Midland Ave Regional Treatment Facility & ConveyancesFacility Plan, Jan 2003
by Environmental Engineering Associates, LLP for Onondaga County Department of Water Environment Protection
Introduction
Please note:
This facility plan was amended in June 2003. Click
below for the current document:
Midland Avenue RTF and Conveyances: Facility Plan Amendment, June 2003
This Facilities Plan report has been prepared to
summarize the basis of design and preliminary planning
for the overall Midland Avenue RTF and Conveyances
project. Engineering Reports will be prepared for
separate phases of the overall project to describe
each phase in greater detail, clarify project scope
and issues, and present the basis of design to be used
in preparation of Contract Documents for the
construction of the projects.
1. Project background
2. Evaluation of Midland Avenue RTF and conveyances flows
3. Midland Avenue conveyances/off-line storage
4. Midland Avenue RTF
5. Project phasing/implementation schedule
Appendices
|