Midland Avenue RTF and Conveyances: Facility Plan Amendment, June 2003
by Environmental Engineering Associates, LLP for Onondaga County Department of Water Environment Protection
5. Project phasing/implementation schedule
To facilitate the construction of the Midland Avenue
RTF and Conveyances Project, the County requested
approval of re-sequencing the project from the NYSDEC
in March 2000. Based on this re-sequencing, the
following project phases were developed:
-
Tallman Street CSO transmission pipeline
from Tallman Street to a terminus point approximately
60 feet north of Oxford Street (completed December
2000).
-
RTF
-
2.5 MG off-line, underground storage tank.
(Note: Included in Phase Two Project subsequent to
NYSDEC approval of revised phasing plan [see
discussion below] to permit reduction in RTF peak
influent pumping rate from 667 cfs to 330 cfs.)
-
Tallman Street CSO transmission pipeline
from the terminus point of the Phase One Project to
the RTF
-
Midland Avenue CSO transmission pipeline
from the RTF to a point approximately 1,000 feet
upstream of the RTF
-
Entire Bellevue Avenue CSO transmission
pipeline.
-
Midland Avenue CSO transmission pipeline from a
point approximately 1,000 feet upstream of the RTF to
West Newell Street
-
Entire Elmhurst Avenue CSO transmission
pipeline.
The revised phasing plan was subsequently approved by
the NYSDEC in May 2000.
The County completed the construction of the Phase One
Project in December 2000. The Phase One Project was
initiated and completed within the revised minor
milestone dates established for this project phase by
the NYSDEC. Remaining significant milestone dates
presently established for the project by the NYSDEC
and proposed County milestone date revisions are as
follows:
|
Milestone
|
NYSDEC current established date
|
County proposed date revisions
|
Submit phase two engineering design report (minor milestone)
|
Mar 1, 2003
|
Apr 1, 2003
|
Phase two site acquisition (minor milestone)
|
Apr 1, 2003
|
Aug 1, 2003
|
Complete phase two SEQRA documentation (minor milestone)
|
Apr 1, 2003
|
May 1, 2003
|
Submit phase two construction documents (minor milestone)
|
May 15, 2003
|
Sep 1, 2003
|
Commence phase two construction (minor milestone)
|
Oct 1, 2003
|
Mar 1, 2004
|
Complete phase two construction and commence operation of the RTF (minor milestone)
|
Sep 1, 2005
|
Oct 30, 2006
|
Complete construction and begin operation of entire Midland Avenue Conveyances/RTF (major milestone)
|
May 1, 2007
|
May 1, 2008
|
The separate sewer separation projects planned for the
Midland Avenue service area pursuant to the ACJ are
scheduled to be completed by January 1, 2012 (major
milestone).
|