However, computer modeling has been used to
demonstrate that the disinfection of all CSOs is not
required to achieve water quality standards for
bacteria in those portions of Onondaga Lake designated
as Class B. See Appendix B for a summary of the
Bacteria Model developed for Onondaga Lake.
Click here for Appendix B. Memorandum: Bacterial model update for Onondaga Lake.
CSOs also contribute to the release of floating solids
in violation of 6 NYCRR Part 703.2. The term floating
solids or floatables is used to describe those
materials that float at or near the water surface, and
can include neutrally buoyant materials that are
carried along within the flow. Besides being unsightly
in the water bodies, floatables may also be a source
of pathogens and biochemical oxygen demand (BOD).
CSO-related pollutants have a negative impact on the
ecology of natural waters and contribute to problems
in other areas of the environment. The nature of
floatable material can vary widely, and can include:
-
Street litter such as plastics, paper and cigarette
butts
-
Natural material such as leaves, branches and twigs
-
Sewage-related material such as condoms, tampons,
toilet paper, fecal matter and other material flushed
down toilets.
The quantity of floatable material that is discharged
can also vary widely depending on the:
-
Degree to which the watershed is littered
-
Number of antecedent dry-weather days during which litter can accumulate
-
Implementation and maintenance of upstream source controls
-
Land use
-
Season
-
Intensity of rainfall
-
Frequency at which best management practices are performed.
Currently there are no numerical regulatory
requirements for the capture of floatable material.
However, the ACJ states:
The County's program shall achieve:
B. elimination or minimization of floating substances
in Onondaga Lake attributed to the County's
CSOs . . . .
The goal for floatables removal is that floatables
from CSOs are to be eliminated for up to and including
a 1-year, 2-hour, design storm through the use of
floatables control technologies where applicable.
However, on occasion, higher intensity and/or duration
storms will cause flow rates that exceed those
generated by the 1-year design storm event. During
such events, lower floatables capture efficiency is
expected.
In an effort to demonstrate compliance with the 85%
capture requirement, the calibrated SWMM models were
executed for the various compliance projects included
in the ACJ. The models were run using a long-term
simulation approach based upon 30 years of
precipitation data for the Syracuse metropolitan area.
For pre-abatement conditions, without implementation
of any CSO abatement projects, the County Sanitary
District trunk and interceptor sewer system transports
74% of the average annual volume of combined sewage
collected within the City of Syracuse collector and
combined sewer system to Metro for treatment. A
summary of this volume capture information is
presented in Table 1 found in Appendix C.
Click here for Appendix C. CSO volume capture table.
For comparison purposes, it is estimated that with the
implementation of CSO projects as of December 2004 the
sewer system transports approximately 81% of the
average annual volume of combined sewage to Metro for
treatment. Upon implementation of all the ACJ CSO
Abatement projects, as described above, the average
annual volume of combined sewage collected within the
combined sewer system for transport to Metro is
projected to be 88%. A summary of this volume capture
information is presented in Table 2 found in Appendix
C. These data indicate that the fully implemented ACJ
CSO compliance projects will satisfy the 85% capture
requirements of the ACJ. The Harbor Brook project
represents the recommended abatement alternative as
developed in this document. Table 3 in Appendix C
presents the CSO volume capture information for the
combined treatment of CSO both at Metro and the
proposed ACJ CSO compliance projects.
A separate
Environmental Information Document (EID)
has been developed as a companion document for the
Harbor Brook CSO Abatement Facilities Plan. In
addition, a Phase I Cultural Resource Survey has been
completed by Hartgen Archeological Associates, Inc. as
a subconsultant to Brown & Caldwell on potential sites
for CSO facilities. This document also serves as a
companion document to the Facilities Plan.
During the compilation of this draft Facilities Plan,
County staff and design engineers met with and gave
presentations to various individuals and groups to
provide information on the purpose and status of the
Facility Plan and to obtain public input on potential
issues and concerns. Individuals included interested
county and city officials, area business people, local
school and church officials and residents of the
City's west side. Meetings were held with Tomorrow's
Neighborhood Today (TNT) Westside Sector, Neighborhood
Watch at Frazier School and representatives of Sacred
Heart Seniors and the Knights of Columbus.
With completion of the Facilities Plan, which provides
the data on the CSO abatement needs and proposes
alternative solutions, the County will continue its
public participation activities to solicit and receive
further input from the community. Public participation
activities will include direct mailings to area
residents, holding availability sessions in the
neighborhoods near Harbor Brook, presentations to
local groups and organizations, public information
meetings, and other activities.
|