|
Clinton CSO Abatement: Environmental Information Document (Nov 2005) Clinton Street CSO Abatement Project (Nov 2005)
Prepared by SGD Environmental Services for Environmental Engineering Associates, LLP
LEAD AGENCY: Onondaga Co. Dept of Water Environment Protection
650 Hiawatha Blvd., W., Syracuse, NY 13204
Contact: Randy R. Ott, PE, Commissioner, 315-435-2260
1. Introduction
The Introduction section of this document is designed
to provide information regarding the Onondaga County
Combined Sewer Overflow (CSO) Lake Improvement Program
and how it relates to the Clinton Street CSO Abatement
Project (background/project description, need and
benefits). The evolution (selection process) of the
Clinton Street CSO Abatement Project is also included.
Lastly, the schedule for completion of selected
project components, regulatory review requirements,
and a summary of permits and/or approvals associated with
the Clinton Street CSO Abatement Project are described
in this section. A list of commonly used terms and
acronyms can be reviewed in Appendix A.
Click here for Appendix A. Commonly used terms and acronyms.
The Onondaga County Sanitary District owns, and the
Onondaga County Department of Water Environment
Protection (OCDWEP) operates and maintains, certain
combined trunk sewers and interceptor sewers within
the City of Syracuse. (Prior to January 2001, Onondaga
County Department of Water Environment Protection was
referred to as Onondaga County Department of Drainage and
Sanitation [OCDDS].)
Transfer of ownership from the
City of Syracuse to Onondaga County was effected by a
joint act of the Syracuse Common Council and the
Onondaga County Legislature once in 1978 and again in
1982. The City of Syracuse continues to own, operate,
and maintain the combined tributary collector sewer
system. During periods of wet weather, this combined
tributary collector sewer system generates a mixture
of storm water and untreated sewage that exceeds the
conveyance and storage capacity of the trunk and
interceptor sewer system resulting in discharges of
this combined flow to Onondaga Creek and eventually
Onondaga Lake.
In January 1989, Onondaga County (County) entered into
a Judgment on Consent with the State of New York and
the Atlantic States Legal Foundation (ASLF) in
settlement of litigation in connection with alleged
violations of state and federal water pollution
control laws. The conditions of the Judgment on
Consent required the County to perform a series of
engineering and scientific studies to evaluate the
need for upgrading the Metropolitan Syracuse
Wastewater Treatment Plant (Metro) and abating CSOs
that occur within that portion of the Metro service
area located within the City of Syracuse and served by
the City's combined collector system.
Based on the results of the required studies, and in
consultation with the New York State Department of
Environmental Conservation (NYSDEC) and the U.S.
Environmental Protection Agency (USEPA), the County
developed a plan for upgrading the Metro plant and
providing abatement of CSOs (long-term control plan).
The County submitted a proposed Municipal Compliance
Plan (MCP) to the NYSDEC and ASLF in January 1996.
Subsequent negotiations with regard to the proposed
MCP resulted in the execution of an Amended Consent Judgment
between the parties, which was executed
by the U.S. District Court in January 1998 (see
Appendix B - Amended Consent Judgment).
Appendix B. Amended Consent Judgment (1998): Email Susan Miller, Project Deputy Director or phone 315-435-2260 for copy.
The 1998 ACJ replaced and superseded the 1989 Judgment
on Consent including the requirement for an approved
MCP and Effluent Compliance Schedule. Pursuant to the
ACJ (1998), the County is required to implement a
collection of projects that focus on improving the
water quality of Onondaga Lake including the following
programmatic elements:
-
Upgrades and improvements at Metro (interim and major)
-
Interim and major improvements concentrating on abating CSOs in the Metro service area
-
An oxygenation demonstration project
-
An ambient water quality monitoring project.
(The ACJ settlement divided improvements into two
groups: interim - to be completed by 7/1/02 [except
for sewer separation); major - completion dates
established by project [OCDDS LIPO 2001a). The
Clinton Street CSO Abatement Project is considered a
"major" project [Section 1.4 -
Schedule
identifies project component completion dates].)
With regard to improvements to the combined sewer
system, paragraph 14 of the ACJ states the following:
The County shall design, construct, maintain, and
modify and/or supplement, as necessary, a CSO control
and upgrade program in accordance with DEC CSO
guidance, as set forth in TOGS 1.6.3 (CSO Control
Strategy), which implements the "presumptive approach"
in EPA's CSO control policy, as set forth in 59 F.R.
18688 (April 18, 1994). The County's program shall
achieve the following:
- elimination or the capture for treatment of no less
than 85% by volume of the combined sewage collected in
the combined sewer system during precipitation events on a system-wide annual average basis,
- elimination or minimization of floating substances
in Onondaga Lake attributed to the County's CSOs,
and
- achievement of water quality standards for bacteria
for all portions of Onondaga Lake that are classified
as 'Class B' (As defined in Title 6 of the New York State
Compilation of Codes, Rules and Regulations [6 NYCRR]
Part 701, the best usages of Class B waters are
fishing and secondary contact recreation [e.g.
boating]. The waters shall be suitable for fish
propagation and survival.) pursuant to 6 NYCRR Part 895"[6 NYCRR
895, Onondaga Lake Drainage Basin].
To achieve compliance with the above requirements, the
County shall complete the specific tasks by the
applicable milestone compliance date set forth in the
CSO Control and Upgrade Schedule that is attached as
Appendix B and hereby made an enforceable part of this
Amended Consent Judgment. All elements of the CSO
Control and Upgrade program shall be completed and in
full operation on or before January 1, 2012.
As previously noted, the Clinton Street CSO Abatement
Project is one component of the Lake Improvement
Program. Other CSO projects associated with the ACJ,
and addressed elsewhere by others, include the
following (OCDDS LIPO 2001a):
Interim phase projects:
- Hiawatha Boulevard Regional Treatment Facility (RTF)
Demonstration
- Newell Street RTF Disinfection Demonstration
- Harbor Brook In-Water System
- Erie Boulevard Storage System Upgrade
- Kirkpatrick Street Pumping Station Upgrade
- Onondaga Creek Floatables Control
- Harbor Brook Floatables Control Facility (FCF)
- Teall Brook FCF
- Siphon Crossings Evaluation and Rehabilitation
- CSO Toxicity Evaluation
Major projects:
- Midland RTF and Conveyances
- Franklin FCF
- Maltbie FCF
- Sewer Separation
The ACJ stipulates that the Clinton Street CSO
Abatement Project "will abate those CSO discharges
located within the downtown portion of the Onondaga
Creek basin." This area represents the Clinton Street
CSO Abatement Project service area (see Figure 1-1)
and is the second largest service area in the County's
combined sewer system (approximately 1000 acres) (EEA
2005).
|
|
Figure 1-1. Clinton Street combined sewer service area
|
As listed in Table 1-1, there are eleven
NYSDEC-permitted CSOs within the Clinton Street CSO
service area.
| TABLE 1-1. CLINTON STREET COMBINED SEWER SERVICE AREA OVERFLOWS |
|
No.
|
ID
|
Drainage in acres
|
Location
|
|
1
|
027
|
134
|
West Fayette Street - East
|
|
2
|
028
|
24
|
Walton Street - West
|
|
3
|
029
|
8
|
Walton Street - East
|
|
4
|
030
|
312
|
West Jefferson Street - East
|
|
5
|
031
|
25
|
West Jefferson Street - West
|
|
6
|
032
|
25
|
Tully Street - West
|
|
7
|
033
|
18
|
Dickerson Street - West
|
|
8
|
034
|
214
|
Gifford Street - East
|
|
9
|
035
|
23
|
Gifford Street - West
|
|
10
|
036
|
188
|
West Onondaga Street - West
|
|
11
|
037
|
33
|
West East Adams Street - East
|
|
|
|
Total 1004
|
|
|
Source: EEA 2005, 2003b
|
A map depicting the location of these overflows within the Clinton Street CSO service area is presented on Figure 1-2.
To assist in meeting ACJ requirements, the Clinton
Street CSO Abatement Facilities Plan prepared by
Environmental Engineering Associates, LLC (EEA)
identifies that the proposed Clinton Street CSO
Abatement Project will involve the conveyance,
storage, and high-rate treatment of overflows at a
Clinton Street Regional Treatment Facility (RTF) prior
to discharge to Onondaga Creek. (Overflows from
existing CSOs 027 through 037 up to the 1-year 2-hour
duration, 15-minute rainfall interval design storm
event [1-yr design storm event].)
Incorporated herein by
reference, the Facilities Plan identifies the minimum
CSO abatement requirements for the Clinton Street CSO
Abatement Project as follows:
-
Eliminate or capture for treatment at Metro at least 107 million gallons (MG) of combined sewage on an average annual basis,
-
Provide adequate facilities to eliminate or minimize floating substances (floatables) from discharging to Onondaga Creek from the Clinton Street service area CSOs,
-
In combination with other CSO abatement projects, provide sufficient facilities to reduce bacterial concentrations to less than 200 colony forming units (cfu)/100 milliliters (ml) for the Clinton Street service area CSO discharges for the 1-year
design storm event, and
-
Satisfy the additional requirements outlined in pages 7 and 8 of ACJ-Appendix B (herein see Appendix B - Amended Consent Judgment).
Implementation of the Clinton Street CSO Abatement Project and achievement of the above noted treatment requirements will assist in complying with ACJ requirements and will provide significant water quality benefits as part of the County's overall
CSO control and upgrade program (EEA 2005).
In February 2000, facilities planning efforts were
initiated to identify the recommended/preferred
alternative (siting and treatment technology) for the
Clinton Street CSO Abatement Project. In February
2005, the Clinton Street CSO Abatement Project Facility Plan (Feb 2005 draft) (EEA 2005) summarized an assessment
undertaken by EEA to identify viable CSO treatment
technologies and potential RTF locations for the
project. The facilities planning process took into
consideration the ACJ requirements (summarized above),
design criteria associated with such requirements, and
the concerns expressed by the service area community.
To date, more than 30 public meetings involving
potentially affected community groups/organizations
and businesses have been conducted (see
Section 9,
Community and public participation).
As described in greater detail in
Section 7,
Alternatives, a variety of CSO treatment approaches,
technologies, and RTF locations were preliminarily
identified:
Treatment approaches:
- Sewer separation
- Regional conveyance and storage
- Regional conveyance and treatment (with disinfection)
Treatment technologies:
- Vortex separators
- Enhanced vortex separators
- Continuous deflective separation (CDS)
- Ballasted flocculation
- Coarse screening (mechanically cleaned)
- Fine screening
- Brush screens
- Rotary drum screens/sieves
- Microscreens
- Net bags
- Overflow retention facility (ORF)
Regional treatment facility locations:
- Clinton Station
- Tully Street
- West Onondaga Street
- West Washington Street
- Wyoming Street
- Gifford Street
- Dickerson Street (East and West alternatives)
Based upon screening evaluations identified in the
Facilities Plan, the most feasible CSO treatment
technology/approaches for achieving compliance with
the Clinton Street CSO service area ACJ treatment
requirements were:
Sewer separation
consists of the installation of new separate sanitary sewer and building connections to collect only the sanitary waste. The sanitary waste connections are eliminated from the existing combined sewer to convert it to a storm
sewer (EEA 2005). See Figures 1-3 and 1-4.
|
|
Figure 1-3. Sewer separation (combined sewer shown)
|
|
|
Figure 1-4. Sewer separation (separate sewers shown)
|
|
|
Figure 1-5. Vortex separator schematics
|
Regional conveyance and storage
includes the installation of conveyance piping to
collect and divert overflows to a central or regional
storage site. The CSO volume generated during a
wet-weather event would be stored in a regional
storage facility. Following the wet-weather event, the
stored CSO volume would be discharged to a municipal
treatment plant for at least primary treatment prior
to discharge. Storage is divided into either "in-line"
or "off-line" storage. In-line storage utilizes
conveyance capacity for storage whereas off-line
storage utilizes tankage for storage (EEA 2005).
Regional conveyance, in-line storage and treatment (with disinfection) using vortex separators or ORF
-
Vortex separator is designed to cause the incoming
wastewater to flow in a circular motion creating what
is called a vortex which forces the solids within the
wastewater downward to a discharge pipe that directs
the concentrated material back to the existing
interceptor sewer. The lighter or floatable materials
are captured by a baffle at the top of the vortex unit
and are also directed back to the interceptor sewer by
a force main. The treated wastewater flow is
discharged to a high rate disinfection chamber where a
chlorine bleach solution is applied to kill the
bacteria. Before the disinfected wastewater is
discharged to the Creek, the treated wastewater is
dechlorinated (EEA 2005). See Figure 1-5.
|
|
Figure 1-6. Typical overflow retention facility (ORF)plan view without disinfection
|
-
Overflow retention facility - the ORF consists of
a large tank where wastewater is stored and the solids
are allowed to settle to the bottom before the treated
wastewater is discharged from the facility. Similar
disinfection and dechlorination facilities, as
described for the vortex separators, are used to kill
the bacteria (EEA 2005). See Figure 1-6.
Utilizing non-cost criteria (e.g., proximity to
residents, businesses, and sensitive receptors,
community enhancements, engineering considerations,
and ACJ compliance, etc.), two preferential sites for
the Clinton Street CSO abatement facilities were
identified: Clinton Station (Trolley Lot) and
Dickerson Street (EEA 2005, Section 3, Alternative
Site Analysis).
Figure 1-7 depicts preliminary conveyances and in-line storage/vortex separator RTF at Clinton site (CSO 037 inc)
In February 2005, following review of project-specific
plans, reports, and memorandums, as well as input from
the City of Syracuse and potentially affected
community groups (residential and business), a
recommended/preferred alternative for the Clinton
Street CSO Abatement Project (siting and technology)
was identified by the County. As reflected in the
Facilities Plan (EEA 2005), it was identified
that the Clinton Street CSO Abatement Project would
involve the construction and operation of an RTF at
Clinton Station (Trolley Lot) using in-line
storage/vortex separators and closure of existing CSOs
028 and 029.
Figure 1-8 shows an aerial view of the Clinton Station RTF and conveyances
The existing system currently stores approximately 74%
of the total average annual wet weather flow. The
Clinton CSO Abatement Project will store an additional
12% of the total average annual wet weather flow
within the service area for treatment at Metro with
remaining peak wet weather flows representing 14%
being treated (removal of solids, disinfection,
dechlorination) onsite and discharged to Onondaga
Creek (18 times on an average annual basis). This
represents approximately 118 MG of treated CSO being
discharged to Onondaga Creek.
Figure 1-9 provides a draft schematic of the building
In general, the RTF and conveyances are proposed as follows:
| Table 1-2 General Design Features |
|
Building
|
|
- Site acreage: 2 acres (Note: Clinton Station parking lot is 5 acres but only 2 acres is needed for construction)
|
|
- Height: 1.5 stories or approximately 25 feet with a 10-foot stack
|
|
- Size: 35,000-40,000 square feet
|
|
- Storage capacity of RTF and conveyance: 3.7 million gallons (MG)
|
|
- Figure 1-9 provides a draft schematic of the RTF.
|
|
Disinfection facilities
|
|
- Disinfection tank use: estimated 31 times per year (an estimated 13 events will be captured and returned for treatment at Metro and an estimated 18 events will be disinfected and discharged to the Creek).
|
|
- Disinfection tank entirely underground
|
|
- Disinfection tank outfall: 120-inch diameter (emergency controlled diversion spillway has not been designed at this time).
|
|
- Size: approximately 16,000 square feet
|
|
- Pipe depth: 15 - 20 feet below grade
|
|
- Chemical tank sizes: liquid sodium hypochlorite = 6200 gallons; liquid sodium metabisulfite = 2100 gallons (tanks located inside building)
|
|
Conveyances
|
|
- Total estimated length: 6,000 linear feet of conveyance, force main, and outfall piping
|
|
- Easements: 30 - 75 feet temporary; permanent easement 30 feet
|
|
- Pipe depth: 12 - 40 feet
|
|
- RTF influent conveyance diameter: 27 - 108 inch
|
|
Construction
|
|
- Anticipated construction period: 3 - 3.5 years:
|
|
- Phase 1 conveyances (Fayette to West Jefferson): 6 - 9 months
|
|
- Phase 2 RTF and remaining conveyances: 2.5 - 3 years
|
|
- Construction conveyance easement: 30 - 75 foot width maximum
|
|
- Depth of disturbance: 10 to 50 feet maximum (influent sump/wet well)
|
|
- Estimated area of disturbance: 5.5 acres:
|
|
- RTF: 2 acres
|
|
- Piping: 3.5 acres
|
|
- Green design and construction techniques will be utilized to the extent practicable
|
|
Operation
|
|
Intermittent (only during wet weather conditions): estimated 49 overflow events going to RTF per year:
|
|
- 31 events will be captured and returned for treatment at Metro:
|
|
- 18 events will be stored in conveyances and non-disinfection tank portion of RTF.
|
|
- 13 events will be stored in the conveyances and RTF including the disinfection tank.
|
|
- 18 events will require treatment at the RTF and will be discharged following dechlorination to Onondaga Creek. This represents approximately 118 MG of treated CSO being discharged to Onondaga Creek.
|
|
Sources: EEA 2005 and 2003a
|
The regional treatment facility using vortex
separation with high rate disinfection acts as a
storage facility for smaller storms while providing
treatment for larger storms. The storage capacity of
the RTF and conveyances is estimated at 3.7 MG. As
previously noted, approximately 49 overflow events per
year will be captured and stored within the
disinfection facilities. An estimated 31 events will
be captured and pumped back to the main interceptor
sewer for conveyance to Metro for treatment. An
estimated 18 overflow events per year will result in
discharges of treated/disinfected effluent to Onondaga
Creek. The recommended/preferred alternative
identified by the County, therefore, maximizes the
flow to Metro while providing cost-effective treatment
of larger storms. Others will address detailed
engineering aspects of the project in yet-to-be
developed design reports. This document focuses on the
natural and human environmental setting, potential
impacts, and mitigation measures associated with
implementation of the above facilities (see Figures
1-7 and 1-8).
The following (Table 1-3) is a summary of the current
ACJ construction milestone dates related to the
Clinton Street CSO Abatement Project.
| Table 1-3 ACJ Compliance Milestone Schedule |
|
No.
|
Project component
|
Milestone
|
Current milestone date
|
|
1
|
Commence construction of conveyances
|
Minor
|
Oct 28, 2004
|
|
2
|
Commence construction of RTF
|
Minor
|
Oct 28, 2004
|
|
3
|
Complete construction of conveyances
|
Minor
|
May 1, 2007
|
|
4
|
Complete construction of RTF
|
Major
|
Jan 1, 2012
|
|
Source: EEA 2005
|
The County is currently in negotiations with the ACJ
parties regarding revisions to milestone dates for
several ACJ projects, including the Clinton Street CSO
Abatement Project (Clare 2005).
The State Environmental Quality Review Act (SEQR) and
its implementing regulations (6 NYCRR Part 617) require
the consideration of environmental factors in certain
actions that are directly undertaken, funded, or
approved by local, regional, or state agencies. In
accordance with 6 NYCRR Part 617, subject actions are
classified as either "Type I" actions or "Unlisted"
actions. Actions specified by SEQR as "Type II"
actions are not subject to SEQR review.
With respect to the Clinton Street CSO Abatement
Project, Onondaga County plans to undertake the
proposed project. Given that the action is the direct
result of an amended consent order, the project is
classified by SEQR as a Type II action under 6 NYCRR
617.5(c)(29):
civil or criminal enforcement proceedings, whether administrative or judicial, including a particular course of action specifically required to be undertaken pursuant to a judgment or order, or the exercise of prosecutorial discretion
In accordance with SEQR, such a classification would
negate the SEQR environmental review process for the
project. However, in 1998 the NYSDEC required that the
Clinton Street CSO Abatement Project (as well as other
selected ACJ projects) undergo the SEQR review process
as a Type I action. Although by regulation, the
project would be classified as a Type II action
because it is a product of enforcement, the Clinton
Street CSO Abatement Project is being analyzed as if
it were a Type I action.
In accordance with 6 NYCRR Part 617(a)(2) for Type I
actions, a full Environmental Assessment Form (fEAF)
must be used to evaluate the significance of the
action. The fEAF must contain enough information to
describe the proposed action, its location, its
purpose and its potential impacts on the environment
so that the environmental significance or
nonsignificance of the proposed action can be
identified. The fEAF consists of three parts:
Part 1
of the EAF is a form designed to assist in determining whether the action proposed may have a significant effect on the environment.
Part 2
of the EAF is a form that provides information regarding the magnitude of impacts that can be expected from a proposed project. The magnitude of the impact is classified as either a "small to moderate impact" or as a "potential large
impact" for both natural and human resources.
Part 3
of the EAF is to be developed when potentially large impacts have been identified during Part 2 but can be minimized through the implementation of mitigation measures. Part 3 includes the defined mitigation measures.
A Lead Agency must be designated to coordinate the
environmental review process and assure compliance
with the procedural requirements of SEQR when two or
more agencies are involved in a review of a Type I
action.
(Involved agency
means a state or local agency that has jurisdiction by
law to fund, approve or directly undertake an action.
If an agency will ultimately make a discretionary
decision to fund, approve or undertake an action, then
it is an "involved agency" notwithstanding that it has
not received an application for funding or approval at
the time the SEAR process is commenced [6 NYCRR Part
617].)
The involved/interested agencies for this
action due to their actual and/or potential direct
involvement (as described in Section 1.6 below)
consist of:
- Onondaga County
- Office of Parks, Recreation, and Historic
Preservation (OPRHP)
- City of Syracuse
- Onondaga County Industrial Development Agency
(OCIDA)
- United States Army Corps of Engineers (USACOE)
- NYS Environmental Facilities Corporation (NYSEFC)
- NYS Department of Transportation (NYSDOT)
- NYSDEC
- USEPA
(An
interested agency
is an agency that lacks the jurisdiction to fund,
approve or directly undertake an action but wishes to
participate in the review process because of its
specific expertise of concern about the proposed
action. An "interested agency" has the same ability to
participate in the review process as a member of the
public [6 NYCRR Part 617].)
In March 2005, Onondaga County submitted a Lead Agency
designation letter to provide notice of the County's
desire to serve as Lead Agency. In addition, the
following documents were provided:
-
Parts 1 and 2 of the fEAF (forms) prepared by the County under separate cover.
-
The Clinton Street CSO Abatement Project EID represents Part 3 of the fEAF.
Following submittal of the Lead Agency designation
letter, a possible Lead Agency dispute arose "based on
the City's failure to specifically concur with the
County's proposal to serve as lead agency following
the County's March 2005 coordination letter." In July
2005, the NYSDEC "agreed that the County should serve
as lead" (NYSDEC 2005).
Following coordinated environmental review of SEQR
documents, the County as Lead Agency will make a
formal determination of environmental nonsignificance
(negative declaration) or environmental significance
(positive declaration). The filing of a negative
declaration by the County will conclude the SEQR
review process wherein the filing of a positive
declaration requires the preparation of an
Environmental Impact Statement (EIS) (draft and final)
and a statement of findings. Should it be concluded
that a positive declaration be filed in connection
with the Clinton Street CSO Abatement Project, it is
the intent of the County that this document also serve
as the draft Environmental Impact Statement (dEIS).
The implementation of the Clinton Street CSO Abatement
Project will require a series of reviews and
approvals, as well as obtaining various permits from
regulatory agencies (federal, state, and local). Table
1-4 summarizes the various reviews, approvals, and
permits anticipated for the Clinton Street CSO
Abatement Project (both construction and operational).
| Table 1-4 Anticipated Approvals/Permits |
|
Type (citation)
|
Governing agency(ies)
|
Activity covered
|
Comment
|
|
SEQR: Description of SEQR activities is in Section 1.5.
|
Lead Agency & involved/interested agencies
|
NYS env review
|
This document is Part 3 of fEAF. Co. seeks to be Lead Agency. Involved agencies have approval authority/ jurisdiction.
|
|
Co. approvals (various)
|
Onondaga Co.
|
Funding, Lead Agency designation**, final determination.
|
Inc. Capital Improvement Prog, Annual Capital Budget, Commissioner's Hearing, Co. Executive Approval, Co. Health Dept Approval, Legislative Approval
|
|
Federal & State Historic Preservation Laws (9 NYCRR 428 & 36 CFR 800)
|
Office of Parks, Recreation, & Historic Preservation (OPRHP) & Onondaga Nation
|
Archeological sensitivity assessment review (Phase 1A & Phase 1B)
|
See Sections 3.5 & 5.5
|
|
City permits***
|
City of Syracuse
|
Permanent easements & road cut permits for sewers in City streets
|
|
|
Railroad crossing permit/easement
|
OCIDA & New York Susquehanna & Western
|
Installation of conveyances under/adjacent to railroad tracks
|
OCIDA easement also needed to install conveyances on OCIDA property
|
|
Federal stream crossing & excavation or fill of navigable waters permit (§10 Rivers & Harbors Act/§404 of Clean Water Act)
|
USACOE
|
Navigable waters/waters of U.S.
|
Same permit as required by state but undergoes independent federal review
|
|
Revolving Loan Fund
|
NYSEFC
|
Project funding of reimbursable work items
|
|
|
Road crossing
|
NYSDOT
|
Work within a state roadway
|
A small portion of the conveyance will be in right-of-way of West Street (a NYSDOT roadway).
|
|
Excavation/fill of navigable waters (6 NYCRR 608.5)
|
NYSDEC
|
Excavation/fill of waterway during stream crossing
|
Stream classification of Creek in project area is "C": suitable for fishing (6 NYCRR 701, 895). Therefore 6 NYCRR 608.5 permit
|
required.
|
State Pollutant Discharge Elimination System (SPDES) permit (6 NYCRR 750-757)
|
NYSDEC
|
Construction activity storm water permit & discharge permit for treated effluent
|
|
|
Bulk chemical storage permit (6 NYCRR 595-599)
|
NYSDEC
|
Tank permits for treatment chemicals
|
|
|
Air facility registration
|
NYSDEC
|
Odor control units
|
Confirmation will be based on final design
|
|
Facilities Plan, Eng. Design Report, & Const. documents
|
NYSDEC
|
Design & build
|
|
|
Note: Should the County receive federal funding for the project, review & approval of the project by the USEPA under NEPA will be required.
|
*** Source: Macry (2002), Wallace (2002), & Esposito (2002)
|