Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)
by Brown and Caldwell
for Onondaga County Dept of Water Environment Protection

Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)

Harbor Brook CSO Abatement Project Facility Plan (Aug 2005)

Onondaga County entered into an Amended Consent Judgment (ACJ) in 1998 that requires it to eliminate or capture for treatment at least 85% by volume of the combined sewage collected in the combined sewer system during precipitation events, eliminate or minimize floating substances in Onondaga Lake attributed to the County's CSOs, and achieve water quality standards for bacteria for all portions of Onondaga Lake that are Class B.

The ACJ listed the Harbor Brook In-Water System (HB IWS) as an Interim CSO Project. The purpose of this facilities plan is to compare the HB IWS to alternatives for abatement of CSOs in the Harbor Brook basin, including regional facilities and sewer separation. The comparison is based on engineering and operational considerations, environmental and community effects, and cost-effectiveness.

This report has the following sections:
 Executive summary
 1. Basis for CSO Abatement
 2. Harbor Brook In-Water System
 3. Technology Evaluation
 4. Siting Analysis
 5. Sewer Separation
 6. Alternatives Analysis
 7. Scenarios
 8. Recommended Plan
 9. Project Implementation Schedule
 Appendices

In addition, an Environmental Information Document has been written to address the Harbor Brook project.


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection