Clinton Street CSO Abatement Project Facility Plan (Nov 2005)
by Environmental Engineering Associates, LLP
for Onondaga County Department of Water Environment Protection

7. Project phasing/implementation schedule

As described in Section 1.7, the following presents the phasing/implementation schedule for the Clinton Street CSO abatement facilities.
 
Milestone Date
Commence construction of conveyances Oct 28, 2004
Commence construction of RTF Oct 28, 2004
Complete construction of conveyances May 1, 2007
Complete construction of RTF Jan 1, 2012

Onondaga County is currently negotiating with the parties to the ACJ regarding revisions to milestone dates for several ACJ projects including the Clinton Street CSO Abatement Project.