|
Environmental information document (draft), Clinton Street CSO Abatement Project February 2005
Prepared by SGD Environmental Services for Environmental Engineering Associates, LLP
PROPOSED LEAD AGENCY
Onondaga County, Department of Water Environment Protection
650 Hiawatha Blvd., W., Syracuse, NY 13204
Contact: Richard L. Elander, PE, Commissioner, 315-435-2260
5. Impact evaluation and mitigation measureshuman resources
Based on concerns expressed during public meetings
(see Section 9),
potential impacts to downtown area transportation and
parking resources have emerged as a primary concern
for many local businesses. Given these concerns,
County representatives subcontracted the services of
Sear-Brown (DeWitt, New York) to conduct a traffic
study to:
-
Identify traffic volumes within the select project areas (i.e., road closures)
-
Evaluate the streets to be temporarily closed during construction
-
Propose detour routes to accommodate traffic flow during construction
In addition, the traffic study identified on-street
and off-street parking areas that will likely be
influenced during the installation of the conveyances.
The study was developed in coordination with the
Syracuse City School District, Syracuse Police
Department, Central New York Regional Transportation
Authority (CNYRTA) Centro, Hanford Pharmaceuticals,
Byrne Dairy, the Greater Syracuse Tenants network, the
MOST, and the Clinton Street Mitigation Advisory
Committee
(see Section 9)
(SB 2003). A copy of the study has been included as
Appendix D.
Click here for Appendix D. Detour technical memo: Detour for road closures associated with Clinton Street CSO abatement project.
The following subsections provide a summary of
impacted transportation and parking resources and the
mitigation measures to be initiated by the County (in
cooperation with local entities) to minimize these
impacts to the greatest extent practicable. In
addition, the County will work closely with downtown
representatives [e.g., Armory Square Association,
Syracuse Convention and Visitors Bureau, Clinton
Street Mitigation Advisory Committee
(see Section 9),
etc.], so that public information is kept up to date
and if traffic/parking/pedestrian issues arise, they
are addressed and resolved promptly (i.e., complaint
response program).
The following subsections have been prepared to
address anticipated street closures and detour routes,
as well as construction-related and operation-related
vehicular traffic, associated with the implementation
and operation of the Clinton Street CSO Abatement
Project.
5.1.1.1 Street closures and detour routes
A summary of pertinent street closures and detour
route information as detailed in the traffic study is
presented in Table 5-1. In order to facilitate the
effectiveness of the detour routes identified, various
improvements will be undertaken (SB 2003):
-
Adequate detour signage (especially to avoid traffic from detouring onto private roadways, parking lots and/or driveways)
-
Adjusting signal timing
-
Modifying signal phasing
-
Temporarily allow turns on select streets where it is normally restricted
-
Change lane designations (e.g., convert one-way street to two-way street, utilize more than one lane for turning)
-
Prohibit and/or restrict parking on select streets.
Details regarding the level of service for the
affected areas utilizing the detour routes are
identified in Appendix D.
Click here for Appendix D. Detour technical memo: Detour for road closures associated with Clinton Street CSO abatement project.
TABLE 5-1 TRAFFIC STUDY SUMMARY
Sources: SB 2003, *EEA 2003a Source for figures is Sear-Brown 2003, prepared by SGD Environmental Services
| Fayette Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
East of Onondaga Creek
|
6 weeks
|
Yes
|
Figures 5-1 and 5-2 (two options depicted; final to be identified with input from involved parties)
|
Notes:
- Except for local traffic, it is anticipated that the block from Walton Street to Franklin Street will be closed to through traffic.
- The Walton/Fayette Streets intersection will remain open so that Armory Square traffic can access Walton Street.
- For West Fayette and West Onondaga, construction will be staged such that only one street is closed at a time.
|
|
Figure 5-1. Fayette Street detour route (option 1)
|
|
|
Figure 5-2. Fayette Street detour route (option 2)
|
| Walton Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
East of Onondaga Creek at the Fayette/Walton Street and the Walton Street parking lots
|
8 weeks
|
No
|
Figure 5-3
|
Notes:
- Walton Street will be closed from Fayette Street to Franklin Street, except to local traffic, but will be completely restricted in the area of the Creek.
|
|
Figure 5-3. Walton Street detour route
|
| West Jefferson Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
Street will be completely closed on the west side of the MOST, between the MOST and the railroad tracks
|
16-18 weeks*
|
No
|
Traffic will be detoured to east side of the West Jefferson Street circle.
|
Notes:
- Complete closure will be necessary to relocate existing utilities, construct conveyances, and bore under the railroad tracks. Pedestrian traffic will be allowed through the tunnel during boring activities.
| West Street northbound service road |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
Northbound service road from Fabius St to West St Northbound
|
6-8 weeks (full)*; 20-30 days (partial)
|
No
|
No detour anticipated
|
Notes:
- The service road will remain open during part of the construction and closed temporarily at the point where the service road meets West Street.
| Dickerson Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
West of Onondaga Creek and east of the Rescue Mission Recreation Center
|
6 - 8 weeks
|
No
|
Figure 5-4
|
Notes:
- The Clinton Street northbound service road will remain open during the Dickerson Street closure but closed temporarily during the installation of conveyances along the east side of the Creek.
|
|
Figure 5-4. Dickerson Street detour route
|
| Gifford Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
West of Onondaga Creek and east of the Rescue Mission
|
8 weeks
|
Yes
|
Figure 5-5
|
Notes:
- Gifford Street will be open to local traffic only from Granger Street to closure area. Access from the Clinton Street side will be restricted.
Gifford will be converted to a two-way street to allow access to the Rescue Mission. The Clinton Street service road will remain open during the Gifford Street closure.
|
|
Figure 5-5. Gifford Street detour route
|
| Clinton Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
Clinton Street north of Onondaga/Gifford Streets will be partially closed; no full closure required
|
8 weeks (partial)
|
Yes, but only partial closure needed
|
No detour is proposed since Clinton Street will remain open.
|
Notes:
- The Clinton Street service road will remain open during the Clinton Street partial closure.
| West Onondaga Street |
|
Proposed closure
|
Duration (est.)
|
Centro route?
|
Detour route
|
|
West of Onondaga Creek between Seymour and Clinton Streets
|
8 weeks
|
Yes
|
Figure 5-6
|
Notes:
- Concerns regarding truck traffic exiting Oneida Street onto Adams Street are currently being investigated.
- For West Onondaga and West Fayette, construction will be staged such that only one street is closed at a time.
|
|
Figure 5-6. West Onondaga Street detour route
|
Police, fire, emergency officials, and property owners
in the affected areas will be made aware of (in
advance) the schedule of street closures and detour
routes. Construction will be coordinated to minimize
peak holiday season impacts. Notifications will be
published in local newspapers and the County will work
with local media representatives (e.g., radio and
television) to provide information regarding detour
routes and alternate parking areas (especially during
downtown events and Syracuse University events).
For those businesses within construction zones,
impacts to accessing driveways/private parking areas
may occur. Construction will be staged such that
access (including deliveries) to these businesses
remains open (or alternatives available) during
project implementation. Lastly, separate design
meetings with these individual property owners will be
held to specifically address and minimize impacts (SB
2003).
As necessary, the County will coordinate with the City
of Syracuse regarding the Creekwalk project to further
minimize impacts from implementation of both the
project within the relatively same timeframe.
5.1.1.2 Construction-related traffic
During the construction phase of the project, various
construction-related vehicles (e.g., material delivery
trucks, spoil trucks, concrete trucks, backhoes, etc.)
will access and egress from the streets affected by
the installation of the conveyances as well as the
RTF. Selection of Clinton Station will require that
the County reconstruct the Fabius Street bridge for
construction access to Clinton Station (as well as
during operation of the RTF). Such renovation will
limit RTF construction traffic from entering the
Armory Square area.
It is estimated that between 0 and 75 truck trips
daily will be required during the construction period
for removal of spoil material and delivery of select
backfill, concrete and other equipment and materials
(when RTF and conveyance construction are being
performed simultaneously). Truck trips associated with
conveyance and force main construction will range from
0 to 20 trips per day depending upon the sections of
sewer being constructed. A range of 0 to 60 trips per
day are projected for the RTF during the construction
period (Albright 2004).
The contractor will be required to prepare a
Maintenance and Protection of Traffic (MPT) Plan that
provides details regarding:
-
Details regarding the detour routes (see Section 5.1.1.1)
-
Appropriate signage for construction vehicles
-
Utilization of flag persons
-
Use of flares (as appropriate)
-
Utilization of barricades and/or guard rails
-
Use of reflectors and/or lights on trenches left open at night
-
Parking areas for contractor personnel (see Section 5.1.4 below).
During construction, the County will closely monitor
the contractor and their adherence to the MPT plan. In
addition, the County will mandate that the contractor:
-
Coordinate with local officials to identify the most appropriate access routes for construction vehicles to and from the affected streets.
-
Make deliveries of construction material during off-peak hours to the greatest extent practicable.
-
Remove construction-related vehicles when not directly involved with construction to areas of low traffic flow or to an offsite location.
Based on the above mitigation measures, impacts to
local traffic from construction-related vehicles will
be temporary in nature and are not considered
significant.
5.1.1.3 Operation-related traffic
RTF operation and maintenance.
The RTF will typically be serviced with pickup trucks
or small utility vehicles. After a wet weather event,
several staff would be dispatched to wash down the
facility. The bar racks and grit sump will be cleaned
periodically as needed. Covered dump trucks would
transport the debris to a permitted offsite landfill.
Small tanker trucks would be utilized for chemical
deliveries. Loading and unloading of the trucks would
be performed within the building with the overhead
doors closed. The frequency of deliveries and
maintenance will be dictated primarily by the
occurrence of a wet weather event large enough to
cause CSO to be diverted to the RTF. It is estimated
that up to four vehicles (pickup trucks, panel trucks,
dump trucks, and sewer jet-vac trucks) per event would
travel to the RTF (CDM/C&S 2003).
Operation and maintenance-related traffic would
primarily utilize the Fabius Street entrance proposed
for repair as part of this project, thereby minimizing
traffic through the Armory Square area. Given that
vehicular traffic and facility operations will blend
with existing traffic in the downtown Armory Square
area, no significant impacts from operation and/or
maintenance of the RTF are expected.
Conveyances operation and maintenance.
The County will need to periodically inspect the
conveyances and the CSO diversion chambers. This is
likely to be performed annually or on an as-needed
basis, for example to verify a report of a dry weather
overflow or investigate a complaint. Inspections can
be planned around periods of lower traffic volume for
the diversion chambers, while complaints or
emergencies would have to be addressed immediately for
the sake of public health and safety (Albright 2003a).
For the purposes of this document, mass transit
consists of Centro bus traffic, City of Syracuse
School District traffic, and train traffic.
5.1.2.1 Centro bus routes
As illustrated in Table 5-1, the traffic study
identified that Centro utilizes various streets within
the project area. Based on this study, the majority of
the street closures will not directly impact Centro
(SB 2003):
-
Walton Street
-
West Jefferson Street
-
West Street northbound service road
-
Dickerson Street
-
South Clinton Street
It is proposed that the bus routes along Gifford
Street and West Onondaga Street (two routes affected
by street closures) follow the detour routes outlined
above in Section 5.1.1 to minimize impacts. Alternate
routes to Fayette Street during the construction phase
of the project involve the temporary removal of
parking from various portions of Walton and Franklin
Streets. Alternative detours for the Centro buses
utilizing this route are being investigated by Centro
(SB 2003). The County will work with Centro
representatives to minimize construction-related
impacts.
5.1.2.2 City of Syracuse School District
As described in
Section 3.1.2.1,
the City School District utilizes the Centro bus
system for transporting children to and from City
schools. As such, those routes along Fayette, Gifford,
and West Onondaga Streets, will be rerouted during the
construction phase of the project (see above).
5.1.2.3 Rail services (OnTrack)
The County will work closely with OCIDA and NYS&W to
obtain the necessary permits and easement to work
within the railroad right-of-way as well as to bore
under the tracks in the West Jefferson Street area.
Discussions will include the identification of
measures to be employed during boring activities to
address the railroad's concern regarding access and
parking (particularly during sporting events) (see
Section 5.1.4 below). No impacts to the rail service
are expected as construction and operation of the RTF
and conveyances will not involve track closure.
Sidewalks and paths exist throughout the project area.
During the construction phase of the project,
pedestrian access to sidewalks and, therefore,
businesses will be temporarily rerouted as needed.
However, access to existing businesses will be
maintained during construction through adherence to
the following activities, as applicable:
-
Temporary pedestrian bridges will be used during excavation that requires street closures.
-
Signs will be provided throughout the affected areas to guide patrons to businesses.
-
A review of pavement markings and crosswalks will be conducted to ensure well-marked pedestrian facilities during construction. The County will provide hatched crosswalks to improve visibility during construction.
-
Covered walkways with plexiglas-type windows will be utilized to protect pedestrians while allowing pedestrians to observe construction activities.
-
Separate design meetings with these affected property owners will be held to specifically address concerns and minimize impacts.
Currently only the northbound service road of West
Street has a sidewalk to allow pedestrian traffic from
the Fabius Street area to Walton Street. As such, a
pedestrian access route along West Street to enable
pedestrian traffic to Walton Street will be designed
during construction. Collectively, given the above
mitigation measures, pedestrian traffic will continue
to be able to access the downtown area within the
project area.
The traffic study prepared by Sear-Brown (2003)
identified the on-street parking and off-street
parking lots to be impacted during construction of the
conveyances. The siting of the RTF at Clinton Station
will impact available parking at the parcel itself
since the site is currently a 700-space parking lot.
Table 5-2 provides a summary of the parking areas
expected to be impacted as a result of the
construction and operation of the Clinton Street CSO
Abatement Project (RTF and conveyances).
TABLE 5-2 ANTICIPATED PARKING CLOSURES
Sources: SB 2003, *EEA 2003a See Figure 5-7 for project area
|
Project area
|
On-street parking
|
Off-street parking
|
|
RTF site (Trolly Lot)
|
NA
|
No impact to 245 spaces (est.), temporary closure of estimated 185 spaces (during construction only), and the permanent closure of 270 spaces (northwest portion of Clinton Station parking lot).
|
Notes and mitigation measures:
- A separate detailed parking resources development plan will be prepared (see Section 5.1.4.2) to mitigate the permanent loss of an estimated 270 parking spaces (430 estimated spaces would remain available in the
Clinton Station parking lot following construction activities).
|
Project area
|
On-street parking
|
Off-street parking
|
|
Fayette Street
|
4-6 metered temporarily closed
|
Temporary partial closure of Mill Pond Landing 80-car surface parking lot.
|
Notes and mitigation measures:
- As previously noted in Section 5.1.1, two options exist for the Fayette Street detour.
- Depending on option selected, temporarily parking from one side of Walton and both sides of Franklin Street between Fayette and Walton will be closed. Centro is reportedly evaluating detours for the Centro buses.
- The extent of any partial closure will be identified during design. Separate design meetings will be held with the affected owners to specifically address/minimize impacts.
|
Project area
|
On-street parking
|
Off-street parking
|
|
Walton Street
|
4-6 metered temporarily closed
|
Temporary partial closure of Mill Pond Landing 80-car surface parking lot. Temporary partial closure of the Walton/Jefferson (Butler) 75-car surface parking lot.
|
Notes and mitigation measures:
See comment for Fayette Street options and associated on-street parking impacts.
During the Clinton Street CSO Abatement Project, the two lots will not be partially closed at the same time.
The extent of any partial closure will be identified during design. Separate design meetings will be held with the affected owners to specifically address/minimize impacts.
|
Project area
|
On-street parking
|
Off-street parking
|
|
West Jefferson Street
|
Parking on west side of MOST circle
|
Temporary partial closure of the Walton/Jefferson 75-car lot (Butler lot). MOST back entrances may be impacted.
|
Notes and mitigation measures:
The extent of any partial closure will be identified during design.
Separate design meetings will be held with the affected owners to specifically address/minimize impacts.
|
Project area
|
On-street parking
|
Off-street parking
|
|
West Street northbound service road
|
Parking along service road temporarily closed
|
None
|
Notes and mitigation measures:
|
Project area
|
On-street parking
|
Off-street parking
|
|
Dickerson Street
|
None
|
None
|
|
Gifford Street
|
20-25 parking spaces along road (both sides) will be temporarily closed
|
None
|
Notes and mitigation measures:
Alternate parking arrangements will be coordinated with the Rescue Mission.
|
Project area
|
On-street parking
|
Off-street parking
|
|
Clinton
|
Small parking lots under & adjacent to conveyances at Clinton may warrant closure during const. Given nearness of lots to Clinton Station, need for alternate parking will be identified during prep of parking resources dev plan.
|
-
|
Notes and mitigation measures:
|
Project area
|
On-street parking
|
Off-street parking
|
|
West Onondaga Street
|
None
|
None
|
Notes and mitigation measures:
Figure 5-7 shows the parking lots that will be affected. See Table 5-2, above.
5.1.4.1 Conveyance impacts and mitigation measures
No permanent parking replacement will be required as a
result of installing the conveyances. Parking patterns
will, however, be temporarily altered during the
construction of the conveyances. Table 5-2 identifies
measures to be undertaken by the County to minimize
the temporary loss of parking as the installation of
the conveyance progresses along the affected streets.
In addition, the following general measures will be
initiated:
-
The County will develop temporary alternative parking plans with adequate signage and notification to business owners and the general public. Notifications such as press releases, webpage listing (e.g., Armory Square's webpage), and direct
mailings may be used. Signage will differentiate between weekday and weekend/weekday evening parking locations.
-
To maximize parking available to downtown patrons, contractors will be required to park outside the Armory Square area.
-
The County will request that the City review Clinton Street operations and possibly add parking along the five-lane section of the street during construction.
-
To encourage travel into the area during construction, the County will discuss with the City waiving of parking meter fees (with parking time limits).
It should be noted that a parking availability
assessment conducted by the City identified that
sufficient vacant parking spaces currently exist
within the Armory Square area. In May 2002, the City
of Syracuse collected parking data in the Armory
Square area to evaluate potential parking impacts
associated with the development of the proposed
Creekwalk. In summary, the City assessment identified
that vacant spaces during peak parking demand are
available (i.e., noon on weekdays and from 8pm to 12am
on weekends). Specifically, the assessment estimated
that in the Armory Square area 688 vacant spaces are
currently available during the weekday and 965 vacant
spaces are currently available for parking on the
weekend (Rauber 2002). As such, the findings of the
assessment demonstrate that parking will be available
in the immediate Armory Square area during the partial
closures of the above parking lots and the metered
parking spaces.
The 2002 City assessment described above also
identified the permanent loss of 95 parking spaces due
to the construction of the Creekwalk (Rauber 2002); no
permanent parking will be lost due to the Clinton
Street CSO Abatement Project conveyances. Given that
95 spaces will be lost due to the Creekwalk, weekday
vacancy of up to 593 weekday parking spaces (870
spaces weekend) will be available in the Armory Square
area following Creekwalk construction. Based on this
information, sufficient Armory Square area off-street
parking will be available (weekdays and weekends)
during the construction of the conveyances. Mitigation
measures associated with Clinton Station are discussed
below. Therefore, with mitigation, construction of the
Clinton Street CSO project will not have an adverse
impact on the available parking resources in the
surrounding area. Measures that could be considered to
enhance available parking resources and implemented in
conjunction with Clinton Station are discussed below.
5.1.4.2 Clinton Station parking enhancement measures
Construction of the RTF at Clinton Station will affect
an estimated 455 parking spaces within the lot (185
temporarily and 270 permanently, estimated). The City
parking availability assessment identified that 688
weekday and 965 weekend vacant parking spaces are
currently available (following Creekwalk construction
an estimated 593 weekday and 870 weekend vacant
parking spaces will be available). These figures
demonstrate that sufficient parking will exist during
the construction phase of the RTF (as well as
following construction of the Creekwalk). The County
supports the need for an adequate parking inventory
within the downtown central business district in order
to maintain existing businesses as well as attract new
business. As of the writing of this document, specific
details regarding measures designed to develop/enhance
alternate parking during construction and operation of
the RTF had not been finalized. Alternatives discussed
during Mitigation Advisory Meetings and among County
representatives, but not officially endorsed by the
County at this time, include:
Construction phase parking alternatives under consideration :
- Subsidize current patrons of the Clinton Station parking lot who volunteer to relinquish their parking spaces.
- County purchase of available parking passes at other existing garage and sell them at subsidized rates to Clinton Station parking lot patrons.
- Develop a new temporary parking lot.
- Provide a direct subsidy to the City that would be applied by the City to reduce monthly rates to accommodate lost parking spaces within a City-owned parking lot/garage.
Post-construction parking alternatives under consideration:
- Following construction of the RTF, allow parking at the Clinton Station parking lot outside the immediate area of the RTF. It is estimated this parking area would provide 430 spaces.
- Construct a parking deck within the Clinton Station parking lot.
- Develop one or more new surface parking lots.
- Provide parking mitigation funds to assist
existing parking projects such as the parking garages
proposed for Excellus and HaRTFord (see Section 3.2.2.4).
- Mitigation measures will focus on cost-effective enhancement.
For this project, the County seeks to work
cooperatively with organizations such as the City of
Syracuse, the Downtown Committee, the Armory Square
Association, and Syracuse 20/20 to develop and
implement a parking resource development program that
will mitigate adverse parking disruptions.
An urbanized setting of commercial, retail, and light
industrial, with recreational and residential land
uses, typify the project area
(see Section 3.2.1).
As such, it is the County's opinion that the proposed
CSO facilities and conveyance pipes are compatible
uses with the existing land uses within the project
area. The project is a public works project intended
to protect the health and welfare of the public and to
improve the water quality of Onondaga Creek that flows
through the project area and to Onondaga Lake. As
such, even were it to be determined that the project
was not compatible with the project area, the public
need and benefits to be gained from the project
immunize the project from any local zoning
restrictions that might be construed as inconsistent
with project implementation.
The character of the proposed RTF is benign in its
operation, and its architecture will be compatible
with other building structures in the area. The RTF
will include an aboveground building approximately 1.5
stories in height, constructed of concrete and masonry
sound proof building materials, and designed with a
state-of-the-art activated odor control system. In
addition, as noted above in Section 5.1 -
Transportation, the County will develop and implement
a parking resources development program that will
mitigate parking disruptions due to the siting of the
RTF at Clinton Station. As such, significant long-term
impacts from the RTF will not occur.
Potential impacts during construction.
The route of the conveyances will be within street
rights-of-way, vacant lots, parking lots (private and
public), and along and within Onondaga Creek
(see Figures 1-7 and 1-8).
The installation of the conveyance pipes will restrict
building development atop the conveyances, but will be
compatible with current and proposed land uses (such
as the Creekwalk and surface parking amenities).
During the construction phase of the project, however,
a community concern expressed to the County appears to
be the potential loss of patrons to the downtown area.
Construction-related mitigation measures.
Permanent dedication of land for public infrastructure
and facilities is a legitimate and necessary function.
The lack of critical infrastructures and facilities
can also be an impediment to urban development.
Disregard for the existing and potential future urban
uses and building and landscape forms could result in
degradation of current land uses and/or inhibit future
economically beneficial uses.
The County will work closely with businesses, local
planners, and the City prior to and during
construction of the project. To date, the following
activities have been identified and will be undertaken
by the County to minimize impacts to area businesses:
-
The County proposes to undertake mitigation measure to the extent practicable to maintain vehicular and pedestrian flow in the project area.
-
During construction, a full-time construction management and inspection program will exist.
-
A complaint response program will be utilized: Project representatives will be on the construction site continuously and will develop an ongoing relationship with adjacent businesses and residents with regard to construction-related concerns and
issues. The representatives will work closely with the project contractors to see that issues or incidents are quickly addressed/resolved. The County will also publish a telephone number(s) so that individuals can report complaints or make other
comments.
-
Meetings will be held on a regular basis to allow an opportunity for residents or businesses to discuss any issues or incidents directly with representatives of the contractor, project engineer and the County. The time, dates and locations of
these meetings will be established for the duration of the construction project and written notifications of the meeting schedule will be distributed throughout the impacted area.
-
Newsletters will be published on a regular basis and distributed to residents and businesses in the impacted area. The newsletters will provide information of the status of the construction project.
-
The County will work in coordination with the impacted businesses, residents and organizations to produce appropriate public information materials in order to inform the public at large regarding traffic detours, parking alternatives and
business
access plans.
-
The County will work with local media representatives (e.g., radio and television) and provide information regarding detour routes and alternate parking areas (especially during downtown events and Syracuse University events).
-
A public information brochure will be produced to depict the improvements being developed within the area. This brochure will highlight the new Dickerson Street bridge (if applicable), the Syracuse Creekwalk, and the cleanup of Onondaga Creek
and
Lake through the removal of untreated combined sewer overflows.
-
Construction will be coordinated to minimize peak holiday season impacts through coordination efforts described above.
-
A business compensation program, proposed by the Armory Square Association, is being considered by the County.
-
The County will assess providing nighttime security for the construction work zone.
-
Hold events during construction to celebrate completion of critical phases and announce new detours.
-
Upon completion, celebrate the "closing of the ditch" to attract patrons to the downtown area.
In summary, implementation of the above-described
mitigation measures will result in relatively minor
impacts to area land use when compared to the benefits
of such a project. Based on the information presented
above, impacts to land use from the construction and
operation of the Clinton Street CSO Abatement Project
will be minimized to the greatest extent practicable.
New development and re-development is planned by the
City of Syracuse and private developers within the
general downtown and Clinton Street combined sewer
service area. The Clinton Street CSO Abatement Project
may have short-term adverse impacts associated with
construction, which the County will endeavor to
mitigate to the extent practicable. Long-term impacts
will be positive resulting from:
-
Significant improvements in water quality in Onondaga Creek and Onondaga Lake.
-
Reduction or elimination of sewage-type odors within and beyond the project area.
-
An attractive urban building (RTF) and landscaped site.
As such, enhancement to Creek conditions will improve
the success of proposed projects such as the Onondaga
Creekwalk, Rescue Mission park plans, and other
existing or proposed recreational facilities along
Onondaga Creek and Onondaga Lake. As described below,
it is the County's objective to work closely with the
City and local businesses regarding construction
schedules and activities planned for the immediate
future.
5.2.2.1 Proposed Onondaga Creekwalk
No permanent loss of parking from installation of the
underground conveyances will occur (see Section 5.1);
temporary parking and traffic-related impacts during
the installation of the conveyances in the vicinity of
the proposed Creekwalk will occur.
Above grade structures will not be allowed to be built
over the conveyances. Such dedication of open space is
consistent with the City's plan to develop this area
for a Creekwalk. Coordination of project schedules for
the Creekwalk and conveyances will minimize the
duration of impacts. Without such coordination,
construction of the conveyances and the Creekwalk in
the West Jefferson to Fayette Street area would result
in unnecessary and/or prolonged impacts to both
environmental and human resources (e.g., geology,
water, and traffic patterns) in the area.
A potential additional benefit to coordination
activities includes the possible assistance by the
County in the development of the Creekwalk (i.e.,
subsurface preparation and/or non-federal financial
assistance). This measure will assist in minimize
impacts (environmental, human and financial)
associated with the construction of the Creekwalk. In
summary, impacts from the construction of the West
Jefferson to Fayette conveyances and Creekwalk can be
mitigated through the coordination of construction
activities with the City as described above.
5.2.2.2 Proposed Dickerson Street replacement
Depending on construction schedules the County will
endeavor to work with the City to minimize
construction-related impacts should the Dickerson
Street conveyance construction activities coincide
with the Dickerson Street bridge replacement
activities. Collectively, therefore, impacts from
construction activities would be minimized to the
greatest extent possible.
5.2.2.3 Proposed Hanford Pharmaceuticals expansion
Given that the construction of the conveyances will be
within the West Street service road right-of-way
(outside the proposed expansion area of the Dupli
Graphics building), direct impacts to the expansion
efforts planned by Hanford Pharmaceuticals are not
anticipated. As described above in Section 5.1.1, the
County will continue to work closely with the
pharmaceutical company prior to and during conveyance
installation in this area to minimize
construction-related impacts.
5.2.2.4 Other possible downtown planned land uses
Impacts to the New York State funded projects (parking
garages and Landmark upgrades) are not expected as
these projects are outside the project area.
Renovations to the former Dunk & Bright building are
anticipated by SU. The Rescue Mission's park plans
between West Onondaga and Gifford Streets will commit
the area to open space. Such land use will be
consistent with that required from the installation of
the conveyances. In summary, no long-term impacts from
the installation of the conveyances in these areas are
expected. In addition, as described above in Section
5.1.1, during the construction phase of the project,
the County will continue to work closely with the
Rescue Mission and SU to minimize construction-related
impacts.
P.It otential impacts.
According to the NYSDEC, "noise is defined as any
loud, discordant or disagreeable sound or sounds." A
number of environmental factors, however, dictate the
level or perceptibility of noise at a given point of
the receptor. These factors include:
-
Distance (sound decreases with distance).
-
Multiple sources (sound is not cumulative).
-
Temperature, humidity, and wind direction (relatively insignificant role in sound perception).
-
Structures (can influence perception: windows open vs. closed, and structures can act as barriers or can produce a canyon effect).
-
Sound characteristics (sharp and startling vs. continuous and dull) (NYSDEC 2001).
In order to assess the noise-related impacts,
consideration of the existing background levels in the
project area, as well as the anticipated noise levels
of equipment to be used must be evaluated.
The following provides a summary of typical sound levels:
|
Source
|
Level (dBA)
|
Distance (feet)
|
|
Quiet suburban area nighttime
|
40
|
--
|
|
Quiet urban area
|
50
|
--
|
|
Undisturbed speech
|
65
|
3
|
|
Commercial area
|
65
|
--
|
|
Garbage truck
|
71-83
|
50
|
|
Highway traffic
|
75
|
50
|
|
Noisy urban daytime
|
75
|
--
|
|
Freight train
|
75
|
50
|
|
Bulldozer
|
80
|
50
|
|
Jackhammer
|
82
|
50
|
|
Backhoe
|
83-86
|
50
|
|
Diesel truck
|
91
|
50
|
|
Sources: NYSDEC 2001, Landrum and Brown 2001
|
Notes: dBA = sound pressure level or perceived loudness expressed in A-weighted decibel scale (dBA) which is weighted towards those portions of the frequency spectrum most sensitive to the human ear.
Typical human reactions to increases in sound levels
above background are as follows (NYSDEC 2001):
|
Increase in sound pressure (dB)
|
Reaction
|
|
Under 5
|
Unnoted to tolerable
|
|
5 - 10
|
Intrusive
|
|
10 - 15
|
Very noticeable
|
|
15 - 20
|
Objectionable
|
|
Over 20
|
Very objectionable to intolerable
|
Figure 5-8 shows noise dissipation at the northern end of the project area.
Based on the above information, the dissipation of
noise from common construction-related equipment was
evaluated. Table 5-3 provides a summary of two noise
dissipation scenarios.
Table 5-3 Noise Dissipation Analysis Typical scenario: Jackhammer operation. |
|
Distance*
|
Decibel level and reaction outside
|
Decibel level and reaction inside
|
|
50 ft
|
82 objectionable (+17 above background)
|
~67 - 77 decibel tolerable to very noticeable (+2 - 12 above background)
|
|
200 ft
|
71 intrusive (+6 above background)
|
~56 - 66 decibel not audible to tolerable (? +1 above background)
|
|
800 ft
|
66 unnoticed to tolerable (+1 above background)
|
~51 - 61 decibel not audible (< background)
|
|
1600 ft
|
65 not audible (at background)
|
~50 - 60 decibel not audible (below background)
|
| Worst case scenario: Jack hammer, backhoe, and truck operating at the same time |
|
50 ft
|
92 very objectionable to intolerable (+27 above background)
|
~77 - 87 decibel very noticeable to intolerable (+12 - 22 above background)
|
|
200 ft
|
80 very noticeable to objectionable (+15 above background)
|
~65 - 75 decibel background to intrusive/very noticeable (+0 - 10 above background)
|
|
800 ft
|
70 intrusive (+5 above background)
|
~55 - 65 decibel not audible (? background)
|
|
1600 ft
|
67 unnoticed to tolerable (+2 above background)
|
~52 - 62 decibel not audible (below background)
|
Notes:
* = Approximate
Assumed background: commercial area: 65 decibels
Influence of other structures not accounted herein (e.g., barrier/canyon effect)
Noise dissipation levels are approximate and designed to provide insight into potential noise levels in project area during construction; values based on literature review. No physical studies were conducted.
Equip. decibel levels, calculated levels, & human reaction(s) based on DEC: Assessing and Mitigating Noise Impacts (2002).
Figure 5-9 shows noise dissipation at the southern end of the project area.
In summary, based on the above information, as
construction activities progress along the route of
the conveyances, impacts to area receptors will
diminish. Although construction of the RTF will have
the longest period of construction, impacts to area
receptors will be limited at Clinton Station given the
buffer the railroad tracks offer. As described below,
initiation of the mitigation measures will further
minimize impacts to area receptors.
Mitigation measures.
Table 5-4 has been prepared to identify mitigation
measures associated with identified noise-related
impacts.
TABLE 5-4 NOISE-RELATED MITIGATION MEASURES
Construction-related measures
- complaint response program will be utilized.
- contractors will be required to maintain properly functioning equipment and comply with occupational safety and health act standards.
- construction equipment will be required to use available noise suppression devices and properly maintained mufflers.
- vehicles will be equipped with mufflers recommended by the vehicle manufacturer.
- staging of construction equipment and unnecessary idling of equipment within noise sensitive areas will be avoided whenever possible.
- use of temporary sound fences or barriers will be evaluated.
- notification will be given to residents and businesses within 300 feet of major noise generating activities. the notification will describe the noise abatement measures that will be implemented.
- monitoring of noise levels will be conducted during the construction phase of the project. exceedence of pre-determined acceptable noise levels will require the contractor(s) to stop work and remedy the situation prior to continuing
construction.
- if piles or sheeting are needed, design engineers will investigate the options of vibratory and/or boring methods.
- should piles require installation, monitoring of existing structure conditions, photographic and/or video catalogs will be conducted (both pre-construction and construction).
Design features
- RTF will be oriented to minimize permanent impacts.
- landscaping will be utilized as appropriate to buffer potential noises.
- noise producing equipment will be housed within
the RTF.
- acoustical paneling and other noise abatement features will be used throughout building.
Operational measures
- the RTF will only operate during wet weather events and will be fully enclosed and sound-proofed on the interior.
- up to four vehicles per event would be dispatched
to the RTF during each event. these vehicles would include pickup trucks, panel trucks, dump trucks, and/or sewer jet-vac trucks, all of which currently operate in and around the
proposed project area.
- vehicular traffic from facility operations will
blend with ambient noise in the armory square area.
operation-related traffic will be directed to use the
fabius street bridge to the RTF as opposed to west jefferson street or the south side of
clinton station along dickerson street.
- overhead doors will be closed during operation (including maintenance).
- the county will maintain properly functioning equipment.
Sources: EEA 2002 and EEA 2003a
Noise from construction equipment will be audible
within the project area during the construction of the
RTF and conveyances. However, the impacts will be
limited to the duration the construction activities
take place. It is anticipated that noise from facility
operations (e.g., influent pumps, odor control
equipment, and ventilation blowers and fans) beyond
the property limits of the RTF site will not occur
based on the design measures to be employed by the
County. Given the above noise avoidance and reduction
measures to be employed by the County, expected sound
levels will not produce significant long-term noise
impacts or permanently impair the use of neighboring
properties.
The Clinton Street CSO Abatement Project will not
place an unusual burden on community services such as
fire, police, recreation, or utilities:
Fire protection
The RTF will be designed and built to meet applicable federal, state and local codes (such as national fire codes published by the National Fire Protection Association, New York State Uniform Fire Protection and Building Code, and
Onondaga County Office of Mutual Aid and Training standards).
Measures to assist in emergency response situations during the construction phase of the project, as well as measures to obtain egress onto West Street from trucks at Fire Station #6 (Fabius Street), will be coordinated with the City Fire
Department.
Police protection
To maximize safety (and health) during construction activities, contractors will be required to prepare and utilize a site-specific health and safety plan. To minimize the dangers of unattended open trenches, equipment, materials,
or other unsafe conditions, the contractor will be required to employ as appropriate flashing lights, temporary fencing or barricades, and/or heavy metal cover plates. Furthermore, the contractor will be required to properly secure unattended
equipment and materials. The County will also assess the need for night-time security personnel. Public safety agencies and utilities will be notified prior to the start of construction.
From an operational standpoint, the necessity of fencing the perimeter of the site has not yet been identified by the County (EEA 2002). The RTF will, however, be a secure structure and locked when staff are not required at the site.
Recreation facilities
The loss of recreation areas from the construction of the conveyances and the RTF will not occur. Rerouting of traffic patterns during construction may result in temporary delays in accessing the MOST, Jefferson Park and/or
Armory Square Park (recreational areas within the project area). Section 5.1 - Transportation, however, identifies the mitigation measures to be employed to minimize these temporary access impacts.
Utilities
Construction contracts will require contractors to coordinate the project with Dig Safely New York. Construction activities within proximity to identified utilities would be in accordance with the respective utility company's standards.
In addition and where appropriate, excavation activities will also provide outside companies/owners an opportunity to address maintenance or replacement needs of their infrastructure that could further benefit the area.
The location of conveyances will be recorded with appropriate officials so that private individuals and/or utility companies performing excavations in the vicinity of the conveyances will not accidentally puncture or break the conveyance line.
Natural gas and electricity supplied by National Grid - Niagara Mohawk Power Corporation will be used to power and heat the RTF. Power and gas needs will be coordinated with the utility to provide sufficient electricity to meet the needs of the
project as well as the community businesses and residents of the area.
In summary, significant impacts to community services, recreational facilities, and local utilities are not anticipated. Disruptions in the current transportation network will be short-term and mitigated to the greatest extent practicable based on
community and City-identified concerns.
5.3.2.1 Waste management during construction - general practices
Left unmitigated, construction-related impacts could
include aesthetic impacts from disorderly and
unsightly work areas and accidental releases of
materials such as petroleum products and/or lubricants
used onsite by the contractors. Construction
mitigation measures include the following:
-
Dumpsters will be closed when not in use and locked at night.
-
Fuels and lubricants stored onsite will be kept in locked, well-maintained storage areas accessible only by authorized personnel.
-
Site-specific health and safety plans will be required for contractors working onsite.
-
The County will utilize a complaint response program.
-
C&D debris will be removed in a timely manner based on contract requirements.
-
Contractors will be required to properly dispose of C&D debris at a licensed offsite facility.
5.3.2.2 Waste management during construction - contaminated materials assessment
Federal and state regulations will govern the County's
management of contaminated materials if identified
during the construction phase of the project (e.g.,
contaminated soils, asbestos-containing materials, and
lead-contaminated building materials). Based on a
Phase I Environmental Assessment (draft) conducted by
EEA in July 2003, several properties located in the
RTF area, northwestern, northeastern, and southern
conveyance areas have been used at different times for
commercial/industrial activities that may pose
potential environmental concern (EEA 2003b).
During trench excavation activities associated with
archeological studies
(Section 3.5.1),
field screening with a photoionization detector was
performed. In addition, a limited number of soil
samples were collected and analyzed as part of the
Phase I Environmental Assessment. As reported by EEA
(2003), although field screening of soils detected the
presence of volatile organic compounds (VOCs) in some
locations, subsequent laboratory analysis did not
indicate the presence of elevated VOCs (EEA 2003b).
Semi-volatile organic compounds (SVOCs) and Resource
Conservation Recovery Act (RCRA) metals were detected
in samples collected from some of the archeological
trenches. As reported by EEA (2003), the presence of
such parameters is potentially associated with fill at
and in the vicinity of the site. While standards for
fill in soils in former industrial sites have not been
developed by New York State, the levels detected in
the samples collected during the Phase I Site
Assessment were below New Jersey historic fill
criteria (EEA 2003b).
Two ground water samples were collected from
observations wells at the RTF area. Two parameters
(lead and selenium) were detected in one well at
concentrations slightly above state ground water
standards (EEA 2003b).
While ongoing remedial activities supervised by the
state are being conducted at one of the commercial
locations identified during the Phase I Environmental
Assessment, EEA recommended that various soil and
ground water investigations be conducted "to determine
if there are impacts to the site from historic
operations." Such investigations, referred to as a
Phase II Environmental Assessment, included advancing
soil borings and installing temporary wells at or
adjacent to identified areas of concern. Soil and
ground water samples would be collected for VOC, SVOC,
polychlorinated biphenyl (PCB), and RCRA metal
analyses. The data from the Phase II investigation
would be used for the following purposes as warranted
or as needed:
-
To aid the construction contractor with preparing a worker and community Health and Safety Plan to mitigate potential exposures to constituents in soil/ground water
-
To identify appropriate handling techniques for impacted soil and ground water removed during construction activities.
-
To identify disposal procedures for impacted ground water (e.g., discharge to the environment following treatment, discharge to sanitary sewer, etc.).
-
To aid the County with identifying fair market prices for properties that may be impaired due to environmental conditions (EEA 2003b).
In addition, based on the results of the Phase I
Environmental Assessment, EEA (2003b) recommended that
prior to demolition of structures, a visual survey be
conducted to assess the need for (and scope of)
characterization activities (e.g., building material
sampling, etc.), including a thorough asbestos
inspection.
5.3.2.3 Waste management during operation
No impacts from waste management activities during
facility operation are anticipated. As conditions
dictate, sanitary and non-sanitary solids and
floatables will be pumped from the RTF and transported
by a force main to the main interceptor sewer for
treatment at Metro. Larger materials and grit
(approximately 500 cubic yards/year) will be removed
from the site on a periodic basis and disposed at a
New York State permitted landfill/waste incinerator
(EEA 2003a). This quantity of material does not
represent a significant increase in waste generation.
According to SOCPA records, the City has experienced a
decrease in population since the 1950s (SOCPA 2003a).
More recently, as previously noted in Section 3.4.1,
the City of Syracuse has experienced a 10% decrease in
population since 1990. The Clinton Street CSO
Abatement Project has been designed to improve the
quality of effluent-related discharges to Onondaga
Lake, decrease odors associated with combined sewerage
entering the Creek, and improve water quality and
aquatic habitat. These improvements, coupled with
anticipated planned land uses in the area (see Section
5.2.2), may help facilitate or encourage the
redevelopment of commercial and residential uses (or
create new opportunities for such) within the
immediate project area.
Based on the siting of the conveyances
(see Figures 1-7 and 1-8),
no residential structures will be demolished as a
result of installation activities (one vacant
commercial building will be demolished at the corner
of West Onondaga Street and Clinton Street). In
addition, permanent impacts to residential structures
will not occur since the RTF will be constructed at
Clinton Station, an area devoid of structures. As
such, based on this information, no long-term negative
impacts to residential structures within the project
area will occur. To the contrary, as noted above, the
implementation of the project will improve area
aesthetics for existing residents and may encourage
the redevelopment of residential properties within the
area.
Construction-related.
Until such time that the Clinton Street CSO Abatement
Project has been fully defined and design has been
initiated, it would not be appropriate to proceed with
preparation of a labor estimate specifically for the
project. As the Midland Phase II project and the
Clinton Street CSO Abatement Project are of comparable
size, it is believed that the average labor force
requirements over the construction period would be
similar (Albright 2003b):
-
Startup activities (shop drawing submission, mobilization and site preparations) and closure activities (demobilization, punch list and finish work): less than 10 workers.
-
Construction activities: 13 - 153 workers (Note: peaks are expected to be different due to variations in the scope and phasing of the work).
The Clinton Street CSO Abatement Project will require
that 10% of the workforce be contracted to
minority-owned business enterprises (MBE) and 5% to
woman-owned business enterprises (WBE). Contractors
will also be required to achieve an Equal Employment
Opportunity goal of hiring 10% minority employees and
5% female employees as part of the project workforce.
As with other CSO projects, the Clinton CSO Abatement
Project is subject to a Project Labor Agreement.
Operational.
The automated design of the RTF will allow it to
operate without full-time staff assigned to the
facility. Current OCDWEP personnel will be required to
perform periodic maintenance of mechanical,
electrical, control, and building systems/components.
Maintenance personnel will be required for wash down
after wet weather events. As such, workforce increases
within the OCDWEP are not expected.
5.4.4.1 Regional and local economics
Implementation of the projects associated with the
ACJ-mandated Lake Improvement Program represent the
largest single municipal capital improvement project
in Onondaga County history. To minimize adverse
impacts to the local economy, the Lake Improvement
Program is being partially funded by federal and state
grants. Without grant funds, however, the cost of
constructing and operating the individual ACJ projects
would represent a significant drain on the local
economy. Further, since much of the work is
anticipated to be completed by local companies
(including labor), much of the expenditures from the
ACJ projects will stay local. At the time of the ACJ
negotiations, Onondaga County and Central New York
were in the midst of a significant economic slow down
that started in the early-1990s and extended
throughout the late-1990s. Construction-related jobs
for the Lake Improvement Program (as well as others in
the area) are now on the rise and the County is
working with local labor unions and training agencies
to gear up the area's workforce to fill the necessary
jobs (EEA 2000).
The cost of the Lake Improvement Program, including
operational expenses, will be born by the Onondaga
County Sanitary District, which includes approximately
two-thirds of the County's population and most of the
businesses and industry. Therefore, the cost of the
program will not fall unfairly on any one particular
City or County resident. The total 15-year impact of
the program on the sewer unit charge has been
estimated to be approximately $234 per unit. The
increase is projected to rise over the period of 15
years between $5 and $25 per year (Karsinski 2005).
The total estimated project cost for the Clinton
Street CSO Abatement Project (in-line storage/vortex
separator RTF at Clinton Station) is $71,300,000 (EEA
2005).
5.4.4.2 Local business district
During construction, the potential loss of patrons
could potentially cause disruptions to a small number
of businesses. The County will work closely with
businesses, local planners, and the City prior to and
during construction of the project to minimize overall
economic impacts during construction. As previously
noted in the Land Use section (Section 5.2.1), the
following activities will be undertaken by the County:
-
The County proposes to undertake mitigation measure to the extent practicable to maintain vehicular and pedestrian flow in the project area.
-
During construction, a full-time construction management and inspection program will exist.
-
A complaint response program will be utilized: Project representatives will be on the construction site continuously and will develop an ongoing relationship with adjacent businesses and residents with regard to construction-related concerns and
issues. The representatives will work closely with the project contractors to see that issues or incidents are quickly addressed/resolved. The County will also publish a telephone number(s) so that individuals can report complaints or make other
comments.
-
Meetings will be held on a regular basis to allow an opportunity for residents or businesses to discuss any issues or incidents directly with representatives of the contractor, project engineer and the County. The time, dates and locations of
these meetings will be established for the duration of the construction project and written notifications of the meeting schedule will be distributed throughout the impacted area.
-
Newsletters will be published on a regular basis and distributed to residents and businesses in the impacted area. The newsletters will provide information of the status of the construction project.
-
The County will work with local media representatives (e.g., radio and television) and provide information regarding detour routes and alternate parking areas (especially during downtown events and Syracuse University events).
-
The County will work in coordination with the impacted businesses, residents and organizations to produce appropriate public information materials in order to inform the public at large regarding traffic detours, parking alternatives and
business
access plans.
-
A public information brochure will be produced to depict the improvements being developed within the area. This brochure will highlight the new the Dickerson Street bridge (if applicable), the Syracuse Creekwalk, and the clean up of Onondaga
Creek and Lake through the removal of untreated combined sewer overflows.
-
Hold events during construction to celebrate completion of critical phases and announce new detours.
-
Upon completion, celebrate the "closing of the ditch" to attract patrons to the downtown area.
-
Construction will be coordinated to minimize peak holiday season impacts through coordination efforts described above.
-
A business compensation program, proposed by the Armory Square Association, is being considered by the County.
-
The County will assess providing nighttime security for the construction work zone.
Collectively, based on the information presented
above, impacts to local businesses from the
implementation of the Clinton Street CSO Abatement
Project will be minimized to the greatest extent
practicable. Aside from meeting ACJ mandated
requirements to improve the water quality of Onondaga
Creek, implementation of the project may induce both
commercial and residential growth of the area on a
long-term basis.
A Letter of Understanding between the County and OPRHP
regarding the Onondaga Lake Improvement Project was
signed in April 2000. Consistent with the terms
identified in the letter (as well as the National
Historic Preservation Act of 1966), detailed studies
have been performed and documented by Hartgen (2001
and 2003) that indicate historic and archeological
resources exist in the project area. Mitigation
measures identified to date [as recommended by Hartgen
(2003)] include avoidance of select areas known to be
culturally sensitive and/or a combined Phase II/III
archeological investigation. The County will continue
to consult with OPRHP (in conduction with Onondaga
Nation) to minimize impacts to the historical and
archeological resources of the project area.
Potential impacts.
Significant aesthetic impacts are those that may
cause a diminishment of the public enjoyment and
appreciation of an inventoried resource, or one that
impairs the character or quality of such a place
(NYSDEC 2000a).
Given that conveyances will be underground, discussion
regarding visual impacts is limited herein to the
presence of the RTF building. As described in Section
1.3, the RTF is estimated to be a 25-foot tall, 40,000
square foot (maximum) structure; essentially a
1.5-story building. A stack approximately 10 feet
above the rooftop will also be visible. As described
below, based on the building height and location (RTF
will be located behind the elevated railroad
embankment and creek bank vegetation), building
visibility will be largely obscured or blend into the
existing downtown setting.
Sensitive receptors and state-recognized historic
sites within 1000 feet of the RTF site:
-
Gethsemane Holiness Church at 201 Gifford Street (sensitive receptor)
-
Rescue Mission complex on Gifford Street (sensitive receptor)
-
PEACE West Side Center at 200 Wyoming Street (sensitive receptor)
-
Armory Square Historic District (a National Register Listed site)
-
206 Gifford Street (a historic site eligible for listing)
-
Clinton Plaza Apartments at 550 South Salina Street (sensitive receptor)
-
Hanford Pharmaceuticals at 429 West Street (sensitive receptor)
-
Galaxy Communications at 235 Walton Street (sensitive receptor)
Due to the presence of the elevated railroad
embankment (which ranges in height from an estimated 8
- 20 feet), views of the RTF building from the Armory
Square Historic District will be substantially
obscured. Views from the PEACE Center, Galaxy
Communications and the Gifford Street sites (206
Gifford, Church, and Rescue Mission) will be largely
obscured due to other multi-story buildings,
vegetation located along Onondaga Creek, and the
intervening distances between the RTF and receptors.
The RTF will be visible to workers at Hanford
Pharmaceuticals having windows on the east side of the
building (approximately 10-15 windows), residents of
Clinton Plaza Apartments having windows on the west
side of the building (approximately 50), and persons
continuing to park their cars at Clinton Station after
project completion (Clare 2003). Occupants of
multi-story commercial and residential properties,
such as Hawthorne Suites, Hotel Syracuse, MONY
building, Chimes building, Marx Hotel, etc. will be
capable of seeing the RTF.
Mitigation measures.
Views of the RTF building will likely be limited to
nearby structures at, or above, the height of the RTF
structure due to the following:
-
The topography of the surrounding area is relatively flat (400 ft above sea level) thus limiting views of the structure.
-
The location of the RTF building on the northern portion of the Clinton Station parcel is away from Clinton Street/Dickerson Street and commercial traffic.
-
The RTF building height is relatively short (approximately 25 feet or 1.5-story) with an estimated 10-foot stack.
-
The RTF building will be located behind the elevated railroad embankment that ranges in height from an estimated 8-20 feet.
To further improve the aesthetics of the area to the
sensitive receptors and historic properties identified
herein, as well as to commercial and residential
properties within view of the RTF, the mitigation
measures listed below will be undertaken by the
County. These measures not only minimize the view of
the RTF building from neighboring buildings but
significantly reduce and obscure the view of the RTF
from ground level as pedestrians (residents and/or
patrons) travel downtown.
-
The building will house only the minimum amount of equipment and staff-related space necessary to operate effectively the RTF building thus minimizing the footprint of the building to the greatest extent practicable.
-
The building site will be landscaped and the building and site will be properly maintained by the County.
-
The architecture of the building will be compatible with other buildings within the project area.
Based on the above measures, the RTF will not present
adverse aesthetic effects. No impacts that diminish
the public enjoyment and appreciation of the
inventoried resources, or that impairs the character
or quality of such a place, have been identified. From
ground level within the Armory Square area, view of
the RTF will not be possible. In addition, the RTF
will be designed and landscaped to be compatible with
surrounding architecture and, as such, will enhance
the overall appearance of the view shed by replacing
part of a barren parking lot and neglected creek bank
with an attractively designed and landscaped facility.
Furthermore, as described herein, the Clinton Street
CSO Abatement Project provides an opportunity for a
secondary aesthetic improvement of the proposed
Creekwalk along Onondaga Creek. The project provides
an opportunity, both timely and economically, to
assist with the extension of the Walton Street to
Fayette Street portion of the Creekwalk.
The state's environmental justice policy is "designed
to ensure fair treatment and meaningful involvement of
all people, regardless of race, color or income, with
respect to the development, implementation and
enforcement of environmental laws, regulations and
policies" (NYSDEC 2003b). The state's policy applies
to NYSDEC applications requiring review of major
projects or major permit modifications such as SPDES
that could impact a potential environmental justice
area. An environmental justice area is described by
the state as a minority or low-income community that
may bear a disproportionate share of the negative
environmental consequences resulting from project
operations or the execution of governmental programs
and policies. Applicable state environmental justice
definitions are as follows (NYSDEC 2003a):
Low-income community
means a Census Block Group, or contiguous area with multiple Census Block Groups, having a low-income population equal to or greater than 23.59% of the total population.
Low-income population
means a population having an annual income that is less than the poverty threshold. For purposes of this policy, poverty thresholds are established by the U.S. Census Bureau.
Minority community
means a Census Block Group, or contiguous area with multiple Census Block Groups, having a minority population equal to or greater than 51.1% in an urban area and 33.8% in a rural area of the total population.
Minority population
means a population that is identified or recognized by the U.S. Census Bureau as Hispanic, African-American or Black, Asian and Pacific Islander or American Indian.
The USEPA recognizes that census data are useful for
screening analyses, but results should always be
validated through other means, including public
participation, touring the community, and talking with
local officials and community leaders.
Given that the Clinton Street CSO Abatement Project
will involve the issuance of a SPDES permit, a
preliminary assessment of potential environmental
concerns was undertaken. The steps used to assess such
concerns consist of the following:
-
Identify the area to be affected by the project.
-
Evaluate whether the affected area consists of a minority and/or low-income community.
-
Identify the potential adverse environmental impacts of the project.
-
Evaluate whether the potential adverse environmental impacts are likely to disproportionately impact the identified environmental justice area.
The Clinton Street CSO Abatement Project EID embodies
the review elements that can be used to assess whether
the proposed project places a disproportionate amount
of adverse environmental, economic, social, or health
impacts on low-income and/or minority populations. The
following subsections provide a preliminary assessment
of environmental justice applicability with regard to
the Clinton Street CSO Abatement Project based on the
above methodology.
In assessing environmental justice, the County's
review focuses on the potential impacts associated
with the construction and operation of the RTF. In an
effort to locate the most viable site for the RTF, an
alternatives review process
(Section 7)
and numerous community meetings were conducted,
including those with representatives from neighboring
residential communities
(see Section 9).
To meet the requirements of the ACJ, placement of
facilities associated with the Clinton Street CSO
Abatement Project is limited to the downtown area
since the CSOs to be abated are located along Onondaga
Creek in this area
1-2).
Based on this requirement, the majority of the
conveyance lines must parallel the Creek where the
CSOs exist. For this reason regardless of where the
RTF is sited, common conveyance routes exist along
West Onondaga to Dickerson, West Street (northbound
service road), and West Jefferson to Fayette Streets.
Given that the RTF is the only above ground structure
associated with this abatement project, the affected
project area is considered that area surrounding the
RTF building itself. The selection process for siting
the RTF was based on environmental evaluations
(including impacts to natural and human resources) and
engineering evaluations; the process was conducted
independent of factors such as income or ethnicity. As
a result of the above selection process, as described
in greater detail in
Section 7,
Clinton Station was identified by the County as the
recommended/preferred siting alternative for the RTF
(see Figure 1-7).
In summary, siting of the RTF at Clinton Station
offered the least overall impact to the community
while remaining the most cost effective alternative.
Land use within the project area is comprised largely
of parking, street rights-of-way, and commercial/light
manufacturing (Hanford). Residential properties such
as the Rescue Mission, Clinton Plaza Apartments, and
the Center Armory exist in proximity to the project
area. These properties are diverse and range from
assisted housing at the Clinton Plaza Apartments to
upscale townhouse/condominium complexes within the
Armory Square Historic District (SDCD 2000 and SOCPA
2003a).
To assess potential environmental justice concerns, it
is necessary to characterize the area population
affected by the proposed RTF at Clinton Station in
terms of minority composition and in terms of relative
income distribution. Based on the above descriptions
regarding minority and low-income communities using
Block Group data presented in Section 3.4 -
Demographics:
-
Approximately 56% of the RTF project area is identified as minority, and
-
Approximately 49% of the RTF project area is identified as existing below the poverty level.
Both of these numerical representations using Block
Group data exceed the criteria specified by the state
regarding minority and low-income communities (greater
than 51.1% and 23.59%, respectively). Given such
findings, an assessment of whether potentially adverse
environmental impacts are likely to disproportionately
impact the identified minority and low-income
community of the affected project area was undertaken.
As previously noted, land use within the project area
is comprised largely of parking, street rights-of-way,
and commercial/light manufacturing (Hanford). Based on
Census Block data (subset of a Block Group), an
estimated 485 persons reside in the immediate area of
Clinton Station. Construction of the Clinton Street
RTF will result in short-term disruptions to resources
such traffic, parking, noise, and air quality
(see Sections 4, 5 and 6 and the
Assessment Summary Table).
No residential structure demolition will occur at the
RTF site.
From an operational standpoint, the influent pumps
within the building will not operate continuously. The
building will be constructed of soundproof materials
and noise issues will be minimized to the greatest
extent practicable. Impacts to area residents are not
foreseen as the site is (and will be) buffered by the
elevated railroad embankment, landscaping, Creek
vegetation, and the building's distance from nearest
receptors (site is five acres). As stated in
Section 4.3.1,
the chlorination/dechlorination process is state and
federally approved for sewage-related uses and does
not pose a significant risk to aquatic animals or to
humans. The facility will operate in accordance with
applicable air resource regulations. In addition,
odors from the facility as a result of treatment
activities will be minimized to the greatest extent
practicable as the RTF will utilize state-of-the-art
activated carbon odor control systems to eliminate
sewage-type odors. Furthermore, the County will adhere
to applicable regulations with regard to the storage
(and transport) of chemicals. As identified in
Section 4.2.2,
similar facilities utilizing the same carbon odor
control systems have not experienced complaints from
neighboring properties.
As noted in
Section 5.5.2,
the RTF will resemble a 1.5-story building and built
consistent with local architectural styles. The
facility grounds will be landscaped to provide an
aesthetically pleasing setting. The RTF will be
designed and constructed to minimize permanent impacts
to the neighboring community and transient receptors.
In addition, long-term aesthetic benefits include the
elimination of CSOs that include floatable solids
within the Creek during storm events.
Given that the facility will operate periodically,
operational truck-related traffic will not
significantly affect the community. As previously
noted, reconstruction of the Fabius Street bridge will
allow RTF traffic to utilize West Street (a major
arterial) and bypass smaller secondary downtown
streets consisting of, and utilized by, local
residents.
In summary, the Clinton Street RTF may have short-term
adverse impacts associated with construction but given
the mitigation measures program described herein, the
short-term impacts will be relatively minor when
compared to the benefits of such a project. No
significant impacts from the operation of the RTF are
anticipated.
As previously noted, to meet the requirements of the
ACJ, placement of facilities associated with the
Clinton Street CSO Abatement Project is limited to the
downtown area because the CSOs to be abated are
located along Onondaga Creek in this area. Based on
this engineering requirement, the siting of the RTF
must be in close proximity to Onondaga Creek. As
described in greater detail in
Section 7 (Alternatives),
two alternative RTF sites emerged as the most feasible
out of an original seven possible locations identified
by EEA (2005). The two alternative locations
identified as most feasible consist of Clinton Station
(the recommended/preferred location) and the Dickerson
Street alternative (EEA 2005).
The Dickerson Street alternative is located between
Fabius and Dickerson Streets. Utilizing the state's
environmental justice review policy with respect to a
Block Group evaluation reveals that the same Block
Groups are affected with the Dickerson Street option
as the Clinton Station option (i.e., T30-BG1 and
T32-BG1). Such findings indicate that the Dickerson
Street option is also comprised of minority and
low-income communities.
Given the common Block Group data, and consistent with
the USEPA's approach of validating the census data
through site reconnaissance, actual land use at the
Dickerson Street alternative was compared to Clinton
Station. In summary, the Dickerson Street site is a
mix of both active and inactive commercial and
residential properties. Selection of the Dickerson
Street alternative would require the demolition and
relocation of commercial and residential properties.
Wherein Clinton Station is buffered by the elevated
tracks and creek vegetation, the Dickerson Street
alternate would not be buffered and would be located
directly adjacent to the Rescue Mission's recreation
center in a mixed commercial and residential area. The
Rescue Mission residential treatment center would be
located across Dickerson Street to the south of the
Dickerson Street RTF site option.
Although the RTF project area is located in a
low-income and minority community, based upon the
information summarized above and described in detail
within this document, adverse environmental impacts
disproportionately affecting a specific ethnic and/or
low-income population were not identified.
Furthermore, placement of the RTF in Clinton Station
has less potential for directly impacting residential
and commercial properties than the Dickerson Street
site alternative since no residential structures will
be demolished. In summary, the project will be of
benefit to the community as a whole by removing a
significant source of odors in Onondaga Creek within
the project area as well as improve the water quality
of both the Creek and Lake.
Given the assessment described above, it is the
County's determination that the Clinton Street CSO
Abatement Project is not subject to the state's
environmental justice policy since adverse
environmental impacts disproportionately affecting a
minority and/or low-income population were not
identified. The project as proposed is designed to
address longstanding environmental and public health
concerns regarding untreated CSO discharges to
Onondaga Creek and subsequently the Lake. The ACJ
mandated Clinton Street CSO Abatement Project creates
beneficial and positive long-term conditions to an
area currently experiencing deleterious impacts from
untreated CSO discharges. As such, even if it is
ultimately determined that the project will result in
significant adverse impacts, it is the County's
position that the overall public health and
environmental benefits of the project will justify
such impacts. Consistent with the policy's directives,
however, the County will continue to communicate
project activities with the community through various
meetings and written documentation
(see Section 9).
|