Go to home page
Go to home page

Midland Ave Regional Treatment Facility & Conveyances—Facility Plan, Jan 2003
by Environmental Engineering Associates, LLP
for Onondaga County Department of Water Environment Protection

3. Midland Avenue conveyances/off-line storage


 

This section provides a brief description, basis of design flows, and preliminary sizing of the Midland Avenue conveyances and off-line storage facility.

3.1 Description of facilities and operation

The Midland Avenue Conveyances will consist of CSO transmission pipelines of varying sizes, located along Onondaga Creek in the southern section of the City of Syracuse. The Midland Avenue Conveyances will collect overflows from the existing CSOs 039, 042, and 044, up to the one-year design storm, and all combined sewer flow from CSOs 043, 052, 060 (includes former Overflow 077), 061,067 (see Newell Street CSO discussions in Section 2.4), 076 [to be permanently closed] and convey these flows to the Midland Avenue RTF, to be located near Oxford Street. The Midland Avenue Conveyances and proposed 2.5 million gallon (MG) off-line, underground storage tank (to be located northwest of the intersection of Midland Avenue and West Castle Street) will also provide flow storage and attenuate the peak flow to the Midland Avenue RTF. At CSO locations 039, 042, and 044, the existing regulator structures will be modified to direct overflows up to the one-year design storm event to the new Conveyance pipelines and, as appropriate, the off-line storage facilities. For CSO locations 043, 052, 060 (includes former Overflow 077), 061, 067, and 076, the existing regulator structures will be permanently closed and all flows will be directed to the Conveyances pipelines and, as appropriate, the off-line storage facility.

The Midland Avenue Conveyances/Off-Line Storage Facility will include the following components:

    from Tallman Street to the Midland Avenue RTF, which will collect and convey combined sewer flow (up to the one-year design storm event) from CSO 039; from West Newell Street to the Midland Avenue RTF, which will convey combined sewer flow (up to the one-year design storm event) from CSO 044 and all combined sewer flows from CSOs 043, 060 (includes former Overflow 077), 061, 067, and 076. which will convey combined sewer flow (up to the one-year design storm event) from CSO 042 across Onondaga Creek to the RTF; and siphon (to be determined during design), which will convey all combined sewer flow from CSO 052 across Onondaga Creek to the Midland Avenue Conveyances and RTF.

Figure 3-1 presents the conceptual plan layout for the Midland Avenue Conveyances and Off-Line Storage Facility. This conceptual plan will be further developed during final design.

In addition to the CSO transmission pipelines and off-line storage facility, a connection between the existing Main Interceptor Sewer (MIS) and the Midland Avenue RTF must be provided to allow a portion of the flows in the filled MIS upstream of the RTF to discharge into the RTF. This relief of MIS flows will provide for downstream conveyance capacity in the MIS for the RTF underflow (equal to five percent of the RTF influent pumping/treatment rate).

As noted in Section 1.3, overflows from CSOs 038, 040, 041, 045, 046A, 046B, 047, 048, 050, 051, 053, and 054 will not be connected to the Midland Avenue Conveyances or contribute flow to the Midland Avenue RTF, as existing combined sewers in these areas will be separated. Under this sewer separation program, it is generally anticipated that new sanitary sewers will be constructed in these drainage basins and existing combined sewers will be converted to storm sewers, with the existing CSO outfall converted to a storm sewer outfall. Alternatively, sub-basin storm only discharges may be directed to an adjacent sub-basin to permit the closure of the existing CSO outfall. This sewer separation program will prevent future CSO discharges from these drainage areas.

As described previously in Section 1.5, the ACJ established two phases for construction of the Midland Avenue RTF and Conveyances project. Phase One included construction of the Conveyances with a construction commencement date of May 1, 1999 and a construction completion/begin operation date of May 1, 2004. Phase Two included construction of the RTF with a construction commencement date of May 1, 2004 and a construction completion/begin operation date (major milestone) of May 1, 2007.

In order to comply with the ACJ CSO Construction Milestone Completion Schedule outlined above and to better address construction impact issues associated with constructing the RTF following construction of the Conveyances in accordance with the ACJ, the County, in conjunction with NYSDEC, requested modification to the construction sequencing of the project to initiate the RTF project prior to completion of the Conveyances project. A more thorough discussion of this revised project sequencing is presented in Section 5.

3.2 Design flow rates/conveyance sizing

Based on the CSO conveyance and RTF capacity determinations resulting from the RTF Hydraulic Evaluations described in Section 2.2, the Midland Avenue CSO Conveyances have been sized to accommodate additional pipeline storage and conveyance capacity for the one-year design storm event. Specifically, the design flow rates for the Midland Avenue Conveyances have been developed based on the following:

  1. Transmission to the Midland Avenue RTF of the peak discharge from the CSOs to remain in the system upon completion of the Project (i.e., CSOs 039, 042, and 044) up to the one-year design storm event;

  2.  
  3. Necessary service area capture component to result in a minimum 85% capture of the total system-wide overflow volume; and

  4.  
  5. Transmission to the Midland Avenue RTF of additional flows above the one-year design storm event for the six CSOs scheduled to be closed upon completion of the Project (i.e., CSOs 043, 052, 060 (includes former Overflow 077), 061, 067, and 076), as discussed in Sections 2.2 and 2.3.

Table 3-1 presents the design flow rates and required sizing for each segment of the proposed Midland Avenue Conveyances.
 
TABLE 3-1. CONVEYANCE DESIGN FLOW RATES / SIZING
CSO transmission conduits (CSO connected) Diameter (inches) Approx length (ft) Peak flow (cfs)
Midland Transmission Conduits      
W. Newell Street (CSO 067)/W. Brighton Avenue (CSO 076) 36 1,020 26
W. Brighton Avenue (CSO 076)/Elmhurst Avenue (CSO 052) 54 600 42
Elmhurst Avenue (CSO 052)/W. Colvin (CSO 060) 66 850 138
W. Colvin (CSO 060)/Kirk Avenue 120 1,850 304
Kirk Avenue/South Avenue (CSO 044) 144 1,525 303
South Avenue (CSO 044)/Midland Avenue (CSO 043) 144 1,360 430
Midland Avenue (CSO 043)/Midland RTF 144 295 511
       
Tallman Transmission Conduits (039)      
Tallman Street East 54 128 255
Tallman Street/Midland RTF 84 886 255
       
Bellevue Avenue Transmission Conduits (042)      
Midland Avenue/Midland RTF 66 200 183
       
Elmhurst Avenue Transmission Conduits (052)      
Elmhurst Avenue (CSO 052)/Midland Trans. Conduits 66 180 100
       
Connection Conduits      
Midland Avenue East (CSO 043) 72 35 225
West Castle/South Avenue (CSO 044) 48 50 65
West Colvin (CSO 060 and CSO 077) 60 40 185
Crehange/Onondaga (CSO 061) 12 25 8
Brighton/Midland Avenue (CSO 076) 54 0 40
MIS TAP 48 40 33

3.3 Off-line storage facility

As noted in Appendix E, Midland RTF Size Evaluations, a total of 6.7 MG of in-line/off-line storage (2.5 MG additional in-line/off-line storage plus 4.2 MG storage in Midland Avenue Conveyances) is necessary to reduce the peak influent flow rate of the RTF to 330 cfs to achieve ACJ compliance for the Midland Avenue service area. During preliminary planning for the additional 2.5 MG in-line/off-line storage, a parallel 12-foot diameter pipeline, 900 feet in length (0.8 MG storage) plus a 1.7 MG off-line underground storage tank were considered as options to achieve the total required storage of 2.5 MG. Further review of the available land area for locating the additional 2.5 MG of upstream storage (northwest intersection of Midland Avenue and West Castle Street on the east side of Onondaga Creek) revealed that construction of the parallel 12-foot diameter pipeline would potentially interfere with the stability of the existing Main Interceptor Sewer (MIS) that parallels the eastern edge of Onondaga Creek in close proximity to the proposed parallel pipeline. Therefore, it has been determined that a single, 2.5 MG underground storage tank in the Midland Avenue/West Castle Street location provides the most practical and cost-effective upstream, off-line storage option for use in conjunction with 330 cfs RTF.

Figure 3-1 depicts the conceptual plan location for the 2.5 MG upstream, off-line storage facility. Figure 3-2 and Figure 3-3 depict a conceptual plan and section for the 2.5 MG off-line storage facility.


Home |  Info  | M / WBE  | Projects  | New  | Links  | Contact  | Glossary  | Site map
 
Susan Miller, Project Deputy Director
Phone 315-435-2260   Fax 315-435-5023
 Onondaga County Dept of Water Environment Protection