|
Midland Avenue RTF and Conveyances: Facility Plan Amendment, June 2003
by Environmental Engineering Associates, LLP for Onondaga County Department of Water Environment Protection
3. Midland Avenue conveyances/off-line storage
As described in Section 2.5, the recommended CSO
abatement plan for the Midland Avenue RTF and
Conveyances Project includes the installation of a 330
cfs RTF at the Oxford Street location (east of
Onondaga Creek) plus 4.2 MG of in-line conveyances
storage plus 2.5 MG of upstream off-line storage. This
section provides a brief description of operations,
basis of design flows, and preliminary sizing of the
Midland Avenue Conveyances and off-line storage
facility. Section 4 describes in more detail, the
facilities and operation of the Midland Avenue RTF.
3.2 Description of Facilities and Operation
The Midland Avenue Conveyances will consist of CSO
transmission pipelines of varying sizes, located along
Onondaga Creek in the southern section of the City of
Syracuse. The Midland Avenue Conveyances will collect
overflows from the existing CSOs 039, 042, and 044, up
to the one-year design storm, and all combined sewer
flow from CSOs 043, 052, 060 (includes former Overflow
077), 061, 067, 076 [to be permanently closed] and
convey these flows to the Midland Avenue RTF.
The Midland Avenue Conveyances and proposed 2.5
million gallon (MG) off-line, underground storage tank
(to be located directly upstream and adjacent to the
Midland Avenue RTF between Oxford and Blaine Streets)
will also provide flow storage and attenuate the peak
flow to the Midland Avenue RTF. At CSO locations 039,
042, and 044, the existing regulator structures will
be modified to direct overflows up to the one-year
design storm event to the new conveyances and, as
appropriate, the off-line storage facilities.
For CSO locations 043, 052, 060 (includes former
Overflow 077), 061, 067, and 076, the existing outfall
pipelines will be permanently closed and all flows
will be directed via new pipelines to the conveyances
and, as appropriate, the off-line storage facility.
As noted in Section 2.4, overflows from CSOs 038, 040,
041, 045, 046A, 046B, 047, 048, 050, 051, 053, and 054
will not be connected to the Midland Avenue
Conveyances/Off-Line Storage Facility or contribute
flow to the Midland Avenue RTF, as existing combined
sewers in these areas will be separated. This sewer
separation program will prevent future CSO discharges
from these drainage areas.
The Midland Avenue Conveyances/Off-Line Storage
Facility will include the following components:
-
Tallman Street CSO transmission pipeline from
Tallman Street to the Midland Avenue RTF, which will
collect and convey combined sewer flow (up to the
one-year design storm event) from CSO 039
-
Midland Avenue CSO transmission pipeline from
West Newell Street to the Midland Avenue RTF, which
will convey combined sewer flow (up to the one-year
design storm event) from CSO 044 and all combined
sewer flows from CSOs 043, 060 (includes former
Overflow 077), 061, 067, and 076
-
Bellevue Avenue CSO transmission pipeline, which
will convey combined sewer flow (up to the one-year
design storm event) from CSO 042 across Onondaga Creek
to the underground storage tank and the RTF
-
Elmhurst Avenue CSO transmission pipeline or
siphon (to be determined during design), which will
convey all combined sewer flow from CSO 052 across
Onondaga Creek to the Midland Avenue Conveyances and
RTF.
Figure 2-3 presents the recommended plan layout for
the Midland Avenue Conveyances and Off-Line
(Underground) Storage Facility.
In addition to the CSO transmission pipelines and
off-line storage facility, a connection between the
existing Main Interceptor Sewer (MIS) and the Midland
Avenue RTF must be provided to allow a portion of the
flows in the filled MIS upstream of the RTF to
discharge into the RTF. This relief of MIS flows will
provide for downstream conveyance capacity in the MIS
for the RTF underflow (equal to five percent of the
RTF influent pumping/treatment rate).
As noted in Section 2.4, overflows from CSOs 038, 040,
041, 045, 046A, 046B, 047, 048, 050, 051, 053, and 054
will not be connected to the Midland Avenue
Conveyances or contribute flow to the Midland Avenue
RTF, as existing combined sewers in these areas will
be separated. This sewer separation program will
prevent future CSO discharges from these drainage
areas.
The ACJ established two phases for construction of the
Midland Avenue RTF and Conveyances Project. Phase One
included construction of the Conveyances with a
construction commencement date of May 1, 1999 and a
construction completion/begin operation date of May 1,
2004. Phase Two included construction of the RTF with
a construction commencement date of May 1, 2004 and a
construction completion/begin operation date (major
milestone) of May 1, 2007.
In order to comply with the ACJ CSO Construction
Milestone Completion Schedule outlined above and to
better address constructability impact issues
associated with constructing the RTF following
construction of the Conveyances in accordance with the
ACJ, the County requested and NYSDEC subsequently
approved modification to the construction sequencing
of the project to initiate the RTF project prior to
completion of the Conveyances project. A more thorough
discussion of this revised project sequencing is
presented in Section 5.
The Midland Avenue CSO Conveyances have been sized to
accommodate additional pipeline storage and conveyance
capacity for the one-year design storm event.
Specifically, the design flow rates for the Midland
Avenue Conveyances have been developed based on the
following:
-
Transmission to the Midland Avenue RTF of the peak
discharge from the CSOs to remain in the system upon
completion of the Project (i.e., CSOs 039, 042, and
044) up to the one-year design storm event
-
Necessary service area capture component to result
in a minimum 85% capture of the total system-wide
overflow volume
-
Transmission to the Midland Avenue RTF of
additional flows above the one-year design storm event
for the six CSOs scheduled to be closed upon
completion of the Project (i.e., CSOs 043, 052, 060
(includes former Overflow 077), 061, 067, and 076), as
discussed in Section 2.4.
Table 3-1 presents the design flow rates and required
sizing for each segment of the proposed Midland Avenue
Conveyances.
| TABLE 3-1. CONVEYANCE DESIGN FLOW RATES/SIZING |
|
CSO transmission conduits (CSO connected)
|
Diameter (inches)
|
Approximate length (ft)
|
Peak flow (cfs)
|
|
Midland Transmission Conduits
|
|
|
|
|
West Newell Street (CSO 067)/West Brighton Avenue (CSO 076)
|
42
|
1,500
|
26
|
|
West Brighton Avenue (CSO 076)/Elmhurst Avenue (CSO 052)
|
54
|
600
|
42
|
|
Elmhurst Avenue (CSO 052)/West Colvin Street (CSO 060)
|
66
|
850
|
138
|
|
West Colvin Street (CSO 060)/Kirk Avenue
|
120
|
1,850
|
304
|
|
Kirk Avenue/South Avenue (CSO 044)
|
144
|
1,525
|
303
|
|
South Avenue (CSO 044)/Midland Avenue (CSO 043)
|
144
|
1,360
|
430
|
|
Midland Avenue (CSO 043)/Midland RTF
|
144
|
295
|
511
|
|
Tallman Transmission Conduits (039)
|
|
|
|
|
Tallman Street - East
|
54
|
128
|
255
|
|
Tallman Street/Midland RTF
|
84
|
886
|
255
|
|
Bellevue Avenue Transmission Conduits (042)
|
|
|
|
|
Midland Avenue/Midland RTF
|
66
|
200
|
183
|
|
Elmhurst Avenue Transmission Conduits (052)
|
|
|
|
|
Elmhurst Avenue (CSO 052)/Midland Transmission Conduits
|
66
|
180
|
100
|
|
Connection Conduits
|
|
|
|
|
Midland Avenue - East (CSO 043)
|
72
|
35
|
225
|
|
West Castle Street/South Avenue (CSO 044)
|
48
|
50
|
65
|
|
West Colvin Street (CSO 060 and CSO 077)
|
60
|
40
|
185
|
|
Crehange Street/Onondaga Creek (CSO 061)
|
12
|
25
|
8
|
|
West Brighton Avenue/Midland Avenue (CSO 076)
|
54
|
0
|
40
|
|
MIS TAP
|
48
|
40
|
33
|
The proposed 2.5 MG underground, off-line storage
facility will be used in conjunction with the 4.2 MG
of conveyance storage to provide a total storage
volume of 6.7 MG upstream of the RTF. This total
storage volume permits the size of the Midland Avenue
RTF to be reduced from 667 cfs to 330 cfs.
As shown on Figure 2-3, the 2.5 MG underground,
off-line storage facility will be located directly
upstream and adjacent to the Midland Avenue RTF, north
of Blaine Street, on the east side of Onondaga Creek.
Figure 3-1 shows a preliminary plan of the 2.5 MG underground storage facility between Onondaga Creek and the MIS.
Figure 3-2 depicts a preliminary section of the storage facility.
In order to meet the minimum 85 percent volumetric
capture of combined sewage on a system-wide average
annual basis pursuant to the ACJ, it is necessary for
the Midland Avenue Conveyances/Off-Line Storage
Facility and RTF to be operated in a manner that
allows for filling and maximizing storage in the
conveyances, the underground off-line storage tank,
and the influent wet well of the RTF prior to
initiating the RTF influent pumps. This would be
achieved by setting of the RTF influent pump "on"
elevation above the crown of the conveyances at the
RTF.
Flow will enter the RTF influent wet well from the
conveyances. The influent wet well will fill and, as
additional flow enters the wet well, it will back up
into the conveyances. Inflatable dams and/or weir
structures will be installed in the upper reaches of
the conveyances to maximize the conveyances storage
(note: these control structures will be more fully
developed during Phase Three conveyances design).
Conveyances storage will be designed to ensure that no
collector sewer surcharging occurs as a result of
storage operations.
The 2.5 MG underground storage tank will be located at
the downstream end of the proposed Midland Avenue CSO
transmission pipeline at its connection into the RTF
influent wet well. A side overflow weir to the
underground storage tank from the Midland Avenue CSO
transmission pipeline will permit flows above a
pre-established weir elevation (set to maximize
conveyances storage) to enter the storage tank.
As shown in Figure 3-1, the underground storage tank
will be composed of multiple cells to permit sequential
filling of the storage tank. This will permit use of
only those cells necessary for flow storage during
smaller, less intense storm events. Upon achieving the
maximum storage capacity of the conveyances and
underground storage tank (6.7 MG total), the RTF
influent pumps will activate to process additional
flow through the RTF. The RTF influent pump will be
programmed to shut down once the influent flow
elevation recedes to the maximum storage elevation for
the underground storage tank/conveyances system.
At the conclusion of the CSO event, the RTF dewatering
pumps will be used to pump the CSO volume stored in
the RTF, disinfection tank, conveyances and
underground storage tank to the MIS for transport to,
and treatment at, Metro. All stored CSO must be pumped
out in 48 hours or less to comply with accepted
operating procedures and directive by the NYSDEC. A
more detailed description of the separate RTF
operations is presented in Section 4.
In order to demonstrate compliance with the
ACJ-mandated minimum 85 percent volumetric capture of
combined sewage in a system-wide average annual basis,
EEA retained the services of an independent sewer
system modeling consultant, and developer of the
County's computerized Storm Water Management Model
(SWMM), to execute the County's calibrated SWMM using
the various CSO compliance projects that have either
been completed or are proposed for implementation
pursuant to the ACJ. The SWMM executions were run
using a long-term simulation approach based upon over
30 years of precipitation data for the Syracuse
Metropolitan area.
For existing conditions, without implementation of any
CSO abatement projects, the County Sanitary District
trunk and interceptor sewer transports 74% of the
average annual volume of combined sewage collected
within the City of Syracuse collector and combined
sewer system to Metro for treatment. A summary of this
volume capture information is presented in Table 3-2.
|
|
Table 3-2. CSO volume capture table - existing conditions, 1997
|
Upon implementation of the ACJ CSO abatement projects,
as described above, the average annual volume of
combined sewage collected within the combined sewer
system for transport to Metro for treatment is
projected to be in the range of 89% to 91%. A summary
of this volume capture information is presented in
Table 3-3. These data indicate that the
fully-implemented ACJ CSO compliance projects will
satisfy the minimum 85 percent capture requirements of
the ACJ.
|
|
Table 3-3. CSO volume capture table - future conditions, treatment at Metro
|
Table 3-4 presents the CSO volume capture information
for the combined treatment of CSO both at Metro and at
the completed/proposed ACJ compliance projects, which
is projected to be approximately 96%.
|
|
Table 3-4. CSO volume capture table - future conditions, treatment at Metro and RTFs
|
Appendix 8, prepared by Brown & Caldwell (formerly Moffa & Associates), explains the evolution of the capture tables from 1996 to present.
Based on the most recent modeling and resultant
updated volume capture tables, the Midland Project
when completed will achieve a total capture with
treatment at Metro of 92%, based on the one-year storm
and 30-year record of precipitation. Thus, only 8% of
the total average annual CSO flow within the Midland
CSO service area will require regional treatment,
disinfection, dechlorination, and discharge to
Onondaga Creek.
|