|
Environmental information document (draft), Clinton Street CSO Abatement Project February 2005
Prepared by SGD Environmental Services for Environmental Engineering Associates, LLP
PROPOSED LEAD AGENCY
Onondaga County, Department of Water Environment Protection
650 Hiawatha Blvd., W., Syracuse, NY 13204
Contact: Richard L. Elander, PE, Commissioner, 315-435-2260
4. Impact evaluation and mitigation measuresnatural resources
The following section describes the potential natural
resource impacts associated with the implementation of
the Clinton Street CSO Abatement Project. Natural
resources consist of geological, air, water,
ecological, and agricultural resources.
Identified impacts are potential and result when
mitigation measures are not implemented. As such,
following the identification of potential impacts,
mitigation measures to minimize the identified impacts
are discussed. Mitigation measures are primarily based
on industry-specific standards and practices,
County-accepted mitigation techniques, and/or
mitigation measures reached through consensus during
County-sponsored community meetings.
(Section 9
provides information regarding public meetings and
Clinton Mitigation Advisory Committee meetings).
Resultant mitigation measures will be incorporated
into the construction and/or design stages associated
with the Clinton Street CSO Abatement Project.
In addition to the mitigation measures identified
herein, the County will establish a complaint response
program during the construction phase of the project.
The program will be a systematic approach to
receiving, processing, and addressing complaints
regarding the construction of the Clinton Street CSO
Abatement Project. As such, problematic areas
identified during construction will be further
minimized during actual project implementation.
Bedrock will not be encountered and, therefore,
impacts to this geologic resource are not expected. In
addition, no environmental impacts to the geologic
setting are anticipated from the normal operation
and/or maintenance of the Clinton Street CSO Abatement
facilities. During construction, disruption of area
soils and limited alterations to topography will occur
from clearing, excavating, grading, and backfilling
activities.
Potential erosion and/or sedimentation issues.
As a result of excavation activities associated with
the RTF, disruption to area soils to depths from 10 to
50 feet (influent sump/wet well) will occur. Soil
erosion and sedimentation of exposed soils (such as
trenching and stockpiling activities) associated with
pipe installations listed below also represent
potential impacts:
-
West Jefferson Street conveyance extending from the RTF site north/northeast to the back of the MOST:
- Pipe diameter: 84 inch
- Estimated average depth of excavation: 20 feet
- Approximate length: 730 feet (assumed to include the 84-inch pipe in the West Jefferson CSO transmission pipeline)
-
West Jefferson Street north of Walton Street to Fayette Street:
- Pipe diameter: 42 inch
- Estimated average depth of excavation: 16 feet
- Approximate length: 280 feet (assumed to include the 42-inch pipe in the West Jefferson CSO transmission pipeline)
-
West Street conveyance west of the Creek to Walton Street:
- Pipe diameter: 24-36 inch (30-36 inch if CSO 028 is closed as recommended by Facilities Plan)
- Estimated average depth of excavation: 18 feet
- Approximate length: 1,240 feet (assumed to include all of the West Street CSO transmission pipeline from the west bank of the Creek to Walton Street)
-
A small portion of the force main:
- Pipe diameter: 36 inch
- Estimated average depth of excavation: 15 feet
- Approximate length: 140 feet (assumed to include the force main along Dickerson Street)
-
Unmitigated, settlement may occur along the elevated railroad embankment as a result of excavation wall movements and/or consolidation settlement:
- Pipe diameter: 84 inch
- Estimated average depth of excavation: 20 feet
- Approximate length: 330 feet (assumed to include the 84-inch pipe adjacent to railroad embankment)
In addition, clearing, excavation, and grading
activities at the RTF site will result in localized
soil disturbances and minimal alterations of site
topography (less than two acres).
Without the implementation of erosion and
sedimentation controls described below, exposed soils
could result in siltation impacts to Onondaga Creek
(water quality issues) and/or air quality issues
(dust).
Erosion and sedimentation controls.
The County will comply with applicable soil and
erosion control requirements and follow guidelines for
urban and sediment control issues by the state. This
will include the development of an erosion and
sediment control plan designed to maximize erosion
control and minimize nutrient and sediment runoff.
Since the construction phase of the project will
involve the disturbance of more than one acre,
coordination with the NYSDEC will be required to
obtain a SPDES permit for construction activities.
Permit conditions will require the development and
adherence to a site-specific storm water pollution
prevention plan (SWPPP).
The above plans will be utilized by the contractor
during the construction phase of the Clinton Street
CSO Abatement Project. In summary, the plans will
include the following industry-specific and accepted
standards and practices:
-
Identification of construction limits (minimal area required to complete construction activities).
-
Inspection of construction activities to assess and correct areas of erosion and/or sedimentation (as necessary, corrective measures will be implemented).
-
Inspection of areas of erosion and/or sedimentation and implementation of corrective measures, as necessary.
-
Utilization of silt fencing, hay bales, stone check dams, and/or sediment traps on areas of potential erosion and/or sedimentation concern (including diversion swales to capture sediment-laden runoff, where necessary).
-
Covering stockpiled soils with mulch or netting when not in use.
-
Identification of storm water management technique(s) as outlined in the site-specific SWPPP (including, as needed, the installation of temporary sediment basins to minimize erosion and sedimentation caused by storm water runoff).
-
Implementation of dust control measures (see Section 4.2.1).
Following construction, restoration activities will commence within the project area:
-
Erosion control devices will be removed and the areas will be stabilized.
-
Grading operations will return contours to their approximate original configuration (subsoil will be scarified prior to placement of topsoil).
-
Disturbed soils outside the creek bank will be seeded and mulched consistent with flood control measures as soon as practicable after disturbance .
-
Paved areas, curbs, sidewalks, etc., will be returned to their original condition.
In summary, as noted above, temporary impacts to the
geological setting (i.e., upper 50 feet of soil or
less) of the project area will occur as a result of
construction activities. However, the above-described
mitigation measures (including the complaint response
program) will minimize these short-term impacts to
minor disruptions and, therefore, no long-term
permanent impacts to the geologic setting are
expected.
Potential settlement impacts.
Based on the preliminary study prepared by Haley &
Aldrich (2003), construction of the RTF building at
Clinton Station appears feasible from a geotechnical
standpoint. The existence of fill deposits is not
considered to significantly impact construction of
such a building at the site. Haley & Aldrich state
that temporary construction dewatering requirements
may represent a construction issue at the Clinton
Station parking lot.
Directional boring to cross the railroad tracks is
anticipated at the West Jefferson Street tunnel
entrance to Clinton Station:
-
Pipe diameter: 84 inch
-
Anticipated boring pit depth of excavation: 25
feet deep (500 ft² excavation)
-
Anticipated receiving area depth of excavation:
25 feet deep (400 ft² excavation)
In addition, the 84-inch West Jefferson Street
conveyance will parallel approximately 300 feet of the
elevated rail. Unmitigated, settlement could occur
along the elevated railroad embankment as a result of
excavation wall movements and/or consolidation
settlement.
Measures to mitigate settlement.
The following measures will be undertaken by the
County prior to construction activities to minimize
the potential for settlement:
-
Detailed geotechnical study to develop appropriate construction plans will be prepared.
-
The County will work closely with Onondaga County Industrial Development Agency (owner of the railway) to obtain the necessary permits and easements for work in proximity to the railroad tracks including boring under the tracks.
-
Tight sheeting to prevent settlement during excavation activities will occur.
-
Ground improvements such as compaction and grouting will take place.
-
Appropriate alteration of excavation and support sequence to minimize ground movement will take place.
In summary, the existence of fill deposits is not
considered a significant impact to constructing a
building such as the RTF at the site and settlement of
the tracks is not anticipated.
As expressed during public meetings, sewage-type odors
emanating from Onondaga Creek in the project area have
been identified by local residents. Given that project
implementation will abate CSO entering the Creek,
sewage-type odors from the Creek will be substantially
reduced and/or eliminated. No impacts to area climate
(including precipitation) will occur as a result of
project implementation. It is recognized, however,
that short-term air resource impacts (primarily dust)
from construction activities will occur. The following
subsections provide a discussion of anticipated
construction-related emissions and dust as well as a
discussion of the odor control features to be
associated with the operational RTF.
Construction-related potential impacts - vehicular emissions.
Minor air quality impacts will be caused by emissions
from construction vehicles, equipment and personnel
automobiles, and emissions from delayed traffic. Air
pollutants typically emitted from vehicles include
ozone, carbon monoxide, nitrogen dioxide, and
particulates (NYSDEC 2000b). It is estimated that 8300
truck trips will be required during the construction
period (3 - 3.5 years) for removal of spoil material
and delivery of select backfill, concrete and other
equipment and materials. The daily rate is estimated
to range between 0 and 75 per day during periods when
RTF and conveyance construction are being performed
simultaneously. The peak rate is projected to occur
only intermittently during excavation of the
disinfection tank and other underground structures of
the RTF (Albright 2004).
Truck trips associated with construction of the
conveyances and force main are estimated to be 4000
trips over the course of construction and will range
from 0 to 20 trips per day depending upon the sections
of sewer being constructed. Approximately 4300 truck
trips are projected for the RTF during the
construction period with a range of 0 to 60 trips per
day. The peak will occur during removal of excavated
spoils associated with the RTF construction (Albright
2004).
Mitigation measures - vehicular emissions.
Although construction vehicle emissions will be offset
given that up to 400 cars will no longer access
Clinton Station on a daily basis during the
construction of the RTF, industry-specific and
accepted standards and practices will be required of
the contractors and will include the following:
-
The contractor will be responsible for maintaining properly functioning construction equipment to minimize exhaust.
-
Construction equipment and vehicles will be turned off when not used for extended periods of time.
-
To the extent possible, deliveries of construction material will be scheduled during off-peak hours.
-
Unnecessary idling of construction vehicles will be prohibited.
-
Effective traffic detour routes will be identified and maintained to avoid significant delays in and around the project area.
In summary, construction-related traffic is not
anticipated to cause a contravention of federal air
quality standards based on the above mitigation
measures and based on comparisons to similar
construction projects (i.e., Metro upgrades) (EEA
2000). Over the 3 - 3.5 year construction period,
construction vehicle-related emissions will not
constitute a significant increase in overall emissions
and no significant impacts to local air quality are
expected.
Construction-related potential impacts - dust.
Excavation activities associated with the construction
of the RTF and pipe trenching and backfilling
activities will generate dust from the movement of
soils during construction activities. Given such
activities, localized dust-related impacts are
expected. The mitigation measures described below are
expected to reduce dust-related impacts.
Mitigation measures - dust.
The County will continue to work closely with
representatives from the community to identify areas
of concern and to mitigate dust-related impacts
effectively (e.g., through direct meetings,
utilization of construction management and inspection
program, and/or through the complaint response
program). To date, to minimize issues related to the
generation of dust during the construction phase of
the project, the following measures have been
identified:
-
Identification of construction limits (minimal area required to complete construction activities).
-
When practical, excavated spoils will be removed as the contractor proceeds along the length of the pipe.
-
When necessary, stockpiling of backfill material will be covered or staged offsite location with backfill material being delivered as needed during the course of construction.
-
Excessive soil on paved areas will be sprayed (wet) and/or swept and unpaved areas will be sprayed and/or mulched . The use of petroleum products or similar products for such activities will be strictly prohibited.
-
Contractors will be required to cover stockpiled soils and trucks hauling soil, sand, and other loose materials (or require trucks to maintain at least two feet of freeboard).
-
Appropriate detours for effective traffic flow will be defined (see Section 5.1).
Based on the above-defined mitigation measures, as
well as utilization of a complaint response program
proposed by the County, air quality impacts from the
generation of dust during construction will not exist
or will be minor in nature.
Potential operational impacts - volatile emissions.
Vehicular traffic during operation of the RTF has been
estimated at four trucks per event. Such figures
represent a minor increase in vehicular emissions.
Minor releases of VOCs may also occur during operation
of the RTF due to the storage of CSO. It is
anticipated that operational emissions will fall
significantly below regulated thresholds based on
similar construction projects (e.g., Metro upgrades,
EEA 2000). As such, emissions from the implementation
of the Clinton Street CSO Abatement Project are
considered minor in nature.
Mitigation measures - volatile emissions.
As described in greater detail below, control
equipment installed to reduce odors will minimize the
release of VOCs associated with stored CSO. In
addition, the County will comply and operate the
facilities in accordance with applicable state air
resource regulations (6 NYCRR 200-240).
Potential impacts.
It is anticipated that implementation of the Clinton
Street CSO Abatement Project will significantly reduce
odors currently observed in the Creek and the
immediate area surrounding the Creek. As previously
noted, current estimates indicate that 74% of the CSO
generated within the service area is sent to Metro.
The installation of the RTF will increase the capture
volume to 86%. As such, the RTF will function to
remove solids and floatables that currently contribute
to Creek odors (EEA 2002).
The County has committed to incorporate odor control
facilities with redundant features to maximize the
capture of odors before air is exhausted from the RTF.
Left unmitigated, odors could be released from RTF
operations as a result of CSO storage. Organic
constituents contained in the stored combined sewage
undergo biodegradation depleting available oxygen and
generating methane and hydrogen sulfide gases. Once
the supply of oxygen has been depleted in the
wastewater, odors can be produced. These odors are
generally caused by the production of hydrogen sulfide
gas by microbial activity. Typically, hydrogen sulfide
is present in wastewater at a concentration up to 20
parts per million (ppm) (EEA 2002). The probability of
odor development is increased with the length of time
the material is stored, higher temperatures, higher
solids concentrations, and increased number of access
points. No odor-related impacts from construction
vehicles are anticipated.
Mitigation measures.
The facility's exhaust system will be equipped with an
advanced, state-of-the-art activated carbon odor
control system. Exhaust will be discharged (after
treatment) through an estimated 10-foot stack located
on the roof of the RTF (i.e., total height above
grade: approximately 35 feet) (EEA 2003a). Table 4-1
summarizes the design features, technologies, and/or
activities that will be implemented by the County at
the Clinton Street RTF.
Table 4-1 Summary of Odor Control Measures
Design features
- RTF will be fully enclosed.
- Disinfection tanks will be underground; no aboveground tanks will exist.
- Odor control equipment will capture odors before air is exhausted.
- Odor control system will contain redundant components to provide for a backup system.
Odor control system
- Preferred technology - Calgon Phoenix Odor Control System:
- System utilizes carbon to adsorb fumes [hydrogen sulfide, methane, sodium hypochlorite (chlorine odors), and sodium metabisulfite (sulfur dioxide odors)].
- System capable of treating levels over 50 ppm to low/nondetectable level.
- Carbon regenerated using water; no chemicals needed to regenerate.
Operational activities
- The RTF, and therefore the disinfection process, will be kept under negative air pressure that will cause the air to be continuously drawn into the building by a ventilation system.
- Overhead doors will be closed during the operation (including maintenance).
- Liquid sodium hypochlorite and liquid metabisulfite will be stored in approved containers (tanks) and meet applicable NYSDEC chemical storage regulations.
- 12 number of air exchanges per hour for active operation; 2 number of air exchanges per hour during inactivity.
- The odor control system will be operated at a higher rate as CSO enters the facility (active). During inactive periods, only a portion of the odor control system will be required for treatment of a smaller rate of air being discharged.
Source: EEA 2002
Based on the above-described mitigation measures, normal operation and maintenance activities at the RTF will not result in odor impacts to area receptors. To the contrary, the operation of the RTF will
substantially reduce and/or eliminate sewage-type odors currently observed in the Creek and surrounding the Creek.
The following section focuses on potential impacts and
mitigation measures associated with the water quality
of Onondaga Creek and floodplains. Given that federal
NWI wetlands and NYSDEC wetlands have not been mapped
within the project area, impacts to wetlands will not
occur.
Implementation of the Clinton Street CSO Abatement
Project will result in a substantial reduction in
solids, floatables, and bacteria currently entering
the Creek in connection with untreated CSO that enter
the Creek. As such, project implementation will result
in an overall improvement to the water quality of
Onondaga Creek and, therefore Onondaga Lake.
Short-term minor impacts in water quality, however,
will occur as a result of construction activities; no
significant negative impacts are anticipated.
Potential impacts.
The following construction activities in and around Onondaga Creek are anticipated:
-
Installation of the West Onondaga Street and the West Street conveyance pipes across Onondaga Creek (see Figure 1-7) if an open trench methodology is employed:
-
West Onondaga Street Creek conveyance:
- Pipe diameter: 72 inch
- Anticipated average depth of excavation: 84 inch
- Approximate crossing length: 60 feet (bank to bank)
-
West Street Creek conveyance:
- Pipe diameter: 36 inch
- Anticipated average depth of excavation: 42 inch
- Approximate crossing length: 60 feet (bank to bank)
-
Construction of the disinfection tank outfall (120-inch diameter) (emergency controlled diversion spillway not designed at this time).
-
Reconstruction activities at the Fabius Street bridge.
-
Construction of bulkheads (specific location yet to be determined)
-
Installation of diversion structures at CSOs 027 through 036
(see Figure 1-2).
-
Installation of portions of the West Onondaga Street and West Street conveyances, as well as majority of the underflow force main, that closely parallel the Creek (within 10 to 40 feet) from Oneida Street to Tully Street and West Jefferson Street
to south of Fayette Street. Collectively, approximately 2800 feet of trenching will be excavated to install these conveyance portions and the force main in this area.
Unmitigated, potential impacts from the above
activities could include siltation, flow disruptions,
damage to the flood control channel, and creek bed
contour changes. Furthermore, without mitigation
measures employed, the direct discharge of ground
water/storm water from excavated trenches and
excavation areas at the RTF site could impair the
water quality of the Creek. Lastly, from an
operational standpoint, impacts to the water quality
could be expected if the RTF treated effluent was not
dechlorinated prior to discharge to the Creek.
Conveyances/force main - mitigation measures.
As described in Table 1-4 Anticipated approvals/permits, the County will be required to obtain state and federal permits to work within (or under) and adjacent to Onondaga Creek. As such, in order to comply with permit requirements, construction
activities will be based on state and federally-accepted and approved technologies and monitored throughout the construction period. Typical mitigation measures associated with crossing the Creek utilizing an open cut methodology will include the
following :
-
Minimize the time required for trenching, pipelaying, and backfilling.
-
Clear vegetation along creek banks only to the extent necessary for construction purposes.
-
Utilize rights-of-way to access both sides of the Creek (to avoid vehicular crossings of the Creek itself).
-
Place silt fencing and/or hay bales along the creek bank approaches to minimize siltation of the Creek, and bank approaches to minimize siltation along the Creek.
-
Store petroleum products 100 feet or more beyond the Creek.
-
If open trenching is utilized, backfill excavated trenches and restore the channel lining so that there is no change in the contour of the channel.
-
If open trenching is utilized, utilize temporary creek diversions and turbidity barriers.
-
Avoid non-construction areas during construction activities (as well as during routine maintenance of the RTF outfall).
-
Inspect creek bank after restoration activities have been completed to assess whether additional restoration activities are warranted.
Construction techniques to minimize potential adverse
impacts from installation of the conveyances in
proximity of the Creek include the following:
-
Install tight sheeting in the trenches.
-
Utilize techniques described in the project-specific erosion and sediment control plan and storm water management plan.
-
Maintain haul roads and street routes.
-
Restore disturbed banks consistent with those required to maintain the flood control channel; areas beyond the flood control portion of the channel will be restored to original or better condition through seeding the banks and placing erosion
control matting on the vegetated banks.
-
Match the existing grade and condition of creek bank. Coordination with the City and upon State concurrence may warrant modification of the existing grade to accommodate the Creekwalk if to be extended south behind Clinton Station.
Trench depths along the conveyance and force main
pipes will range from 15-40 feet below grade. Ground
water will likely be encountered along these
installations based on preliminary geotechnical
evaluations that estimate ground water depths at 6-20
feet. Dewatering of trench excavations from the
infiltration of ground water, as well as storm water,
will be required. During design, analysis of ground
water and pump tests will be performed to assess
ground water quality and to define the pumping rate
and expected volume of water and to establish
appropriate disposal procedures (e.g., filtration or
settling basins followed by discharge to Onondaga
Creek or sanitary sewer); silt-laden water will not be
discharged directly into the Creek.
In summary, no or only minor temporary water quality
impacts and impacts to localized ecosystems will occur
during the construction of bulkheads, diversion
structures, trenching, installation of conveyances and
outfalls, and restoration activities. No permanent
negative impacts, however, are anticipated from these
activities.
RTF construction - mitigation measures.
Due to the presence of fill material at Clinton
Station, it is estimated that 10 feet of fill material
will require excavation to reach an adequate bearing
layer. Underground facilities associated with the RTF
are estimated to be approximately 50 feet below grade
(maximum). Given this excavation depth, ground water
will likely be encountered during excavation. In
addition, storm water will enter the excavation during
storm events. As such, dewatering of the excavation
will be required. During design, analysis of ground
water and pump tests will be performed to assess
ground water quality and to define the pumping rate
and expected volume of water and to establish
appropriate disposal procedures (e.g., filtration or
settling basins followed by discharge to Onondaga
Creek or sanitary sewer); silt-laden water will not be
discharged directly into the Creek. Furthermore, the
use of sheet piling around deep excavations will
reduce the amount of ground water entering the
excavation.
To mitigate potential issues from utilizing Clinton
Station for staging, the following mitigation measures
will be employed:
-
Fuels and lubricants staged onsite will be kept in locked, well-maintained storage areas accessible to only authorized personnel. Storage of such products will not occur within 100 feet of the Creek.
-
Work area and equipment will be secured at the end of the day.
-
As needed, excessive dust/soil on paved areas will be sprayed (wet) and/or swept and unpaved areas will be sprayed and/or mulched. The use of petroleum products or similar products for such use will be prohibited to avoid storm water-related
impacts.
-
Contractors will be required to cover stockpiled soils and trucks hauling soil, sand, and other loose materials.
In conclusion, no significant impacts to the water
quality of the Creek are anticipated from the
construction of the RTF.
Operational mitigation measures.
As previously noted, the existing system currently
stores approximately 74% of the total average annual
wet weather flow. The Clinton CSO Abatement Project
will store an additional 12% of the total average
annual wet weather flow for treatment at Metro with
remaining peak wet weather flows representing 14%
being treated (removal of solids, disinfection,
dechlorination) onsite and discharged to Onondaga
Creek (18 times on an average annual basis). This
represents approximately 118 MG of treated CSO being
discharged to Onondaga Creek.
At this time it is anticipated that the County will
utilize liquid sodium hypochlorite to treat
(disinfect) the CSO discharge. Liquid sodium
metabisulfite will be used to dechlorinate the treated
CSO discharge. This dechlorinating agent reacts with
the chlorine to convert it to a non-toxic liquid
byproduct (EEA 2002). The CSO discharges will be
dechlorinated to achieve compliance with NYSDEC
requirements of not more than 0.1 milligrams per liter
(mg/L) of free chlorine residual. This compares to New
York State regulations for public water supply systems
that require, for systems using chlorine, the free
chlorine disinfection concentration in the water
entering the distribution system cannot be less than
0.2 mg/L for more than four hours (EEA 2003a).
The following summarizes information presented at a CSO Disinfection Workshop that supports that disinfection/dechlorination does not represent a significant water quality impact to the receiving waterway (OCDWEP 2002b).
-
Chlorination/dechlorination has been accepted by the state for the ACJ and is recognized by the USEPA as the best alternative for CSO treatment at this time.
-
NYSDEC's position on chlorination/dechlorination is that it is a safe practice for human contact recreation and sensitive aquatic organisms.
-
It is not likely that chlorination/dechlorination by-products in receiving waters will result in adverse impacts to aquatic ecosystems or to human health.
-
Use of chlorination/dechlorination has proven to be more commercially advanced, more reliable, and more cost effective than alternatives such as treatment with chlorine dioxide, ozone or ultraviolet light.
-
Based on Water Environment Research Foundation (WERF)-sponsored chemical risk assessment, chlorination/dechlorination by-products have a very low tendency to bioconcentrate in aquatic organisms.
-
The effective life of chlorine compounds in the environment is short.
Liquid sodium hypochlorite at a 12-15% concentration
is currently proposed for use in the Clinton Street
CSO Abatement Project. For comparison purposes,
household bleach commonly contains liquid sodium
hypochlorite at a concentration ranging from 6-8%
(OCDWEP 2002b).
In summary, significant impacts to the water quality
and aquatic ecology of Onondaga Creek are not
anticipated from the operation of the RTF and
discharge of treated effluent. The
chlorination/dechlorination process is approved by the
USEPA and NYSDEC for sewage-related uses and does not
pose a significant risk to aquatic animals or to
humans. In addition, the RTF will discharge in
accordance with permit requirements imposed by the
NYSDEC under the SPDES program. The completed project
will result in improved water quality in Onondaga
Creek and Onondaga Lake and an improved ecosystem in
the Creek. No environmental impacts are anticipated
from the normal operation of the Clinton Street CSO
Abatement facilities.
Maintenance mitigation measures.
Mechanical system maintenance and repair and post
event washdown will be required. Mitigation measures
include an automated maintenance scheduling system,
established operating procedures for personnel
dispatch for maintenance and washdown operations,
scheduled deliveries of liquid sodium hypochlorite and
liquid sodium metabisulfite, and adherence to NYSDEC
and Public Employee Occupational Safety and Health Act
(PESHA) regulations for the storage and handling of
chemicals. Based on the above factors, no
environmental impacts are anticipated from the normal
operation of the Clinton Street CSO Abatement
facilities.
Potential impacts.
Flood hazard maps by Federal Emergency Management
Agency indicate that floodprone areas exist within the
project area
(see Figure 2-1)
(FEMA 1986). Permanent
aboveground structures to be constructed within the
100-year flood plain, however, are limited to the RTF
outfall and emergency controlled diversion spillway.
Given the approximate size of the outfall (120-inch
diameter), impacts to floodprone areas are not
expected. The sizing of the emergency controlled
diversion spillway has not been determined at this
time but is not expected to result in significant
long-term impacts to the flood plain.
Mitigation measures.
The Clinton Street CSO Abatement Project will reduce
the potential for flooding given that restoration
activities of the creek channel will improve current
conditions (see Section 4.3). In addition, adherence
to approved erosion and sediment control plans
(including storm water pollution prevention) and the
mitigation measures identified with regard to Creek
disturbances will minimize and/or eliminate potential
floodprone impacts during construction. Additionally,
adherence to appropriate floodzone regulations will be
required. In summary, as presented above, impacts to
areas prone to flooding are not expected from the
implementation of the Clinton Street CSO Abatement
Project.
Potential impacts.
The majority of the project area is devoid of
vegetation (e.g., areas of parking lots, vacant lots,
and roadway rights-of-way). No species of significance
(RTE and species of special concern) or habitats of
significance (federal critical habitats and state
CEAs) are known to exist within the Clinton Street CSO
Abatement Project area. Disruptions will primarily be
limited to the existing urban terrestrial setting in
the vicinity of Onondaga Creek where the conveyances
will be installed. Construction-related impacts will
consist of the removal of a limited amount of
vegetative cover (an estimated 700 ft² of grasses,
shrubs, and saplings along the Creek) and the
temporary displacement of natural habitats. A limited
number of ornamental trees within Clinton Station will
also likely be removed during construction activities.
Mitigation measures.
Previously noted construction-related mitigation
measures (see 4.1 - Geology and 4.3 - Water resources)
will mitigate unnecessary impacts to the terrestrial
community within the project area. These measures
include activities such as:
-
Adhering to an approved sediment and erosion control plan
-
Minimizing the time required for construction activities
-
Minimizing the clearing of vegetation
-
Backfilling excavated trenches to preconstruction contours
-
Avoiding non-construction areas during construction activities
-
Coordinating to the greatest extent possible, work with other planned projects to reduce construction-related impacts
-
Conducting restoration and/or landscaping activities.
It should be noted that prior to work commencing on
the conveyances, the OCDOH will inspect the area for
rodent activity and bait the sewers as part of the
Rodent Control Program (Letteney 2002).
In summary, the temporary loss of vegetation (habitat)
at the RTF site and along the conveyances does not
represent a major impact on terrestrial ecology.
Restoration and landscaping activities will provide
new habitats that are common throughout the downtown
area.
Potential impacts.
As identified throughout this document, the
implementation of the Clinton Street CSO Abatement
Project will result in beneficial improvements to the
water quality of Onondaga Creek to support a more
diverse species of plants and animals (i.e., a
positive impact). The potential for short-term
negative impacts are limited to conveyance
installation activities along/beneath Onondaga Creek
as well as installation of the RTF outfall piping.
Unmitigated, siltation of the Creek could damage
existing habitats and eliminate food resources. In
addition, left unmitigated, impacts to the aquatic
ecology of Onondaga Creek could be expected if the
treated effluent was not required to be dechlorinated
prior to discharge to the Creek.
Mitigation measures.
Approved site-specific construction-related mitigation
measures will reduce siltation impacts to the aquatic
ecology of Onondaga Creek. Sections 4.1 - Geology and
4.3 - Water resources specify the typical mitigation
measures to be employed during the construction of the
project. In addition, the complaint response program
will be operative during the construction of the
project. As such, implementation of the above
identified measures will reduce potentially adverse
impacts to short-term disruptions.
Negative impacts to the aquatic ecology of Onondaga
Creek are not expected as the treated effluent will be
dechlorinated prior to discharge to the Creek. The
dechlorinating agent (sodium metabisulfate) will react
with the chlorine to convert it to a non-toxic liquid
byproduct (EEA 2002). These types of chemicals are
used extensively for disinfection of CSOs throughout
the United States. A CSO demonstration study conducted
by the USEPA in 2001 reported that disinfection using
doses 43% higher than what is proposed by the County
would not provide an aquatic ecology concern (when
followed by dechlorination prior to discharge from the
RTF) (EEA 2002). Given these findings, as well as
those presented in Section 4.3.1 - Water quality,
impacts to the aquatic community with regard to the
discharge of treated effluent are not expected.
Overall improvement of water quality will stimulate
growth and diversification of the aquatic ecology
(Creek and Lake).
There are no agricultural uses within the project
area, as such, there will be no impacts to
agricultural.
|