Clinton Street CSO Abatement Project Facility Plan (Nov 2005)
by Environmental Engineering Associates, LLP for Onondaga County Department of Water Environment Protection
7. Project phasing/implementation schedule
As described in Section 1.7, the following presents
the phasing/implementation schedule for the Clinton
Street CSO abatement facilities.
|
Milestone
|
Date
|
|
Commence construction of conveyances
|
Oct 28, 2004
|
|
Commence construction of RTF
|
Oct 28, 2004
|
|
Complete construction of conveyances
|
May 1, 2007
|
|
Complete construction of RTF
|
Jan 1, 2012
|
Onondaga County is currently negotiating with the
parties to the ACJ regarding revisions to milestone
dates for several ACJ projects including the Clinton
Street CSO Abatement Project.
|