Midland Ave Regional Treatment Facility & ConveyancesFacility Plan, Jan 2003
by Environmental Engineering Associates, LLP for Onondaga County Department of Water Environment Protection
5. Project phasing/implementation schedule
To facilitate the construction of the Midland Avenue
RTF and Conveyances project, the County requested
approval of re-sequencing the project from the NYSDEC
in March 2000. Based on this re-sequencing, the
following project phases can be described as follows:
Phase One Project, including:
-
Tallman Street CSO transmission pipeline from Tallman
Street to a terminus point approximately 60 feet north
of Oxford Street (completed December 2000).
Phase Two Project, including:
included in Phase Two Project subsequent to NYSDEC
approval of revised phasing plan [see discussion
below] to permit reduction in RTF peak influent
pumping rate from 667 cfs to 330 cfs)
the terminus point of the Phase One Project to the
RTF;
the RTF to a point approximately 1,000 feet upstream
of the RTF; and
Phase Three Project, including:
Midland Avenue CSO transmission pipeline from a point
approximately 1,000 feet upstream of the RTF to West
Newell Street; and
Entire Elmhurst Avenue CSO transmission pipeline.
The revised phasing plan was subsequently approved by
the NYSDEC in May 2000.
The County completed the construction of the Phase One
Project in December 2000. The Phase One Project was
initiated and completed within the revised minor
milestone dates established for this project phase by
the NYSDEC. Remaining significant milestone dates
presently established for the project by the NYSDEC
are as follows:
|
Milestone
|
Date
|
|
Submit Phase Two Engineering Report (minor milestone)
|
Mar 1, 2003
|
|
Phase Two Site Acquisition (minor milestone)
|
Apr 1, 2003
|
|
Complete Phase Two SEQRA Documentation (minor milestone)
|
Apr 1, 2003
|
|
Submit Phase Two Construction Documents (minor milestone)
|
May 15, 2003
|
|
Commence Phase Two Construction (minor milestone)
|
Oct 1, 2003
|
|
Complete Phase Two Construction (minor milestone)
|
Sep 1, 2005*
|
|
Complete Construction and Begin Operation of Midland Avenue Conveyances/RTF CSO Control System, including Phase One, Phase Two , and Phase Three (major milestone)
|
May 1, 2007
|
|
* Milestone date requires extension to April 1, 2006 to accommodate new Commence Phase Two Construction date of October 1, 2003 (issued Jan 14, 2003).
|
The separate sewer separation projects planned for the
Midland Avenue service area pursuant to the ACJ are
scheduled to be completed by January 1, 2012 (major
milestone).
|