|
Midland Ave Regional Treatment Facility & ConveyancesFacility Plan, Jan 2003
by Environmental Engineering Associates, LLP for Onondaga County Department of Water Environment Protection
2. Evaluation of Midland Avenue RTF and conveyances flows
The following sections summarize evaluations conducted
to develop design flow requirements for the Midland
Avenue RTF and Conveyances project.
Pursuant to the ACJ, the County was required to
conduct sewer separation evaluations to identify where
sewer separation may be a more cost-effective
alternative to consolidation of CSO flows for
treatment at the Midland Avenue RTF. Specifically, the
ACJ states:
A cost evaluation of sewer separation projects
proposed by the city, or by any party to this
agreement and order, shall be implemented by the
county. When doing this evaluation, the cost of
separation shall be compared with the savings realized
from the sum total of: a.) reduced CSO abatement
project costs; b.) reduced operating costs at the
Metro sewage treatment plant; and any other savings as
applicable; and achieves comparable water quality
benefits. The County is obligated to construct only
those sewer separation projects for which the
anticipated savings exceed expected costs.
To fulfill this requirement, a detailed evaluation of
potential opportunities for sewer separation of the
nine CSOs tributary to the proposed Midland Avenue RTF
and Conveyances not scheduled for sewer separation or
previously permanently closed (i.e., CSOs 039, 042,
043, 044, 052, 060 [includes former Overflow 077],
061, and 076) was conducted.
Appendix A
presents a Sewer Separation Evaluation memorandum (dated October 15, 1998) detailing this evaluation.
This analysis concluded that with the exception of the
minor Glenwood area sewer separation project described
in Appendix A, in comparing the costs of conveying CSO
flows for storage and/or treatment at the Midland
Avenue RTF, there are no cost benefits to separating
additional CSOs within the Midland Avenue service
area.
Subsequent to the preparation of the Sewer Separation
Evaluation memorandum presented in Appendix A, the
County had a separate analysis of up-to-date sewer
separation costs completed by its ACJ Oversight
Program Manager, CDM/C&S Joint Venture. This analysis,
presented in a CDM/C&S memorandum to
the County dated April 30, 2001 (Issued September 10,
2001), established recommended unit costs for sewer
separation for both residential areas and commercial
areas in the metropolitan Syracuse area.
See Appendix B.
These recommended unit costs for sewer separation were
identified to be 70% (residential areas) to 215%
(commercial areas) higher than the unit cost for sewer
separation (dollars per linear foot) used for cost
comparisons in the October 1998 Sewer Separation
Evaluation memorandum. This information further
supports the conclusion of the October 1998 Sewer
Separation Evaluation that in comparing the costs of
conveying CSO flows for storage and/or treatment at
the Midland Avenue RTF, there are no cost benefits to
separating additional CSOs within the Midland Avenue
service area.
As presented in the "Combined Sewer Overflow
Facilities Plan" (Moffa and Associates and Blasland
and Bouck Engineers, PC, February 28, 1991), the
Midland Avenue RTF was preliminarily sized to pump,
treat, and convey up to 650 cubic feet per second
(cfs) of tributary area CSO. This flow rate was based
on flow projection models and was selected as the flow
rate which resulted in no overflows in the Midland
Avenue tributary area up to the one-year design storm
event. Due to the large size of the Midland Avenue
facilities, a review of the previous flow projections
was conducted for the purpose of updating previous
flow projection models and potentially minimizing
facility costs. To complete this hydraulic evaluation,
previous sewer system models were verified and updated
to incorporate the best available information
regarding recent sewer rehabilitation and
replacements, additional CSO storage requirements,
field observations of the existing sewer system, and
other conditions that may affect the flow projections
for the project.
Appendix C
presents a summary memorandum detailing the verification and updating of the previous flow projection models as described above.
Based upon these updated flow projection models, the
Midland Avenue RTF peak influent pumping rate was
determined to be 500 cfs, rather than the previously
estimated peak influent pumping rate of 650 cfs. This
decrease in the influent pumping rate was primarily
attributed to a more accurate predicting flow
projection model following completion of the model
upgrade noted above.
Following completion of the Sewer Separation
Evaluation described in Section 2.1, the County
elected to undertake an additional evaluation of the
potential for the closure of CSOs tributary to the
Midland Avenue RTF and Conveyances project not
currently scheduled for sewer separation or
permanently closed (i.e., CSOs 039, 042, 043, 044,
052, 060 (includes former Overflow 077), 061, and
076). Specifically, this evaluation was conducted to
determine the facility modifications that would result
if one or more of the remaining nine CSOs tributary to
the proposed Midland Avenue RTF and Conveyances were
closed to prevent future discharges from these CSOs.
Appendix D
presents the CSO Closure Evaluation memorandum detailing the results of this evaluation.
Based on review of the results of the CSO Closure
Evaluation, the County has determined that it is
feasible to permanently close the following CSOs as
part of this project: 043, 052, 060 (includes former
Overflow 077), 061, and 076. The RTF hydraulic
evaluation discussed below includes the impacts of
facility design flows necessitated by the permanent
closure of these existing CSOs.
To evaluate the effects of closing the CSOs identified
for closure as described above on the RTF influent
pumping rates, a separate analysis of the RTF influent
pumping rate was conducted using the updated flow
projection models.
Appendix E
presents a memorandum summarizing the results of this hydraulic evaluation.
The conclusion of this evaluation was that, by
maximizing storage in the conveyances, the minimum RTF
pumping/treatment flow rate that would be required
without overflows occurring at the remaining three
tributary area CSOs (i.e., 039, 042, and 044) or the
RTF emergency controlled diversion up to the one-year
design storm event, or that would not result in
elevated hydraulic grade lines upstream of the
existing CSOs scheduled to be closed (i.e., 043, 052,
060 [includes former Overflow 077], 061, and 076), was
667 cfs.
The 667 cfs RTF influent pumping rate was also
demonstrated to achieve compliance with the
ACJ-required elimination or capture for treatment of
not less than 85 percent by volume of combined sewage
collected in the overall combined sewer system during
precipitation events on a system-wide average annual
basis. The RTF Hydraulic Evaluation memorandum in
Appendix E
summarizes and details this analysis.
Subsequent to the preliminary design development for
the aforementioned 667 cfs Midland Avenue RTF, a
series of mediation meetings were held with
representatives from the County, the City of Syracuse,
NYSDEC, the Partnership for Onondaga Creek, Atlantic
States Legal Foundation, and the Onondaga Nation to
discuss alternatives to the 667 cfs RTF. Non-County
mediation representatives expressed concern regarding
the size of the proposed above-ground structure for
the 667 cfs RTF and the issue of
chlorinated/dechlorinated discharges from the RTF.
Complete underground storage of the Midland Avenue
CSOs with subsequent conveyance and treatment at Metro
was identified as the preferred CSO Abatement approach
for the non-County mediation participants.
Through multiple meetings and discussions with the
mediation representatives, various reduced size RTF
and large underground storage alternatives were
evaluated. The results of these evaluations
demonstrated that the three most viable alternatives
for the Midland Avenue CSOs were as follows:
-
RTF with 667 cfs peak influent design pumping rate plus large diameter upstream conveyance providing 4.2 million gallons (MG) of upstream storage (total system storage equals 7.6 MG).
-
RTF with 330 cfs peak influent pumping rate plus large diameter upstream conveyances (4.2 MG) and off-line underground storage tank (2.5 MG) providing 6.7 MG of upstream storage.
See Midland RTF Size Evaluations memorandum,
Appendix F.
Total system storage equals 8.45 MG.
-
Large (12 MG) underground storage tank (with no RTF) plus large diameter upstream conveyances providing 4.2 MG of storage upstream of the 12 MG underground storage tank plus sewer separation for CSO tributary areas
076 and 067 (total system storage equals 16.2 MG).
Capital, operation and maintenance (O&M) and 25-year
present worth costs were developed for the above three
alternatives. These costs are presented in Table 2-1.
| Table 2-1. MOST VIABLE ALTERNATIVES ESTIMATED COSTS |
|
Alternative
|
Estimated project cost
|
Estimated annual O&M cost
|
Estimated 25-year present worth
|
|
1. 667 cfs RTF (plus 4.2 MG upstream storage)
|
$54,780,000
|
$839,000
|
$71,300,000
|
|
2. 330 cfs RTF (plus 6.7 MG upstream storage)
|
$54,420,000
|
$712,000
|
$68,000,000
|
|
3. 12 MG underground storage tank (plus additional 4.2 MG upstream storage)
|
$79,220,000
|
$394,000
|
$87,400,000
|
Notes: 1. Costs based on Dec '02 dollars (ENRCCI=6563). 2. 25-year present worth based on 5% discount rate; rounded to nearest $100,000.
|
Based upon the cost data presented in Table 2-1, the
County has determined that Alternative 2 - 330 cfs RTF
plus 6.7 MG of upstream storage (total system storage
equals 8.45 MG) is the preferred approach to abating
the Midland Avenue CSOs. In addition to having the
lowest estimated project cost and 25-year present
worth, this alternative provides a smaller above grade
structure for the RTF due to its reduced size and
maximizes the cost-effective use of upstream,
underground storage, while decreasing the number of
treated discharges.
Based upon the above series of evaluations, the
following presents the resultant disposition of the
existing CSOs in the Midland Avenue tributary service
area upon completion of the Midland Avenue RTF and
Conveyances Project (Project).
CSOs 039, 042, 044 - Active Overflow Diversions;
to activate only above one-year design storm event
upon completion of Project (three total).
CSOs 043, 052, 060 (includes former Overflow 077), 061, 076 - Active Overflow Diversions;
to be closed upon completion of Project. (Note: as
part of these facilities planning efforts, the County
completed a separate evaluation of eliminating the
Newell Street (CSO 067) RTF and conveying the Newell
Street CSO service area flows to the Midland Avenue
CSO transmission pipeline and RTF.
A memorandum summarizing the results of this evaluation is presented in
Appendix G.
Based upon the results of this evaluation, it has been determined to be
cost-effective to convey Newell Street CSO (067) to
the Midland Avenue CSO transmission pipeline and
subsequently the Midland Avenue RTF for treatment.
Therefore , CSO 067 will be added as an Active
Overflow Diversion; to be closed upon completion of
this project, as part of the Midland Avenue Regional
Treatment Facilities and Conveyances Project) (six
total).
CSOs 038, 040, 041, 045, 046A, 046B, 047, 048, 050, 051, 053, 054 - Active Overflow Diversions;
to be converted to storm only discharge or closed by
sewer separation upon completion of Project (12
total).
Figure 2-1 graphically depicts and shows the location of the overflow elimination plan described above.
In order to meet the minimum 85 percent volumetric
capture of combined sewage on a system-wide average
annual basis pursuant to the ACJ, it is necessary for
the Midland Avenue RTF and Conveyances to be operated
in a manner that allows for filling and maximizing
storage in the Conveyances, the underground storage
tank, and the influent wet well of the RTF prior to
initiating the RTF influent pumps. This would be
achieved through the setting of the RTF influent pump
"on" elevation above the crown of the Conveyances at
the RTF.
Additionally, to maximize storage in the remote, upper
end of the Midland Avenue CSO transmission pipeline, a
weir structure will be required to fully optimize
available storage. Preliminarily, this flow control
structure has been modeled as a bottom outlet orifice
device to limit flow through the structure to 100 cfs
until water levels upstream of the structure reach the
crown of the Conveyance pipeline. After the flows
reach the crown of the Conveyances, the flow control
structure would automatically increase flow capacity
to the downstream Conveyances to relieve upstream
surcharge.
In order to maximize storage in the Conveyance
pipelines, the RTF influent pumps would operate until
such time as the influent flows recede below the crown
of the Conveyances at the RTF. Subsequent to this RTF
influent pump shutdown, CSO volume stored in the RTF
and Conveyances would be pumped to the MIS for
transport to and treatment at Metro.
|